What are the Chiefs building in Kansas?
The Kansas City Chiefs are moving to a new stadium in Kansas City, Kansas, near the interchange of I-70 and I-435 in Wyandotte County (ENR), on land near Kansas Speedway in the Village West area (Kansas Reflector). The Chiefs say the $3 billion stadium will be fully enclosed under a translucent ETFE roof, with more than 400,000 square feet of clear panels right over the field. It holds about 70,000 fans (KWCH) and is set to open in 2031.
The state of Kansas, through the Kansas Sports Facilities Authority, will own the stadium and parking and lease them to the Chiefs for $7 million a year (KCUR). The Chiefs and Hunt Midwest formed Two-Point Development to build a district around the stadium (Kansas City Chiefs).
Is the Chiefs' stadium a $3 billion contract?
No. $3 billion is the Chiefs' projected stadium budget. The value of the Clark | AECOM contract has not been disclosed. The stadium is part of a $4.5 billion plan that also covers a $300 million practice facility and headquarters in Olathe and $1.2 billion of private real estate around both (Kansas City Chiefs).
Kansas picked a finance team in January 2026 for $1.8 billion of STAR bonds, sales tax and revenue bonds (The Bond Buyer); that is 60% of the $3 billion budget. Wyandotte County pledged up to $450 million in future local sales tax (The Beacon).
Where does the Chiefs' Kansas stadium stand now?
It is in preconstruction. On Nov. 9, 2026 Kansas and Wyandotte County settled the county's lawsuit over the stadium law, and the agreement opened a path for the Kansas City Board of Public Utilities to partner with Evergy on the stadium's power (KCUR).
On Nov. 11 the Chiefs named Clark | AECOM the construction team. On Nov. 18 the Kansas Sports Facilities Authority held its first meeting in Topeka, and the Chiefs released four new MANICA renderings, one of them set up for an NCAA Final Four (KMBC; KSHB 41). We found no report of a vote, a contract or a new firm at that meeting.
The stadium has no building permit, and none is expected: KCUR reports the authority-owned stadium and parking are not subject to local zoning or building codes. Sitework is set to begin in 2027 (Kansas City Chiefs).
Who gets what on the Chiefs' stadium?
No one has published a trade-by-trade split of the stadium's cost, so we don't make one up. The Chiefs say Clark | AECOM will lead the strategy and schedule for competitively bidding the work, find and vet subcontractors and suppliers, and advise on materials during design. No subcontractor, engineer or local firm has been named in public yet.
Which firms are on the Chiefs' stadium?
Clark Construction Group and AECOM, through AECOM Hunt, are the construction team as Clark | AECOM (Kansas City Chiefs; ENR). MANICA, of Kansas City, Kansas, is the lead design architect, HNTB is architect of record, and CAA ICON is the owner's representative. Hunt Midwest is the Chiefs' partner in Two-Point Development, the district's master developer. The Kansas City Board of Public Utilities and Evergy have a path to power the stadium, not a signed deal.
Five more firms work on the money and the approvals, not the construction: Gilmore & Bell, Kutak Rock and PFM on the STAR bonds (The Bond Buyer), Canyon Research Southwest on the state's economic impact study, and Econsult Solutions on the Chiefs' own. They come last on the list. 13 firms in all are on the list below.
How do the ways into the Chiefs' Kansas stadium compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Chiefs' Kansas stadium | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the construction team and the designers; the finance firms buy no construction |
| The construction team's bidding | Clark | AECOM leads the strategy and schedule for competitively bidding the work | Subcontractors and suppliers who want to bid | A place on the bid list before sitework begins in 2027 | No bid package or bid date is public yet |
Who should go after the Chiefs' Kansas stadium, and who shouldn't?
| Subcontractors and suppliers in every stadium trade | Clark | AECOM will lead the competitive bidding and line up subcontractors and suppliers before sitework in 2027. |
|---|
| Roofing, glazing and facade firms | The design calls for more than 400,000 square feet of translucent ETFE roof panels over the field. |
|---|
| Electrical and utility suppliers | BPU and Evergy have a path to power the stadium, not a signed deal yet. |
|---|
| Firms that want an open bid this month | This isn't the job yet: no bid package or bid date is public, and the bond lawyers and economists on the list buy no construction. |
|---|
What should you do next on the Chiefs' Kansas stadium?
- Call Clark | AECOM's offices this week and ask how to get on the bid list for the Chiefs' Kansas stadium.
- If you sell into design, call MANICA and HNTB while the design is still being refined.
Questions people ask about the Chiefs' Kansas stadium
How much is the Chiefs' new stadium in Kansas?
The Chiefs put the stadium at $3 billion, a projected budget, not a signed contract. It is part of a $4.5 billion plan that adds a $300 million practice facility and headquarters in Olathe and $1.2 billion of private development around both.
Who is building the Chiefs' stadium in Kansas?
