Who's building Google's data center in Botetourt County, Virginia

Google's Botetourt County data center, at least $3 billion, was ordered stopped by a judge on Nov. 23, who ruled the county broke Virginia's open government law to approve it.

By Porter Stanley. Updated .

Google is building a data center campus, called Project Raspberry, at the Botetourt Center at Greenfield in Daleville, Botetourt County, Virginia. The county's deal calls for at least $1 billion of investment in each of three data centers, at least $3 billion in all, as reported; Google has given no figure itself. On Nov. 23, 2026, a judge voided the county's deal, ordered work stopped and ordered a public hearing. The state stormwater permit names Whiting-Turner as the site's operator. 11 firms are named on the job; the list below has all 11.

$3B+Minimum investment: 3 data centers at $1B+ each (as reported)
118Backup generators of 2,800 kW each
$264MAppalachian Power grid upgrades (as reported)
11Firms named on the job

Get all 11 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 11 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 11 firms on the Google Botetourt data center?

We list the 11 firms named on Google's Project Raspberry data center in Botetourt County, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Permit on the recordAug 6, 2026

The Whiting-Turner Contracting Company

Builder of record on the state stormwater permit for the campus site work on Google's Project Raspberry data center in Daleville, Botetourt County, VA

Google's Project Raspberry data center campus, Botetourt Center at Greenfield, Daleville (Botetourt County), VA

State stormwater registration VAR10X539, Project Raspberry, 1016 International Parkway DC-1A, 110 acres disturbed, received Aug. 6, 2026

Work: Builder of record on the state stormwater permit for the campus site work

Who to call: The Whiting-Turner Contracting Company
The Whiting-Turner Contracting Company office line
(Baltimore, MD)
(410) 821-1100

The opportunity: Virginia DEQ's stormwater layer lists 'The Whiting Turner Contracting Company' as the operator on VAR10X539 'Project Raspberry' at 1016 International Parkway DC-1A, Daleville. The phone is its Baltimore headquarters line. Google also picked Whiting-Turner in 2024 to build a $600 million data center in Wasco County, Oregon.

2Latest recordOct 30, 2026

MTU (Rolls-Royce Power Systems)

Maker of the 118 MTU 20V4000 DS2800 backup generator sets, 2,800 kW each (42 at Building 1, 42 at Building 2, 34 at Building 3) on Google's Project Raspberry data center in Daleville, Botetourt County, VA

Google's Project Raspberry data center campus, Botetourt Center at Greenfield, Daleville (Botetourt County), VA

State air permit application amendment, Reg. No. 21819, filed Oct. 30, 2026; 118 units of 2,800 kWe, about 330 MW of standby power (the math)

Work: Maker of the 118 MTU 20V4000 DS2800 backup generator sets, 2,800 kW each (42 at Building 1, 42 at Building 2, 34 at Building 3)

Who to call: MTU (Rolls-Royce Power Systems)
MTU website https://www.mtu-solutions.com (no main line verified on its own site)

The opportunity: The Oct. 30 amendment reads: 'A total of 118 identical critical MTU 20V4000 DS2800 EGs (42 at Building 1, 42 at Building 2, 34 at Building 3), each rated at 2,800 electrical kilowatts (kWe).' They replace the 114 Caterpillar units in the May application. The application names the maker, not the dealer or installer.

3Latest recordOct 30, 2026

Safety Power

Emissions controls (ecoCUBE SCR and catalyzed DPF) on all 118 backup generators on Google's Project Raspberry data center in Daleville, Botetourt County, VA

Google's Project Raspberry data center campus, Botetourt Center at Greenfield, Daleville (Botetourt County), VA

State air permit application amendment, filed Oct. 30, 2026; Tier 4-equivalent controls on 118 generators

Work: Emissions controls (ecoCUBE SCR and catalyzed DPF) on all 118 backup generators

Who to call: Safety Power
Safety Power office line
(800) 657-1280

The opportunity: The amendment reads: 'The critical EGs will have Tier 4-equivalent controls (Safety Power ecoCUBE control system with SCR and a catalyzed DPF) upon installation.'

