What is LA Metro building on the D Line?
LA Metro is extending its D Line subway, long called the Purple Line, west under Wilshire Boulevard. Section 1, from Koreatown to La Cienega, opened May 8, 2026.
Section 2 runs about 2.59 miles to two new stations: Beverly Dr in Beverly Hills, once called Wilshire/Rodeo, and Century City/Constellation in Los Angeles. It also buys 20 rail cars. Section 3 runs about 2.56 miles more to Westwood/UCLA and Westwood/VA Hospital, with 16 more cars and a parking structure at the VA.
How much does the D Line extension to Century City cost?
Metro's board report asks to raise Section 2's budget by $296 million, from $2,574,969,299 to $2,870,969,299, about $2.87 billion. The finance committee approved it on Nov. 19, 2026, and the full board votes Dec. 3. Metro's chief program management officer, Tim Lindholm, called it the final budget increase needed to open Section 2.
Section 3 is a separate budget of $3.7 billion, counting its finance charges, unchanged in Metro's August 2026 report. Section 2's figure leaves out $88.7 million in finance charges; counted the same way, the two sections come to about $6.7 billion, the sum. As of September 2026, Section 2 had only $6.7 million of contingency left.
Why did the D Line Section 2 budget go up?
The biggest piece, $151 million, settles Tutor Perini/O&G's time-related delay claim. Metro says the claim was first submitted at over $200 million, and the builder's other claims and notices raised the disputed items to over $357 million. The settlement moves Section 2's substantial completion from spring to fall 2027.
Drilling under Beverly Hills High School found three underground anomalies, and two turned out to be oil wells. Metro's cost to the Beverly Hills school district was $22.4 million. A second, stronger tunnel lining added about $75 million to the main contract. Since award, 284 contract changes worth $230 million had been signed by August 2026.
How far along is the D Line subway extension?
Section 2 is in its ninth year of construction and was 95% complete in September 2026. It should open around September 2027, and riders will go from Century City to downtown in about 20 minutes.
Section 3 was 87% complete in August 2026. Its twin tunnels, dug by Frontier-Kemper/Tutor Perini, reached substantial completion on Dec. 23, 2025. Its stations contract is due for substantial completion on June 4, 2027, and Section 3 should open around December 2027. Tutor Perini/O&G reported 3,947,535 work hours on its Section 3 contract through August 2026.
Who is building the D Line subway extension?
Tutor Perini/O&G, a joint venture of Tutor Perini and O&G Industries, holds the Section 2 design-build contract, C1120. Metro awarded it at $1.37 billion in January 2017; Tutor Perini's page now lists $1.55 billion. The same venture holds the Section 3 stations contract, C1152, at $1.45 billion per Tutor Perini.
Frontier-Kemper/Tutor Perini built the Section 3 tunnels under contract C1151, $468 million per Tutor Perini, using a Herrenknecht tunnel boring machine. Steve Bubalo Construction Company moved utilities ahead of the Westwood/UCLA station dig under contract C1153.
Which trade and design firms are on the D Line?
Tutor Perini's pages name its trade partners. Fisk Electric holds $164 million in electrical work on Section 2 and $179 million on the Section 3 stations, about $343 million together, the sum. Desert Mechanical has $34 million in mechanical work on Section 2 and more on Section 3, and Becho has $28 million in support of excavation on the Section 3 stations.
STV is designing the Section 2 stations and tunnels. WSP gives Metro engineering and design support. AECOM, SafeworkCM and Morgner are among the firms leading Purple Line 2 CM Partners on Section 2, with Delve Underground as its lead tunneling consultant, and Mott MacDonald and PGH Wong are in MPPC Partners on Section 3. Hyundai Rotem builds the new rail cars. 20 firms in all are on the list below.
Who LA Metro hired before
LA Metro keeps going back to the same big tunnel builders and engineers: Skanska and Traylor built its last two subways, and WSP and Tutor Perini go back decades on its rail.
- Skanska: builder on D Line Extension Section 1, Koreatown to La Cienega, Los Angeles, CA, 2026.
- Skanska and Traylor Brothers: builder on Regional Connector, downtown light-rail subway, Los Angeles, CA, 2023.
- WSP: engineer on Regional Connector, Los Angeles, CA, 2023. Also on this job.
- Tutor Perini: builder on The original Metro Red Line subway, Los Angeles, CA, 1990s. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 20 firms on this job.