Clark | AECOM, a joint venture of Clark Construction Group and AECOM, named by the Chiefs on Nov. 11, 2026. 13 firms are named in all, listed above.
Who designed the Chiefs' new stadium?
MANICA, a Kansas City, Kansas firm, is the lead design architect, and HNTB is architect of record. CAA ICON is the owner's representative.
Where will the Chiefs' new stadium be?
In Kansas City, Kansas (Wyandotte County), near the I-70 and I-435 interchange, on land near Kansas Speedway in the Village West area. No street address has been published.
When will the Chiefs' Kansas stadium open?
The Chiefs target the 2031 NFL season. Sitework is set to begin in 2027.
How do subcontractors get on the Chiefs' stadium?
Through the construction team. The Chiefs say Clark | AECOM will lead the strategy and schedule for competitively bidding the work. No bid package or bid date is public yet.
How is the Chiefs' stadium being paid for?
Kansas lined up $1.8 billion of STAR bonds (sales tax and revenue bonds) (The Bond Buyer), 60% of the $3 billion budget. Wyandotte County pledged up to $450 million of future local sales tax (The Beacon). The state will own the stadium and lease it to the Chiefs for $7 million a year (KCUR).
Does the Chiefs' stadium have a building permit?
No. KCUR reports the stadium and parking, owned by the state's sports authority, are not subject to local zoning or building codes. We found no Kansas City, Kansas permit for the stadium.
What happened at the Kansas Sports Facilities Authority meeting on Nov. 18?
The authority held its first meeting in Topeka, the Chiefs briefed the board, and the team released four new MANICA renderings, one set up for an NCAA Final Four (KMBC; KSHB 41). We found no report of a vote, a contract or a new firm at that meeting.
Are the bond lawyers and economists building the stadium?
No. Gilmore & Bell, Kutak Rock and PFM work on the STAR bonds, and Canyon Research Southwest and Econsult Solutions wrote economic impact studies. They are on the financing and approval, not buyers of construction work.
How we built this list
We read the Chiefs' releases on the stadium (June 30, July 22, Aug. 31 and Nov. 11, 2026), HNTB's release, ENR, KCUR, The Beacon, The Bond Buyer, KWCH, KMBC, KSHB, the Kansas Reflector and the Kansas Department of Commerce's economic impact study, and kept each firm one of them ties to this stadium, the district around it or its financing (read Nov. 18, 2026). The stadium has no building permit: KCUR reports the authority-owned stadium is not subject to local zoning or building codes, and ATI holds no Wyandotte County permit that names it. No subcontractor, engineer, surveyor or local firm is named in any public record we found, and no state-county agreement signing, contract or new firm was reported from the Nov. 18 meeting. The five finance and study consultants work on the bonds and the approvals, not construction, and come after the construction and design firms. Left out: the firms on the separate Olathe practice facility (Populous, Burns & McDonnell), the bond underwriters (Bank of America, Wells Fargo), and a structural engineer we saw only in a garbled search snippet. There is no trade split: no one has published one for this stadium. Phones are each firm's own office line, except MANICA's (listed by Architect Magazine; the firm's own site did not confirm it), Canyon Research Southwest's (from its report letterhead) and Evergy's (its customer line; it lists no corporate switchboard). We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- Kansas City Chiefs: Chiefs name Clark | AECOM to construction team for new stadium (Nov. 11, 2026)
- ENR: Kansas City Chiefs add JV to construction team (Nov. 2026)
- KMBC: Chiefs share new stadium renderings (Nov. 18, 2026)
- KWCH: Chiefs unveil new renderings of planned stadium (Nov. 18, 2026)
- KSHB 41: Chiefs release new renderings for Kansas City, Kansas stadium (Nov. 18, 2026)
- KCUR: Wyandotte County and Kansas reach agreement over Chiefs stadium (Nov. 9, 2026)
- The Beacon: Wyandotte County looks at giving back some local leverage in Chiefs stadium deal (Nov. 5, 2026)
- Kansas City Chiefs and Hunt Midwest announce Two-Point Development (Aug. 31, 2026)
- Kansas City Chiefs: Legacy reimagined, renderings for new stadium set to open in 2031 (July 22, 2026)
- HNTB: HNTB to help deliver the next home of the Kansas City Chiefs as architect of record (July 22, 2026)
- Kansas City Chiefs: updated economic impact projections of the $4.5 billion capital investment (June 30, 2026)
- The Bond Buyer: Kansas assembles financing team for Chiefs stadium bonds (Jan. 8, 2026)
- Kansas Department of Commerce: Economic Impact Report of NFL STAR Bond Project, by Canyon Research Southwest (Dec. 2025)
- ENR: NFL's Chiefs move to Kansas, sets $4B stadium construction program (Dec. 2025)
- Kansas Reflector: Chiefs moving to Kansas with plan for domed stadium and training facility (Dec. 22, 2025)