What is Meta building in Tulsa?
On April 21, 2026, Meta said it is the company behind Project Anthem, an AI data center at Fair Oaks Innovation Park in east Tulsa, Oklahoma. The site sits between 11th Street and the Creek Turnpike. The Oklahoma Department of Commerce says it will span more than 2 million sq ft, and the Tulsa Flyer reports a 340-acre site.
Meta expects over 1,000 construction workers on site at the peak and about 100 jobs once the data center opens. The Tulsa Flyer reports it is expected to open in 2028.
The city's site plan permit names Atmoss, LLC as the developer. Meta says Project Anthem is its data center, the gate sign reads 'Project Anthem 21304 East 11th St.', and one of the city's permits is for a temporary power meter on the 'Meta Trailer'. We found no filing that says more about how Atmoss and Meta are tied.
How much is Meta's Tulsa data center?
Meta says the Tulsa data center will be an investment of more than $1 billion once done. That is Meta's total, not a construction contract or bid. PartnerTulsa's project plan put the construction cost at about $800 million (Tulsa Flyer), and the Oklahoma Department of Commerce says Meta is putting more than $25 million into local roads and water lines.
The City of Tulsa's 30 issued permits that state a value declare about $139.4 million (our sum, not counting four foundation re-filings that repeat the two big buildings' values). Building 1's core and shell is $52,181,280 for 411,200 sq ft, and Building 2 is $44,382,006 for 349,740 sq ft, both issued Sept. 9, 2026. Two substations are $7,580,100 each, the warehouse $6,400,202 and the administration building $4,788,323.
Those are the values the applicants gave the city for shells and foundations. They do not count the equipment that goes inside.
What is the newest work on Meta's Tulsa data center?
On Nov. 17, 2026, CEC Facilities filed the electrical permit for Building 55, at 34.5 kV. It was CEC's third filing for a whole building's electrical in five days, after Building 2 on Nov. 13 and the administration building on Nov. 16.
On Nov. 16, the city issued US Engineering two permits for tanks, one for industrial water and one for industrial waste water. Sure Steel's metal building drawings for Building 1 were issued Oct. 28. The city's permit search lists 135 permit records at 21304 E. 11th St. S., 109 of them filed in 2026.
On Oct. 29, the job's site said the team was working with the city on limits for heavy trucks on eastbound 11th Street.
Which firms are on Meta's Tulsa data center?
Fortis Construction is the general contractor. The state names it, and the city's permits list it as the on-site contact and as the applicant for a craft tent 'for Project Anthem'.
Three electrical firms are on the permits. CEC Facilities holds the electrical permits for both data center buildings, the administration building and Building 55. Cache Valley Electric has the substation, and OESCO has nine temporary power meters, including one on the Meta trailer.
US Engineering holds the plumbing and underground pipe permits and the two tank permits. Sure Steel filed the metal building drawings, and Ralph L. Wadsworth Construction holds the water, sewer and storm drain permits. HDR is the design firm on the building permits, and Arup is the engineer on the site plan. Meta worked with the Public Service Company of Oklahoma on power. 10 firms in all are on the list below.
How do the ways into Meta's Tulsa data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Meta's Tulsa data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Meta's Tulsa data center?
| Electrical distributors and gear reps | CEC Facilities' 34.5 kV electrical permits on four buildings, Cache Valley Electric on the substation and OESCO's temporary power. |
|---|
| Mechanical, plumbing and pipe reps | US Engineering's 16 plumbing permits, underground HDPE pipe and the two industrial water tanks. |
|---|
| Steel, site and building suppliers | Sure Steel's metal building work on Building 1 and Ralph L. Wadsworth's water, sewer and storm drain permits. |
|---|
What should you do next on Meta's Tulsa data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Meta's data center at 21304 E. 11th St. S. in Tulsa.
Questions people ask about Meta's Tulsa data center
How much is Meta's Tulsa data center?
Meta says it will be an investment of more than $1 billion once done (April 21, 2026). That is Meta's total, not a contract. PartnerTulsa's plan estimated construction at $800 million, and the city's issued permits that state a value add up to about $139.4 million, our sum.
