What is Hut 8 building at Beacon Point near Corpus Christi?
Hut 8 is building Beacon Point, an AI data center campus at 4650 FM 1694 near Robstown, outside Corpus Christi. It sits on about 525 acres with 1,000 MW of utility power lined up through AEP Texas.
The plan is two buildings of 352 MW of computing capacity each. Hut 8 says Phase 1 was redesigned from 224 MW to 352 MW in the same footprint, to fit NVIDIA's DSX reference design. Hut 8 has signed two 15-year leases for the campus with one tenant it has not named.
How much does the Beacon Point data center cost?
Hut 8 says the first two phases are expected to represent a combined capital investment of approximately $17 billion, about $8.5 billion for each phase's data center and computer gear. That is Hut 8's planned spending, not a contract with a builder.
The first building is registered with the Texas Department of Licensing and Regulation at $398,985,153. Hut 8's two leases add up to about $19.6 billion of rent over 15 years, which is not a building cost, and Hut 8 sold $4.25 billion of notes to pay for Phase 1.
Where is the Beacon Point campus, and who had to approve it?
The Texas filing places the campus at 4650 FM 1694, Robstown, in Nueces County. The Coastal Bend Current reports the site lies just outside the Robstown and Corpus Christi city limits in unincorporated Nueces County, so no city council or county commissioners court had to approve it.
Nueces County is under Stage 3 drought limits. Hut 8 says no city water will cool the campus: a closed loop is filled once with water from outside the county.
What is happening on the Beacon Point site now?
Hut 8's Nov. 4, 2026 results report: "Progress during the quarter included commencement of construction of the campus substation, foundation work and underground utility work at Phase 1, and civil design for Phase 2." With the second lease signed, Hut 8 now counts all 1,000 MW at Beacon Point as energy capacity under construction.
KIII reported in October 2026 that about 200 workers were on site, expected to reach 1,000 by early 2027. Hut 8 targets the first Phase 1 data hall in the third quarter of 2027 and Phase 2 in the second quarter of 2028.
Who gets what on the Beacon Point first building?
Hut 8 has not published a trade split. By our math on Turner & Townsend's data center cost index, about $191.5 million of the first building's $398,985,153 Texas filing is electrical work, about $131.7 million is pipes, heat and air, and about $35.9 million is the building shell. Most of the $17 billion is computer gear, so we do not split that figure.
Which firms are on the Beacon Point campus?
The Texas filing names Jacobs as the design firm, and Hut 8 says Jacobs leads engineering, buying and construction management. State stormwater notices name Five-S Group of Baton Rouge for the site and DynaGrid Construction of Lewisville, a power and water line builder, at FM 1694 and County Road 48.
Hut 8 names AEP Texas for the power line and substation hookup, Vertiv for power and cooling systems, and FiberLight, Arelion and Windstream as the network providers. NVIDIA is a technology partner, and Lambda is reported to run the computers. We found no trade subcontractors under Jacobs on any public record yet.
Is Nvidia or Anthropic behind the Beacon Point campus?
Hut 8 has not named its tenant. The Energy Mag reports that the Financial Times named Nvidia as the tenant, and that The Wall Street Journal reported Anthropic agreed to buy about $35 billion of computing over six years from Lambda, for about 350 MW at a Hut 8 site in Nueces County, with Nvidia holding the lease.
We found no statement from Hut 8, Nvidia, Anthropic or Lambda confirming the report, so we list Lambda as reported, not confirmed.
How do the ways into the Beacon Point campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Beacon Point campus near Robstown | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Beacon Point campus?
| Electrical distributors and gear reps | The substation, the 345 kV hookup and Vertiv's power systems; about $191.5 million of the first building is electrical by our math. |
|---|
| Site work, pipe and rental suppliers | Five-S Group on the site and DynaGrid on underground utility lines, with foundations under way. |
|---|
| Fiber and low voltage reps | FiberLight, Arelion and Windstream on the network, and a fully sprinklered building with a fire water tank and pump. |
|---|
What should you do next on the Beacon Point campus?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Hut 8's Beacon Point campus on FM 1694 near Robstown.
Questions people ask about the Beacon Point data center
How much does the Beacon Point data center cost?
Hut 8 says the first two phases are expected to represent a combined capital investment of approximately $17 billion, about $8.5 billion each for the data center and its computer gear. That is Hut 8's own planned figure, not a construction contract. The first building is registered with Texas at $398,985,153.
Who is building Hut 8's Beacon Point campus?
