What is Fort Worth building at Mary's Creek?
Fort Worth is building the Mary's Creek Water Reclamation Facility, a membrane bioreactor plant that treats 10 million gallons of wastewater a day (M&C 26-0822); the city says it can be expanded to 15. It sits on a city site of about 100 acres along Chapin Road, north of Mary's Creek, and the state's accessibility registration lists it at 11091 Chapin Road (TDLR). The Fort Worth Star-Telegram calls it the city's first newly built wastewater treatment plant since the 1950s.
On Aug. 25, 2026, Fort Worth authorized a $537,982,128.13 contract with Webber Waterworks to build it. Ferrovial, Webber's parent, announced the award on Nov. 5, 2026 and called it the company's largest U.S. water infrastructure project to date. Construction is scheduled to begin in November 2026 and be completed by summer 2030 (Ferrovial). We found no report of a groundbreaking or site work yet.
Where does the money for the Mary's Creek plant go?
Webber's $537,982,128.13 contract covers the plant only; the lift stations and force mains that bring wastewater to it are separate contracts. Webber's proposal ranked highest of three. Thalle Construction proposed $576,527,017.43 and Walsh Group $607,890,518 (M&C 26-0822).
Seven preselected equipment packages sit inside Webber's contract. The city picked the makers first, and each signs a subcontract directly with the general contractor. Five prices are stated in the city's contracts: Veolia's membrane system $6,688,000, SAVECO's fine screens $1,298,750, Hydro International's grit equipment $1,151,300.80, Trojan's UV disinfection $945,000 and GEA's centrifuges $900,000, which add up to $10,983,050.80. Vaughan's mixing systems and Vulcan's package have no readable price in the record.
Other figures cover more than the plant contract. The city has appropriated $573,646,319.66 for the plant (M&C 26-0822). EPA's WIFIA fact sheet puts total project costs at $710 million, including the lift stations, force mains and related infrastructure, with a $348 million WIFIA loan. The Texas Water Development Board's June 2026 board item committed $60 million through the Clean Water State Revolving Fund. No one has published a split of Webber's contract by trade, so we do not estimate one.
Which firms are on the Mary's Creek plant?
Webber Waterworks is the general contractor. Plummer Associates designed the plant: process evaluation and concept design from 2022, then preliminary and final design, a $21,497,288 contract after Amendment 2 (M&C 24-0858). The contract documents name Gupta & Associates, Signature Automation and Jacobs with Plummer, and Jacobs is the design firm on the state accessibility registration for the plant's buildings.
CDM Smith designs the Mary's Creek Confluence and Walnut Creek lift stations that carry wastewater to the plant ($3,745,826, M&C 25-0155). Oncor brings the power: a $1,870,059.14 agreement for lines, transformers and metering for a dual-feed service sized for a 4,391 kW load (M&C 26-0356).
The seven equipment makers are Veolia (membranes), SAVECO (fine screens), Hydro International (grit), Trojan (UV), GEA (centrifuges), Vaughan (mixing for the equalization and peak flow basins) and Vulcan Industries. No electrical, concrete or process mechanical subcontractor under Webber is named in any record yet, and the contract carries no small business goal; the city approved a waiver. 14 firms in all are on the list below.
How do the ways into the Mary's Creek plant compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Fort Worth's Mary's Creek plant | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Mary's Creek plant?
| Process equipment, pipe and valve suppliers | Webber Waterworks, the general contractor on the whole plant, and the seven preselected equipment makers working under it. |
|---|
| Electrical and power reps | Webber, which holds the plant contract, and Oncor's dual-feed service to the plant, sized for a 4,391 kW load. |
|---|
| Concrete, rebar and site suppliers | Webber, on a new plant with an equalization basin and a peak flow storage basin, with construction scheduled to begin in November 2026. |
|---|
What should you do next on the Mary's Creek plant?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Fort Worth's Mary's Creek plant.
Questions people ask about the Mary's Creek plant
How much is the Mary's Creek Water Reclamation Facility?
Fort Worth's construction contract with Webber Waterworks is $537,982,128.13 (M&C 26-0822). The city has appropriated $573,646,319.66 for the plant, and EPA puts total project costs, including the lift stations and force mains, at $710 million.
Who is building the Mary's Creek plant?
Webber Waterworks, LLC, a Ferrovial company, is the general contractor. Plummer Associates designed the plant. 14 firms are named in all, listed above.
Where is the Mary's Creek plant?
