Who is the electrician on Aligned's IAD-03?
Loudoun County's permits name J.E. Richards on the electrical permit for every data hall at Aligned's IAD-03, 22715 Relocation Dr, Sterling: halls 110, 120, 130, 210, 220, 230, 310, 320 and 420. Each permit says "The permit is for Data Hall ..." and points to the approved drawings of Tenant Fit-Out B.
Seven of the nine were finaled between May and July 2026. Two were still open on Nov. 10, 2026: data hall 130 (ELECC-2026-029814, issued Aug. 10, 2026) and data hall 230 (ELECC-2026-019131, issued June 26, 2026). Each lists 80 sub panels and 4,800 circuits; hall 130 lists 193 light fixtures and hall 230 lists 191, with 9,600 amps of service.
J.E. Richards also holds the phase 1 build-out's electrical permit (finaled), whose form lists 27 generators, 27 UPS systems and 95 dry transformers, and the electrical permit for the new two-story addition, which lists 10 generators, 10 UPS systems and 34 dry transformers and was back in review on Nov. 10. It holds the fire alarm permits too. No news story we read names the electrician.
Who else is wiring the building?
Rosendin holds the building automation wiring. Loudoun County issued ELECC-2026-043635 on Oct. 13, 2026 (filed Sept. 4): "Low voltage control wiring for building automation systems (BAS)." The work is RS-485 plenum communication wire, 18 to 22 gauge control wire and polytube, in 3/4 to 1 inch conduit or free hanging in the ceiling plenum, with 4,347 devices on the form. The permit says "The low voltage panels and devices will be supplied by the owner."
It is tied to the addition's building permit and is the newest permit at the address. Rosendin also held the first phase's building automation permit in 2025.
IES Communications holds the access control and cameras for halls 130 and 230 (issued Aug. 5, 2026) and the fiber to the addition's six IDF cabinets (issued Sept. 14, 2026). BFPE International holds both halls' VESDA permits.
How big is the job?
Tenant Fit-Out B was issued to Holder Construction on Oct. 7, 2025 on two building permits, both carrying $80,000,000. Their estimated construction costs split it: $62,000,000 for seven halls (BLDC-2025-040329) and $18,000,000 for hall 130 (BLDC-2025-040331). The scope adds "passageways between Data Halls through existing Mechanical Galleries, as well as additional programming, storage, added electrical conveyance".
The addition, issued Nov. 13, 2025, is "a new 2-story precast concrete structure at the south end of the existing building and the interior build out of 2 data halls in the south building addition": 68,585 sq ft, with an estimated construction cost of $74,000,000.
The trade permits' value fields repeat these building figures ($80,000,000 on hall 130's electrical permit, $37,000,000 on the addition's), so they are not electrical prices and we don't add them.
Who owns Aligned?
AIP, MGX and BlackRock's Global Infrastructure Partners completed their purchase of 100% of Aligned on July 21, 2026, a deal Aligned says "represents Aligned's enterprise value of approximately $40 billion". The Associated Press reported it on Oct. 15, 2025 as "A group including BlackRock, Nvidia and Microsoft is buying Aligned Data Centers". AIP was founded by BlackRock, GIP, MGX, Microsoft and NVIDIA.
The coverage named the buyers and the price. None of it named who builds or wires Aligned's buildings.
How do the ways into Aligned's IAD-03 compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The electrician on the permits | A call to J.E. Richards, on all nine data halls, the build-out and the addition | Lighting, wire, panel, gear and generator reps | A conversation with the firm on Aligned's power work at IAD-03 | Its project staff aren't listed publicly, so start at the main line |
| The controls electrician | A call to Rosendin, on the building automation wiring (issued Oct. 13, 2026) | Control wire, conduit and polytube reps | The newest permit on the building | The owner supplies the panels and devices |
| The builder | A call to Holder Construction's Washington, D.C. office in Herndon | Trades and suppliers who sell to GCs | Who holds the scopes no permit names | Most of the fit-out is finaled; ask what is next |
| The low-voltage and fire firms | Calls to IES Communications (access control, cameras, fiber) and BFPE International (VESDA) | Security, cable and life-safety reps | Open permits on halls 130 and 230 | Their scopes are small next to the power work |
Who should go after Aligned's IAD-03, and who shouldn't?
| Electrical distributors, lighting, panel and gear reps | J.E. Richards holds every data hall's electrical permit; halls 130 and 230 list 80 sub panels and 4,800 circuits each, and the addition's permit lists 10 generators, 10 UPS systems and 34 dry transformers. |
|---|
| Control wire and conduit reps | Rosendin's building automation permit (issued Oct. 13, 2026) names RS-485 plenum wire, 18 to 22 gauge control wire and polytube in 3/4 to 1 inch conduit; the owner supplies the panels and devices. |
|---|
| Security, cable and fire reps | IES Communications (access control, cameras, fiber to 6 IDF cabinets) and BFPE International (VESDA) hold open permits on halls 130 and 230. |
|---|
| Who shouldn't bother | A rep looking for a public bid: this is a private job with the trades already named on the permits, and seven of the nine halls' electrical permits are finaled. |
|---|
What should you do next on Aligned's IAD-03?
- If you sell lighting, wire, panels or gear, call J.E. Richards's main line and ask for the team on Aligned's IAD-03 in Sterling (data halls 130 and 230).