What is Google building in Botetourt County, Virginia?

Google is building a data center campus at the Botetourt Center at Greenfield, a county business park in Daleville. State records call it Project Raspberry. Google LLC is the applicant on the state and Army Corps records, and Helio Capital LLC is the developer for Google on the county and water deals.

The plans show three data center buildings of about 300,000 sq ft each, three substations and a 28,000 sq ft office on a 343.6-acre parcel. The work would disturb 240.4 acres. Google bought about 312 acres for $14 million in June 2025, per the county.

How much is the Google Botetourt data center?

Google has not given a dollar figure. The county's performance agreement requires at least $1 billion of investment for each data center, as reported, and three are planned, so at least $3 billion in all.

The county says the three data centers are expected to bring at least $10 million a year in local taxes. The deal also calls for at least 50 full-time jobs per building at a median salary of about $86,000, as reported. Appalachian Power plans about $264 million of power line and substation upgrades to serve the campus, in a filing with state regulators on Sept. 4, 2026.

Why did a judge stop the Google Botetourt data center?

On Nov. 23, 2026, Substitute Judge Michael Doucette ruled that the Board of Supervisors broke Virginia's open government law (FOIA) when it approved the deal on June 24, 2025. The board discussed the deal in a closed session, then voted 5-0 in open session without discussion, and the judge found it did not reasonably identify what it was voting on. He voided the county's actions on the deal since that date, ordered construction stopped and wrote that the fix is a new public hearing that follows the law.

Crews were still on site that afternoon. On Nov. 24 the county said work could go on for several more days, possibly a week, while crews wind down and secure equipment. Google said it is evaluating next steps, and the county said it is evaluating its options.

How far along was the Google Botetourt data center?

Grading began the second week of September 2026 under the county's land disturbance permit. The county had expected the first building to be finished in 2028.

On Oct. 30, 2026, Helio Capital amended its state air permit application for 118 MTU backup generators of 2,800 kW each, 42 at Building 1, 42 at Building 2 and 34 at Building 3, about 330 MW of standby power by the math. The state water permit is still under review, and DEQ has asked Google for more information. The Army Corps wetlands permit, NAO-2025-01857, is pending.

Who is building the Google Botetourt data center?

Google has not announced its builder. The state stormwater permit for the site, VAR10X539, names The Whiting-Turner Contracting Company as the operator, for 110 acres. Google also picked Whiting-Turner in 2024 to build a $600 million data center in Wasco County, Oregon.

Timmons Group is the environmental and site design consultant and Google's agent on the wetlands and water permits. Kimley-Horn wrote the site stormwater report for R. G. Vanderweil Engineers, and ALL4 is the developer's air permit consultant.

Which equipment makers and utilities are on the Google Botetourt data center?

The air permit application names the equipment. MTU makes the 118 backup generators, Safety Power makes their emissions controls, and Rehlko makes a small generator for the entrance booth. An EVAPCO cooling tower spec sheet is attached to the application, which lists 16 cooling towers at Building 3.

Appalachian Power is bringing the power, and the Western Virginia Water Authority has a utility agreement with Google for water and sewer. 11 firms in all are on the list below.

Who Google hired before

Google has gone back to builders it used before: it picked Whiting-Turner in 2024 to build a $600 million data center in Wasco County, Oregon.

  • Whiting-Turner: builder on Google's $600 million data center in Wasco County, Wasco County, OR, 2024. Also on this job.
  • Holder Construction: builder on Google's Project Peanut data center, Chester, Chesterfield County, VA, 2026.

These are earlier or other jobs for the same owner. They are not counted in the 11 firms on this job.

How do the ways into the Google Botetourt data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Google's Project Raspberry data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobWork is stopped by a court order until the county holds a new public hearing; start with the firms whose trade matches what you sell

Who should go after the Google Botetourt data center?

