Who's rebuilding Chicago's Blue Line between Kedzie and Pulaski

Chicago's Blue Line is getting an $86 million track rebuild because 84% of the branch runs under slow zones.

By Porter Stanley. Updated .

The Chicago Transit Authority is rebuilding the Blue Line's Forest Park Branch tracks in the I-290 median between Kedzie and Pulaski, where much of the infrastructure dates back to 1958 (CTA). The $86.3 million not-to-exceed design-build contract goes to Kiewit Infrastructure Co., chosen over John Burns Construction and Walsh Construction (CTA board paper B-2, on the Nov. 16, 2026 agenda). Work is set to start in summer 2027 and last about 10 weeks, removing about 8,000 feet of slow zones, per CTA's Nov. 17 release. 10 firms are named: 5 on this contract and 5 on the wider branch rebuild and its program; the list below has all 10.

$86.3MKiewit's design-build contract (CTA)
84%Of the branch in slow zones (CTA, Nov. 17)
~10 weeksTrack work, starting summer 2027
10Firms named (5 on this contract)

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free, sent to your inbox.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free, sent to your inbox.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on the Blue Line Forest Park Branch rebuild?

We list the 10 firms named on CTA's Blue Line Forest Park Branch rebuild, one row each, with where each name comes from: the 5 on the Kedzie to Pulaski contract first, then the 5 on the wider branch and its program.

1Latest recordNov 16, 2026

Design-build contractor: designs and rebuilds the track, drainage, traction power, electrical, communications and signals between Homan and Pulaski on CTA's Blue Line Forest Park Branch rebuild (Phase 2), on the record 2026-11-16

CTA Blue Line Forest Park Branch, Kedzie to Pulaski segment (Homan Ave. bridge to the Pulaski bridge), I-290 median, Chicago (Cook County, IL)

$86,300,000 not-to-exceed design-build contract

Work: Design-build: removal and replacement of all sub-ballast, ballast, ties, rail, special trackwork and drainage; traction power, electrical, communications and signal systems; connections at both ends

Who to call: Kiewit Infrastructure Co.
Kiewit Infrastructure Co. office line
(Itasca, IL)
(773) 458-1250

The opportunity: AWARD RECOMMENDED TO: Kiewit Infrastructure Company

2Latest recordNov 16, 2026

DBE design subconsultant on Kiewit's team: design survey on CTA's Blue Line Forest Park Branch rebuild (Phase 2), on the record 2026-11-16

CTA Blue Line Forest Park Branch, Kedzie to Pulaski segment (Homan Ave. bridge to the Pulaski bridge), I-290 median, Chicago (Cook County, IL)

11.40% of the design phase

Work: Design survey

Who to call: American Surveying & Engineering, Ltd.
American Surveying & Engineering, Ltd.: no main line verified on its own site (its site's security certificate had expired when we checked, Nov. 18, 2026)
(Chicago, IL)

The opportunity: 11.40% American Surveying & Engineering, Ltd (Design Survey)

3Latest recordNov 16, 2026

DBE design subconsultant on Kiewit's team: electrical and communications design on CTA's Blue Line Forest Park Branch rebuild (Phase 2), on the record 2026-11-16

CTA Blue Line Forest Park Branch, Kedzie to Pulaski segment (Homan Ave. bridge to the Pulaski bridge), I-290 median, Chicago (Cook County, IL)

5.52% of the design phase

Work: Electrical and communications design (also on AECOM's branch-wide design contract: communications and systems design, 3.61%)

Who to call: Facet Engineering, LLC
Facet Engineering, LLC office line
(Chicago, IL)
(773) 657-5900

The opportunity: 5.52% Facet Engineering, LLC (Electrical and Communications Design)

What is CTA rebuilding on the Blue Line between Kedzie and Pulaski?

The Chicago Transit Authority is rebuilding the Blue Line's Forest Park Branch tracks in the median of the Eisenhower Expressway (I-290). CTA says much of the branch's infrastructure is original, dating back to 1958. This stretch is Phase 2 of the Forest Park Branch Rebuild: full-depth track work from Station 175+50, near the Homan Ave. bridge, to Station 215+00, near the Pulaski bridge (CTA board paper B-2).

The job removes all of the sub-ballast, ballast, ties, rail, special trackwork and drainage and puts in new, along with traction power, electrical, communications and signal systems and the connections at both ends (B-2). CTA says the work will remove about 8,000 feet of slow zones, including the Pulaski Crossover, and that about 84 percent of the branch is under slow zones today (CTA, Nov. 17, 2026).

Construction is expected to start in summer 2027 and last about 10 weeks (CTA). Phase 1, the track from LaSalle to the Illinois Medical District, was a $268 million job finished in 2023 (CTA, Nov. 2, 2026).

Where does the $86.3 million on the Blue Line go?

The $86.3 million is a not-to-exceed design-build contract to Kiewit Infrastructure Co., paid with Federal Transit Administration funds (B-2). The award was on the Chicago Transit Board's Nov. 16, 2026 agenda, and CTA's Nov. 17 release says the contract "is being awarded" to Kiewit. Three firms sent proposals: John Burns Construction, Kiewit and Walsh Construction. CTA chose Kiewit and negotiated a best and final offer.

Kiewit committed 25.77 percent of the design phase to DBE firms, all four named, and 20 percent of the construction phase to DBE firms that the board paper does not name yet (B-2). No one has published a split of the money by trade, so we do not estimate one here.