How do the ways into the D Line subway extension compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the D Line (Purple Line) extension | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the D Line subway extension?
| Electrical, systems and controls suppliers | Fisk Electric's about $343 million in electrical work on Section 2 and the Section 3 stations (the sum), as station finishes and systems run through 2027. |
|---|
| Mechanical, concrete and site suppliers | Desert Mechanical on the station mechanical work, Becho on support of excavation, and Tutor Perini/O&G on the four stations. |
|---|
| Engineering, testing and inspection firms | STV as Section 2 engineer of record, WSP, and the two construction management ventures that include AECOM and Mott MacDonald. |
|---|
What should you do next on the D Line subway extension?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on LA Metro's D Line (Purple Line) extension to Century City and Westwood.
- Watch Metro's full board vote on the Section 2 budget on Dec. 3, 2026.
Questions people ask about the D Line subway extension
How much does the D Line subway extension to Century City cost?
Metro's proposed budget for Section 2, Beverly Hills to Century City, is $2.87 billion, up $296 million from $2.57 billion. Metro's finance committee approved it on Nov. 19, 2026, and the full board votes Dec. 3. Section 3, on to Westwood, is a separate $3.7 billion budget.
Why did the D Line Section 2 budget go up $296 million?
$151 million settles the builder's delay claim. Metro also found two abandoned oil wells under Beverly Hills High School and added a second, stronger tunnel lining, which alone added about $75 million to the main contract. Only $6.7 million of contingency was left in September 2026.
Who is building the D Line subway extension?
LA Metro owns the job. Tutor Perini/O&G, a joint venture of Tutor Perini and O&G Industries, builds Section 2 and the Section 3 stations. Frontier-Kemper/Tutor Perini dug the Section 3 tunnels, finished Dec. 23, 2025. 20 firms are named on the job, listed above.
What was Tutor Perini's delay claim on the D Line?
Metro's board report says the claim was first submitted at over $200 million, and the builder's other claims and notices raised the disputed items to over $357 million. Metro settled for $151 million, and the settlement moves Section 2's finish from spring to fall 2027.
When will the D Line open to Century City and Westwood?
Section 2, to Century City, is expected to open around September 2027. Section 3, to Westwood, around December 2027. Riders will go from Century City to downtown in about 20 minutes.
How far along is the D Line subway extension?
Section 2 was 95% complete in September 2026, in its ninth year of construction. Section 3 was 87% complete in August 2026; its tunnels are done and its stations are due for substantial completion June 4, 2027.
Where are the new D Line stations?
Section 2 adds Beverly Dr in Beverly Hills (formerly called Wilshire/Rodeo) and Century City/Constellation in Los Angeles. Section 3 adds Westwood/UCLA and Westwood/VA Hospital. In all, about 5.2 miles of twin subway tunnel.
Which subcontractors are on the D Line subway extension?
Fisk Electric holds about $343 million in electrical work across Section 2 and the Section 3 stations, the sum. Desert Mechanical has the mechanical work, Becho the support of excavation, and Steve Bubalo Construction did the utility moves at Westwood/UCLA.
How can suppliers get on the D Line subway extension?
Call the firms already on the job, starting with Tutor Perini and its electrical and mechanical subcontractors, Fisk Electric and Desert Mechanical. Station finishes, systems and testing run through 2027.
Who designs and manages the D Line subway extension?
STV is the engineer of record for Section 2. WSP gives Metro engineering and design support. AECOM, SafeworkCM and Morgner are among the leaders of the Section 2 construction management venture, with Delve Underground as lead tunneling consultant, and Mott MacDonald and PGH Wong are in the Section 3 construction management venture.
What happens next on the D Line subway extension?
Metro's full board votes on the $296 million increase on Dec. 3, 2026. Metro's program chief called it the final increase needed to open Section 2. We'll update this page when a new contract or firm appears.
How we built this list
We read Metro's Nov. 19, 2026 board report 2026-0591 with its presentation and Attachment C, Metro's August 2026 status reports for Sections 2 and 3, Metro's 2017 board report on Section 3 construction management, Tutor Perini's three project pages, STV's and Delve Underground's project pages and Streetsblog LA, all on Nov. 25, 2026. We kept each firm a public record names on Section 2 or 3. Contract values for joint ventures are for the whole team, not one firm's share; the $343 million, $69.8 million and $6.7 billion figures are our sums. Left out: LA Metro (the owner), a construction management partner whose name we could not tie to one firm, two small business partners with no site we could confirm, a shuttle and valet contractor, the Beverly Hills school district, and Section 1's builders, which appear only under who Metro hired before. Phones are each firm's own line from its own site; Tutor Perini, O&G, Fisk Electric and Delve Underground are headquarters lines and Mott MacDonald's is the US line on its site. Frontier-Kemper, Desert Mechanical, Becho, WSP, AECOM, Morgner, Hyundai Rotem and Herrenknecht show a website only, and we found no website for SafeworkCM, SecoTrans, KKCS or Triunity. First published Nov. 25, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.