Jacobs is the design firm on the state filing and Hut 8's lead for engineering, buying and construction management. State stormwater notices name Five-S Group and DynaGrid Construction on the site. 10 firms are named in all, listed above.
Where is the Beacon Point data center?
At 4650 FM 1694 near Robstown, outside Corpus Christi, on about 525 acres in Nueces County, Texas. The Coastal Bend Current reports the site is in unincorporated Nueces County, outside both city limits.
Did Nueces County have to approve Beacon Point?
No. Because the site lies outside the Robstown and Corpus Christi city limits, the Coastal Bend Current reports that no city council or county commissioners court had to approve or reject it.
When will the Beacon Point data center open?
Hut 8 targets the first data hall delivery in the third quarter of 2027 for Phase 1 and the second quarter of 2028 for Phase 2. The state filing lists Nov. 5, 2027 as the first building's completion date.
Is Nvidia or Anthropic using Beacon Point?
Hut 8 has not named its tenant. The Energy Mag reports that the Financial Times named Nvidia as the tenant, and that The Wall Street Journal reported Anthropic agreed to buy about 350 MW of computing at a Hut 8 site in Nueces County from Lambda, with Nvidia holding the lease. We found no statement from the companies confirming it. Nvidia is confirmed by Hut 8 only as a technology partner.
How many people work on the Beacon Point site?
KIII reported in October 2026 that about 200 workers were on site, expected to grow to 1,000 by early 2027 as work starts on the buildings. Hut 8 expects about 1,900 construction jobs over the first two phases.
Will Beacon Point use local water?
Hut 8 says no city water will be used for cooling. Its closed loop is filled once with water from outside Nueces County and should last about four to seven years. Nueces County is under Stage 3 drought limits.
How do subcontractors and suppliers get on the Beacon Point job?
We found no public bid list. The firms named so far are Jacobs, which manages buying and construction, and the site and utility crews on the state notices. A call to those firms' offices, asking for the Beacon Point team, is the way in we can point to.
What are the risks on the Beacon Point project?
Residents have questioned water and power use, and the Coastal Bend Current notes Hut 8's water promises are, so far, verbal. Hut 8 also answered a directive from the Texas governor on data center power and water in August 2026. Hut 8 says construction remains on track.
What happens next on Beacon Point?
Hut 8 is building the campus substation, Phase 1 foundations and underground utilities, with Phase 2 in civil design. KIII reported the workforce should reach about 1,000 by early 2027.
How we built this list
We read the Texas TDLR registration for the first building, the TCEQ construction stormwater notices for the site, Hut 8's campus page, its May 6, 2026 lease release, its July 20, 2026 campus overview and its Nov. 4, 2026 results, ENR, the Coastal Bend Current, KIII and The Energy Mag, and kept each firm a record or the company names on this job. The site is outside city limits, so there are no city or county building permits to read. Left out: law firms on the construction deal and the notes, the regional economic development group, Hut 8's bitcoin mining affiliate, a fence rental seen in a news photo, an accessibility inspector named on the filing, and Anthropic, a reported customer, not a firm on the job. A TCEQ air permit a tracker tied to Beacon Point belongs to another plant, so we left it out. The trade split is our math on Turner & Townsend's published data center shares, applied to the first building's Texas filing. Phones are each firm's own office line; Vertiv's is from its SEC filings, AEP Texas's is its customer service line, and Arelion and Lambda publish no main line, so we link their contact pages. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- Hut 8: Beacon Point campus page (read Nov. 18, 2026)
- Hut 8: Third quarter 2026 results (PR Newswire, Nov. 4, 2026)
- Texas TDLR registration TABS2027000611, Beacon Point Data Center Project (Sept. 9, 2026)
- TCEQ water quality permit search, construction stormwater TXR1553YP and TXR1509YT
- Hut 8: first Beacon Point lease release (PR Newswire, May 6, 2026)
- Hut 8: Beacon Point campus overview (July 20, 2026)
- ENR: Jacobs expands EPCM role with Hut 8's 1 GW Texas AI campus (May 2026)
- Coastal Bend Current: Beacon Point moves ahead with no local oversight (July 13, 2026)
- KIII via Yahoo News (Oct. 8, 2026)
- The Energy Mag: Anthropic's $35B Lambda deal connects Nvidia to Hut 8's Texas AI data center (Sept. 1, 2026)
- ConstructConnect on Turner & Townsend's Data Center Cost Index (Sept. 2, 2026)