What is GlobalFoundries building in Malta?
GlobalFoundries is building Fab 8.2, a new chip plant next to its existing Fab 8 on the Luther Forest Technology Campus in Malta, New York (Observer Chronicle). The site is 400 Stonebreak Road Extension, on parcels in both Malta and Stillwater (Town of Malta minutes). Governor Hochul's office says the plant will have about 386,000 square feet of cleanroom.
Gov. Hochul and U.S. and Japanese officials broke ground on Nov. 13, 2026. GlobalFoundries CEO Tim Breen said on Oct. 14 that early work on the site was already underway (ENR), and the plant is set to come online in 2029 (Daily Gazette).
The site has been approved since July 26, 2022, when the Town of Malta Planning Board approved the Fab 8.2 site plan. In May 2025 the board extended that approval to July 26, 2027. Conditions still open include a soil disturbance permit, a state air permit for Fab 8.2, county sewer will-serve letters and six off-site traffic improvements before full production.
Is GlobalFoundries' Malta fab a $10 billion or a $21 billion project?
GlobalFoundries puts the initial investment in Fab 8.2 at about $10 billion, supported with $570 million in incentives from New York State. ENR reports the money comes from Japan under the U.S.-Japan initiative and that the figures are total investment, not contract values.
The up to $21 billion in the U.S.-Japan initiative covers two fabs, and Fab 8.2 is the first (GlobalFoundries). New York counts the fab inside a $12.3 billion expansion that also includes Fab 8 upgrades and an advanced packaging and photonics center (Governor Hochul).
No one has published how the fab's money splits by trade, so this page gives no split.
Who is the general contractor on GlobalFoundries' Malta fab?
GlobalFoundries has not named one. JE Dunn Construction is the one builder reported for the fab. The Daily Gazette reported in November 2022 that JE Dunn was hired for the project Malta had approved that July, and ENR wrote in February 2024 that records showed GlobalFoundries hired JE Dunn for the new 633,000 square foot fab.
In October 2026 ENR again cited records showing JE Dunn had been hired, but GlobalFoundries did not confirm that JE Dunn is still on the team, and JE Dunn referred questions to GlobalFoundries. ConstructConnect reports the announcement named no construction contractor.
Which firms are on GlobalFoundries' Malta fab?
4 firms are named. JE Dunn is the reported builder. C.T. Male Associates is GlobalFoundries' engineer on the site plan: its Peter Lilholt presented the application in 2022 and was among those presenting for GlobalFoundries at the 2025 extension. Creighton Manning wrote the traffic report for the 2022 application. LaBella Associates reviewed the plan for the Town of Malta.
No construction manager, designer of the plant or trade contractor has been named for the 2026 work in any source we read. ATI's permit records hold no building permit for the site yet. The list below has all 4 firms.
How do the ways into GlobalFoundries' Malta fab compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on GlobalFoundries' Malta fab | Every supplier, distributor and sales rep | A conversation with a firm already tied to the job | GlobalFoundries has not named its builder or trade contractors yet, so the list is short |
Who should go after GlobalFoundries' Malta fab?
| Construction suppliers and subcontractors | JE Dunn, the one builder reported for the fab, though GlobalFoundries has not confirmed it for 2026. |
|---|
| Site, road and traffic suppliers | C.T. Male's site plan and Creighton Manning's traffic report, with six off-site traffic improvements a condition of the approval. |
|---|
| Firms that work with the town's review side | LaBella Associates, the Town of Malta's consulting engineer on the Fab 8.2 review. |
|---|
What should you do next on GlobalFoundries' Malta fab?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on GlobalFoundries' Malta fab, and ask JE Dunn whether it is on the 2026 work.
Questions people ask about GlobalFoundries' Malta fab
How much is GlobalFoundries' new fab in Malta?
GlobalFoundries puts the initial investment at about $10 billion, supported with $570 million in incentives from New York State. That is an investment figure covering the first fab, not a construction contract.
Is GlobalFoundries' Malta fab a $21 billion project?
No. Up to $21 billion is the funding in the U.S.-Japan initiative for two fabs. Fab 8.2 is the first, at about $10 billion. New York also counts it in a $12.3 billion expansion that includes Fab 8 upgrades and a packaging center.