- If you sell control wire, conduit or building automation parts, call Rosendin about the IAD-03 addition's controls wiring, issued Oct. 13, 2026.
- If you sell to builders, call Holder Construction's Washington, D.C. office in Herndon about what follows Tenant Fit-Out B.
- Open the full list for every permit and firm, with each company's line.
Questions people ask about Aligned's Sterling data center
Who is the electrician on Aligned's Sterling data center?
J.E. Richards. Loudoun County's permits name it on the electrical permit for all nine data halls at 22715 Relocation Dr (DH110, 120, 130, 210, 220, 230, 310, 320 and 420), on the phase 1 build-out (ELECC-2025-013311) and on the addition (ELECC-2025-013312), plus the fire alarm. Rosendin holds the building automation wiring.
Which data halls are still open?
On Nov. 10, 2026 the electrical permits for data hall 130 (ELECC-2026-029814, issued Aug. 10, 2026) and data hall 230 (ELECC-2026-019131, issued June 26, 2026) read "Issued", not finaled. The other seven halls' electrical permits are finaled.
What do the electrical permits list?
Each open hall's permit lists 80 sub panels and 4,800 circuits (193 and 191 light fixtures; hall 230 lists 9,600 amps). The addition's electrical permit lists 10 generators, 10 UPS systems, 34 dry transformers, 66 sub panels and 544 light fixtures; the phase 1 build-out's listed 27 generators, 27 UPS systems and 95 dry transformers. These are the counts on the county forms, not a bill of materials.
Who does the controls wiring?
Rosendin. Loudoun County issued ELECC-2026-043635 on Oct. 13, 2026 for "Low voltage control wiring for building automation systems (BAS)", tied to the addition's building permit, with 4,347 devices on the form. It says "The low voltage panels and devices will be supplied by the owner."
How much does the work cost?
Tenant Fit-Out B is $80,000,000 on both of its building permits; their estimated construction costs split it into $62,000,000 for seven halls and $18,000,000 for hall 130. The addition's building permit lists an estimated construction cost of $74,000,000. The trade permits' value fields repeat these building figures, so they are not added up and are not wiring prices.
Who is building it?
Holder Construction holds every building permit at the address since 2024 (its Washington, D.C. office is in Herndon). Gensler is named on the fit-out permits as the representative and authorized agent.
Is this Aligned's building?
Yes. Aligned lists IAD-03 at 22715 Relocation Dr, Sterling, and the permits name Aligned Data Centers (Relo) Propco LLC and Aligned Energy Data Centers (IAD) Propco, LLC as owner. Aligned announced the Sterling campus in 2022 as a four-story, 72 MW, 430,000 sq ft hyperscale data center.
Who owns Aligned now?
A consortium of AIP, MGX and BlackRock's Global Infrastructure Partners completed its purchase of Aligned on July 21, 2026, at an enterprise value of about $40 billion. AIP was founded by BlackRock, GIP, MGX, Microsoft and NVIDIA. The $40 billion is the whole company, not this building.
Is any of it out to bid?
We found no public bid. It is private work, and the permits already name the trades. The way in is a call to the firms on the record.
What happens next?
Data halls 130 and 230 close out when their permits are finaled. The addition's main electrical permit was back in review on Nov. 10, 2026 on a conformed set. Nothing new had been filed at the address since Sept. 4, 2026.
How we built this list
We read all 174 Loudoun County permit records at 22715 Relocation Dr, Sterling, on the county's public permit portal (LandMARC, read Nov. 10, 2026): building, zoning, electrical, low voltage, mechanical, plumbing, fire and elevator records, with each one's status, dates, value and named firms, and the counts on each electrical permit's form (sub panels, circuits, generators, UPS systems, devices). We read Aligned's own pages and releases, the Associated Press story on the acquisition and Data Center Frontier's 2022 story on the campus. We added the same two electricians' other active Loudoun County data center permits from ATI's records, each checked on the county portal. A row is on the list only if a permit or a firm's own page backs it. First published Nov. 19, 2026. We'll update this page when data halls 130 and 230 are finaled, when the addition's electrical review closes, and when anything new is filed at 22715 Relocation Dr.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- Loudoun County LandMARC, ELECC-2026-029814 (data hall 130 electrical)
- Loudoun County LandMARC, ELECC-2026-019131 (data hall 230 electrical)
- Loudoun County LandMARC, ELECC-2026-043635 (building automation wiring)
- Loudoun County LandMARC, BLDC-2025-040329 (Tenant Fit-Out B, seven halls)
- Loudoun County LandMARC, BLDC-2025-040331 (Tenant Fit-Out B, hall 130)
- Loudoun County LandMARC, BLDC-2024-035070 (two-story addition)
- Loudoun County LandMARC, ELECC-2025-013312 (addition electrical)
- Loudoun County LandMARC, ELECC-2025-013311 (phase 1 build-out electrical)
- Loudoun County LandMARC, ELECC-2026-028656 (halls 130 and 230 access control)
- Aligned Data Centers, Northern Virginia data centers
- Aligned Data Centers, closing release, July 21, 2026
- Associated Press via News4JAX, Oct. 15, 2025
- Kirkland & Ellis release, Oct. 15, 2025
- Aligned Data Centers, Sterling campus release, July 2022
- Data Center Frontier, July 26, 2022