Generator, switchgear and power reps118 MTU backup generators of 2,800 kW each with Safety Power controls, and about $264 million of Appalachian Power grid work.
Mechanical, HVAC and cooling repsEVAPCO cooling towers in the air permit filing (16 at Building 3), and Vanderweil, the building systems engineer.
Site, concrete and civil suppliersWhiting-Turner, the builder on the 110-acre stormwater permit, with Kimley-Horn and Timmons on the site design.

What should you do next on the Google Botetourt data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Google's Project Raspberry data center in Daleville, Botetourt County.
  3. Watch for the county's new public hearing, which the court ordered before work can go on.

Questions people ask about the Google Botetourt data center

How much is the Google Botetourt data center?

Google has not given a figure. The county's deal requires at least $1 billion of investment for each of three data centers, at least $3 billion in all, as reported.

Why did a judge stop the Google data center in Botetourt County?

On Nov. 23, 2026, a judge ruled the Board of Supervisors broke Virginia's open government law (FOIA) when it approved the deal on June 24, 2025, after discussing it in a closed session and voting without publicly identifying what it was approving. He voided the county's actions since then, ordered construction stopped and ordered a new public hearing.

Is construction stopped on the Google Botetourt data center?

The judge ordered it stopped on Nov. 23, 2026. Crews were still on site that afternoon, and the county said the wind-down could take several more days, possibly a week.

Who is building the Google data center in Botetourt County?

Google has not announced its builder. The state stormwater permit names The Whiting-Turner Contracting Company as the operator. 11 firms are named on the job, listed above.

Where is the Google Botetourt data center?

At the Botetourt Center at Greenfield, 1016 International Parkway, in Daleville, Botetourt County, Virginia.

What is Project Raspberry?

Project Raspberry is the name on the state and Army Corps records for Google's Botetourt County campus. Helio Capital LLC is the developer for Google.

How big is the Google Botetourt data center?

Three data center buildings of about 300,000 sq ft each, three substations and a 28,000 sq ft office on a 343.6-acre parcel.

How many backup generators will the Google Botetourt data center have?

The Oct. 30, 2026 air permit filing lists 118 MTU generators of 2,800 kW each, about 330 MW of standby power by the math.

When will the Google Botetourt data center open?

The county had expected the first building in 2028. The court's Nov. 23 order stopped work until the county holds a new public hearing.

How many jobs will the Google Botetourt data center create?

The county's deal calls for at least 50 full-time jobs per building, at least 150 in all, at a median salary of about $86,000, as reported.

What happens next on the Google Botetourt data center?

The court ordered a new public hearing. The state water and air permits and the Army Corps permit are still under review. We'll update this page when a new record or firm appears.

How we built this list

We read Virginia DEQ's Project Raspberry page and its posted documents, including the Oct. 30, 2026 air permit amendment and the June 26 response to the Army Corps; DEQ's stormwater permit layer; the Army Corps public notice; Botetourt County's Google page and news release; and news reports, all on Nov. 25, 2026. We kept each firm a public record or the news names on this campus. Botetourt County's building permits are not public online, so no county permit values are used. The $3 billion is the deal's minimum as reported ($1 billion per data center, three planned), not a Google figure. The 330 MW is the math (118 x 2,800 kW). MTU, Safety Power, Rehlko and EVAPCO are named in the air permit application as the equipment makers; it does not name dealers or installers, and EVAPCO's spec sheet names its customer only as confidential. Left out: the developer (Helio Capital), a wind farm that sells power to Google off site, the people in the lawsuit and their lawyers, a site work firm seen only in a photo, and two units listed 'or equivalent'. Phones are each firm's own line; Whiting-Turner's is its Baltimore headquarters, Appalachian Power's is its project line, and we found no main line on MTU's or Vanderweil's sites, so we give their websites only. First published Nov. 25, 2026. We'll update this page when a new permit, ruling or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 11 firms, free

All 11 firms on the Google Botetourt data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.