Who is building Meta's Tulsa data center?
Fortis Construction is the general contractor, named by the Oklahoma Department of Commerce and on the city's permits. 10 firms are named on the job, listed above.
What is Project Anthem in Tulsa?
Project Anthem is the name used for the data center before Meta said, on April 21, 2026, that it is the company behind it. The city's site plan permit names Atmoss, LLC as the developer.
Where is Meta's Tulsa data center?
At 21304 E. 11th St. S., in Fair Oaks Innovation Park in east Tulsa, between 11th Street and the Creek Turnpike. The gate sign uses a Catoosa mailing address.
How big is Meta's Tulsa data center?
The Oklahoma Department of Commerce says more than 2 million sq ft, on a 340-acre site per the Tulsa Flyer. The first two data center buildings are permitted at 411,200 and 349,740 sq ft.
What is the biggest permit on Meta's Tulsa data center?
Building 1's core and shell, BLDC-239331-2026, at $52,181,280 for 411,200 sq ft, issued Sept. 9, 2026.
Who is the electrical contractor on Meta's Tulsa data center?
CEC Facilities holds the electrical permits for Buildings 1 and 2, the administration building and Building 55. Cache Valley Electric has the substation, and OESCO has the temporary power meters.
How many people will work on Meta's Tulsa data center?
Meta expects more than 1,000 construction workers on site at the peak, and about 100 jobs once it opens.
When will Meta's Tulsa data center open?
The Tulsa Flyer reports it is expected to open in 2028. Building permits for the first two data center buildings were issued Sept. 9, 2026.
Who supplies power to Meta's Tulsa data center?
The Oklahoma Department of Commerce says Meta worked closely with the Public Service Company of Oklahoma to plan for and meet its energy needs. Two substations are permitted on the site.
What happens next on Meta's Tulsa data center?
Electrical permits for Building 2, the administration building and Building 55 were filed Nov. 13 to 17, 2026, so the electrical work inside the buildings is next. A rezoning for a second phase on 375 acres to the west was withdrawn on March 30, 2026.
How we built this list
We read the City of Tulsa's public permit records at 21304 E. 11th St. S. (contacts read from the city's public record on Nov. 18, 2026), Meta's April 21, 2026 announcement, the Oklahoma Department of Commerce, KJRH, the Tulsa Flyer, KRMG and the job's own site, and kept each firm a record or a news report names on this job. The $139.4 million is our sum, as of Nov. 18, 2026, of the 30 issued permits at the address that state a value, without four foundation re-filings that repeat the values of Buildings 1 and 2; a $116 million site permit still in review is not counted. Left out: firms named only on the 2024 to early 2026 site, road and utility permits before Fortis's build (Olsson, JE Dunn, Nabholz, Ellsworth Construction, TTL, Tri-Star Construction and Marrs Electric), Atmoss, LLC (the developer, not a contractor), Herc Rentals (named only as a yard on a permit), individuals on the permits, public agencies and community partners, and two data center permits elsewhere in Tulsa. Phones are each firm's own office line, except OESCO, whose site lists none, so its number is from the city permit record, and PSO, whose number is its customer line. We do not name a county because our sources disagree on it. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- Meta Newsroom: Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma (April 21, 2026)
- Oklahoma Department of Commerce: Meta breaks ground on data center in Tulsa (April 21, 2026)
- KJRH: Data center supporting Meta announced, will be built in east Tulsa (April 21, 2026)
- Tulsa Flyer / The Oklahoma Eagle: Meta's east Tulsa data center (April 22, 2026)
- Tulsa Flyer: Project Anthem in east Tulsa, with the gate sign (March 27, 2026)
- City of Tulsa permit records (EnerGov self-service), read Nov. 18, 2026
- Tulsa Data Center construction site, traffic updates (Oct. 29, 2026)
- KRMG: Project Anthem developer withdraws Phase 2 rezoning request (March 30, 2026)