Other figures are not this contract. FOX 32 reported a $111 million federal Reconnecting Communities grant for the Kedzie to Pulaski track replacement in March 2024. CTA got a $15.8 million federal Carbon Reduction grant, through IDOT, for branch design work (CTA, Nov. 2, 2026). The Connect Program, which covers both I-290 and the Blue Line, says it has secured more than $1.65 billion.

Which firms are on the Blue Line Forest Park Branch rebuild?

Kiewit Infrastructure Co. holds the Phase 2 design-build contract. Its board paper names four DBE design firms: American Surveying & Engineering for design survey (11.40 percent of the design phase), Facet Engineering for electrical and communications design (5.52 percent), Rubinos & Mesia Engineers for civil engineering (5.22 percent) and GSG Consultants for geotechnical and environmental work (3.63 percent). The board paper does not name Kiewit's lead designer.

The other five firms work on the wider branch or its program, not on the Phase 2 contract. AECOM designs track for the rest of the branch, from the Illinois Medical District to the I-290 bridge outside Kedzie to Keeler, for $17,067,640.20 (B-8), with DB Sterlin Consultants as a design subconsultant; Facet and GSG are on that team too. Transit Capital Partners, CTA's program manager, is adding a construction oversight manager and a design oversight manager for the branch (B-1). CDM Smith leads the I-290/Blue Line Corridor Development Office for CMAP, and Mercator Advisors advises that team on funding and financing. 10 firms in all are on the list below.

How do the ways into the Blue Line rebuild compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on CTA's Blue Line Forest Park Branch rebuildEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Blue Line Forest Park Branch rebuild?

Rail, tie and ballast suppliersKiewit, whose contract replaces all the sub-ballast, ballast, ties, rail and special trackwork between the Homan and Pulaski bridges.
Electrical, signal and traction power repsKiewit, whose contract covers traction power, electrical, communications and signals, and Facet Engineering, which designs the electrical and communications work.
Survey, geotechnical and engineering firmsAmerican Surveying & Engineering, GSG Consultants and Rubinos & Mesia on this contract, and AECOM and DB Sterlin on the design of the rest of the branch.

What should you do next on the Blue Line rebuild?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on CTA's Blue Line Forest Park Branch rebuild.

Questions people ask about the Blue Line Kedzie to Pulaski rebuild

How much is the Blue Line Kedzie to Pulaski contract?

$86.3 million, a not-to-exceed design-build contract to Kiewit Infrastructure Co. (CTA board paper B-2; CTA's Nov. 17, 2026 release). It is the contract value, not a full project budget.

Who is rebuilding the Blue Line between Kedzie and Pulaski?

Kiewit Infrastructure Co. holds the design-build contract. Its board paper names four DBE design firms: American Surveying & Engineering, Facet Engineering, Rubinos & Mesia Engineers and GSG Consultants. 10 firms are named in all, listed above.

Who else bid on the Kedzie to Pulaski work?

Three firms sent proposals: John Burns Construction Company, Kiewit Infrastructure Company and Walsh Construction Company II. CTA picked Kiewit and negotiated a best and final offer (B-2).

When does Blue Line track work between Kedzie and Pulaski start?

CTA says construction is expected to start in summer 2027 and last about 10 weeks (CTA, Nov. 17, 2026).

What does the Kiewit contract cover?

Design, then removal and replacement of all sub-ballast, ballast, ties, rail, special trackwork and drainage, plus traction power, electrical, communications and signal systems, from Station 175+50 near the Homan Ave. bridge to Station 215+00 near the Pulaski bridge (B-2).

How much of the Forest Park Branch is under slow zones?

About 84 percent, per CTA's Nov. 17, 2026 release. CTA's own papers give other figures (81 percent in board paper B-2), so the share depends on the date and the document.

Is the $111 million grant the same as the Kiewit contract?

No. FOX 32 reported a $111 million federal Reconnecting Communities grant for the Kedzie to Pulaski track replacement in March 2024. The Kiewit contract is $86.3 million; no source we opened says what the rest of the grant pays for.

What happens to the rest of the Forest Park Branch?

AECOM holds a $17,067,640.20 contract, on the Oct. 27, 2026 CTA board agenda, to design track for the rest of the branch from the Illinois Medical District to the I-290 bridge, outside Kedzie to Keeler (B-8). We found no construction contract named for those later phases yet.

How we built this list

This is a CTA transit job in the I-290 median, so no city permits name its firms. We read CTA's board papers for the Oct. 27 and Nov. 16, 2026 meetings (B-1, B-2, B-8), CTA's Nov. 2 and Nov. 17 releases, CMAP's Sept. 11, 2024 release, the Connect Program site, FOX 32 and each firm's own site, and kept every firm an opened source ties to the branch (read Nov. 18, 2026). Only 5 firms are on the Kedzie to Pulaski contract itself; the other 5 work on the wider branch rebuild or the Connect Program, and each row says which. The board paper names Kiewit's four DBE design firms but not its lead designer, and the construction-phase DBE firms are not named yet. The Nov. 16 board minutes were not posted when we checked, so we cite the board paper and CTA's release. CTA's own documents give different figures for the slow zones: about 84 percent of the branch and about 8,000 feet in the Nov. 17 release, 81 percent in board paper B-2, and 2024 grant coverage said more than 10,000 feet; we give each with its source. The $86.3 million is a not-to-exceed contract, not a project budget, and no one has published a split by trade, so we do not estimate one. Phones are each firm's own office line; AECOM's is its Dallas headquarters, and we found no verified main line for American Surveying & Engineering, Transit Capital Partners or Mercator Advisors. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on the Blue Line Forest Park Branch rebuild

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.