Who is building GlobalFoundries' Malta fab?
GlobalFoundries has not named a builder for the 2026 work. JE Dunn Construction was reported hired for the new fab in 2022 and 2024 records, and ENR says GlobalFoundries did not confirm in October 2026 that JE Dunn is still on the team. 4 firms are named in all, listed above.
Where is GlobalFoundries' new fab?
At 400 Stonebreak Road Extension on the Luther Forest Technology Campus, next to the existing Fab 8, on land in the towns of Malta and Stillwater, Saratoga County, New York.
When will GlobalFoundries' Malta fab open?
Ground was broken on Nov. 13, 2026, and the plant is set to come online in 2029 (Daily Gazette).
How big is Fab 8.2?
Governor Hochul's office says Fab 8.2 will have about 386,000 square feet of cleanroom space.
Is GlobalFoundries' Malta fab approved?
Yes. The Town of Malta Planning Board approved the Fab 8.2 site plan on July 26, 2022, and on May 28, 2025 extended the approval to July 26, 2027. Conditions still open include a soil disturbance permit, a state air permit for Fab 8.2 and county sewer will-serve letters.
How many construction jobs will GlobalFoundries' Malta fabs create?
GlobalFoundries says about 27,000 construction and ecosystem jobs across the two-fab initiative. Governor Hochul's office says GlobalFoundries committed to a project labor agreement for construction.
Has a subcontractor been named on GlobalFoundries' Malta fab?
We found none. No trade contractor is named in GlobalFoundries' releases, the Governor's release or the groundbreaking coverage we read, and ConstructConnect reports the announcement named no construction contractor.
How we built this list
We read GlobalFoundries' releases (Oct. 14 and Nov. 13, 2026), Governor Hochul's release, ENR (Feb. 2024 and Oct. 2026), the Daily Gazette (2022 and 2026), the Observer Chronicle, ConstructConnect, the Town of Malta and Town of Stillwater planning board minutes on Fab 8.2 (2022 and 2025), the state construction stormwater coverage for the site and ATI's own permit records, and kept each firm a source ties to this fab (read Nov. 18, 2026). GlobalFoundries has not named a builder, construction manager, designer or trade contractor for the 2026 work, and none of the groundbreaking coverage we read names one. JE Dunn's tie comes from 2022 and 2024 records as reported by the Daily Gazette and ENR; the original 2022 Albany Business Review report is behind a paywall and was not read. The stormwater coverage names GlobalFoundries as operator and no contractor, and ATI's permit records hold no building permit for the site. A law firm, the county sewer district and an economic development group named in the records are left out, because none does construction or design work on the fab. No published trade split for a chip plant was found, so this page gives none. Phones are each firm's own office line. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- GlobalFoundries: GF breaks ground on first new semiconductor fab under landmark U.S.-Japan initiative (Nov. 13, 2026)
- Governor Hochul: groundbreaking of GlobalFoundries' new $10 billion semiconductor fab (Nov. 13, 2026)
- Daily Gazette: Malta semiconductor fab groundbreaking (Nov. 13, 2026)
- Observer Chronicle: GlobalFoundries Malta Fab 8.2 groundbreaking (Nov. 16, 2026)
- ConstructConnect: GlobalFoundries plans two new semiconductor fabs in Malta, New York (Oct. 20, 2026)
- ENR: GlobalFoundries advances New York chip fab with initial $10B Japanese investment (Oct. 16, 2026)
- ENR: federal funding offer to GlobalFoundries for its chip projects (Feb. 20, 2024)
- Daily Gazette: Malta supervisor on GlobalFoundries' second factory (Nov. 17, 2022)
- Town of Malta Planning Board minutes, joint special meeting (April 26, 2022)
- Town of Malta Planning Board minutes, special meeting, Fab 8.2 approval (July 26, 2022)
- Town of Malta Planning Board minutes, Fab 8.2 extension (May 28, 2025)
- Town of Stillwater Planning Board minutes (May 23, 2022)
- Town of Stillwater Planning Board minutes (June 27, 2022)
- LaBella Associates: GlobalFoundries Fab 8 at Luther Forest Technology Campus (project page)