On a city site of about 100 acres along Chapin Road in Fort Worth, north of Mary's Creek, in Tarrant County. The state's accessibility registration lists 11091 Chapin Road.
When was the Mary's Creek contract awarded?
Fort Worth authorized the contract with Webber Waterworks on Aug. 25, 2026 (M&C 26-0822). Ferrovial announced it on Nov. 5, 2026.
When does construction start and finish?
Ferrovial says construction is scheduled to begin in November 2026 and be completed by summer 2030. The city's project page says May 2030. We found no report of a groundbreaking or site work yet.
Who else proposed to build the Mary's Creek plant?
Thalle Construction Co. proposed $576,527,017.43 and Walsh Group $607,890,518. Webber's proposal ranked highest of the three (M&C 26-0822).
What equipment goes into the Mary's Creek plant?
The city preselected seven equipment makers: Veolia's membrane system, SAVECO's fine screens, Hydro International's grit equipment, Trojan's UV disinfection, GEA's centrifuges, Vaughan's basin mixing systems and a package from Vulcan Industries. Each signs a subcontract with Webber, inside Webber's contract.
How do subcontractors get on the Mary's Creek plant?
Through Webber Waterworks. No subcontractor under Webber is named in any record yet, and the contract carries no small business goal; the city approved a waiver (M&C 26-0822).
Is this Fort Worth's first new wastewater plant in decades?
Yes. The Fort Worth Star-Telegram calls it the city's first newly built wastewater treatment plant since the 1950s.
How we built this list
We read Fort Worth's council communications (M&C 22-0892, 24-0858, 25-0155, 26-0356 and 26-0822), the city's preselection equipment contracts (CSC 64966, 65001, 65023, 65180, 65205, 65235 and 65236), Texas's accessibility registration TABS2026017276, EPA's WIFIA fact sheet, Ferrovial's release, Construction Dive and the Fort Worth Star-Telegram, and kept every firm a record ties to the plant, its lift stations or its power (read Nov. 18, 2026). Losing proposers, sureties, lawyers, public agencies and firms on a neighboring parcel are left out. Webber's signed contract was not found, and no subcontractor under Webber is named yet. Vaughan's equipment price is handwritten and unreadable in the record, and Vulcan's package and price are not readable. The equipment prices are the city's stated figures; no one has published a split of Webber's contract by trade, so we do not estimate one. Phones are each firm's own line, labeled where its site lists only a toll-free, customer care or corporate line; we found no verified line or website for Signature Automation. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- City of Fort Worth M&C 26-0822: Webber Waterworks contract, Mary's Creek WRF (Aug. 25, 2026)
- Ferrovial: Ferrovial awarded water facility project in Texas (Nov. 5, 2026)
- Construction Dive: Ferrovial wins $538M Texas water project (Nov. 13, 2026)
- Fort Worth Star-Telegram via AOL: long-awaited Fort Worth wastewater plant (Aug. 4, 2026)
- EPA WIFIA fact sheet: Fort Worth, Texas (January 2026)
- City of Fort Worth M&C 22-0892: Plummer Associates concept design (Nov. 8, 2022)
- City of Fort Worth M&C 24-0858: Plummer Associates final design (Oct. 15, 2024)
- City of Fort Worth M&C 25-0155: CDM Smith lift station design (Feb. 25, 2025)
- City of Fort Worth M&C 26-0356: Oncor electrical service agreement (May 12, 2026)
- Texas Department of Licensing and Regulation: TABS2026017276
- City of Fort Worth CSC 65180: membrane equipment preselection (Veolia)
- City of Fort Worth CSC 64966: Preselection Package 2 (GEA)
- City of Fort Worth CSC 65023: Preselection Package 2 (SAVECO)
- City of Fort Worth CSC 65235: Preselection Package 2 (Hydro International)
- City of Fort Worth CSC 65205: Preselection Package 2 (Trojan)
- City of Fort Worth CSC 65236: Preselection Package 2 (Vaughan)
- City of Fort Worth CSC 65001: Preselection Package 2 (Vulcan)
- City of Fort Worth resolution 25-5577: Texas Water Development Board assistance (November 2025)
- City of Fort Worth: Mary's Creek Water Reclamation Facility project page
- City of Fort Worth: Mary's Creek Water Reclamation Facility (water department page)
- Texas Water Development Board: June 2026 board item 14, City of Fort Worth, Mary's Creek (CWSRF, $60 million)