What is Google building in Botetourt County, Virginia?
Google is building a data center campus at the Botetourt Center at Greenfield, a county business park in Daleville. State records call it Project Raspberry. Google LLC is the applicant on the state and Army Corps records, and Helio Capital LLC is the developer for Google on the county and water deals.
The plans show three data center buildings of about 300,000 sq ft each, three substations and a 28,000 sq ft office on a 343.6-acre parcel. The work would disturb 240.4 acres. Google bought about 312 acres for $14 million in June 2025, per the county.
How much is the Google Botetourt data center?
Google has not given a dollar figure. The county's performance agreement requires at least $1 billion of investment for each data center, as reported, and three are planned, so at least $3 billion in all.
The county says the three data centers are expected to bring at least $10 million a year in local taxes. The deal also calls for at least 50 full-time jobs per building at a median salary of about $86,000, as reported. Appalachian Power plans about $264 million of power line and substation upgrades to serve the campus, in a filing with state regulators on Sept. 4, 2026.
Why did a judge stop the Google Botetourt data center?
On Nov. 23, 2026, Substitute Judge Michael Doucette ruled that the Board of Supervisors broke Virginia's open government law (FOIA) when it approved the deal on June 24, 2025. The board discussed the deal in a closed session, then voted 5-0 in open session without discussion, and the judge found it did not reasonably identify what it was voting on. He voided the county's actions on the deal since that date, ordered construction stopped and wrote that the fix is a new public hearing that follows the law.
Crews were still on site that afternoon. On Nov. 24 the county said work could go on for several more days, possibly a week, while crews wind down and secure equipment. Google said it is evaluating next steps, and the county said it is evaluating its options.
How far along was the Google Botetourt data center?
Grading began the second week of September 2026 under the county's land disturbance permit. The county had expected the first building to be finished in 2028.
On Oct. 30, 2026, Helio Capital amended its state air permit application for 118 MTU backup generators of 2,800 kW each, 42 at Building 1, 42 at Building 2 and 34 at Building 3, about 330 MW of standby power by the math. The state water permit is still under review, and DEQ has asked Google for more information. The Army Corps wetlands permit, NAO-2025-01857, is pending.
Who is building the Google Botetourt data center?
Google has not announced its builder. The state stormwater permit for the site, VAR10X539, names The Whiting-Turner Contracting Company as the operator, for 110 acres. Google also picked Whiting-Turner in 2024 to build a $600 million data center in Wasco County, Oregon.
Timmons Group is the environmental and site design consultant and Google's agent on the wetlands and water permits. Kimley-Horn wrote the site stormwater report for R. G. Vanderweil Engineers, and ALL4 is the developer's air permit consultant.
Which equipment makers and utilities are on the Google Botetourt data center?
The air permit application names the equipment. MTU makes the 118 backup generators, Safety Power makes their emissions controls, and Rehlko makes a small generator for the entrance booth. An EVAPCO cooling tower spec sheet is attached to the application, which lists 16 cooling towers at Building 3.
Appalachian Power is bringing the power, and the Western Virginia Water Authority has a utility agreement with Google for water and sewer. 11 firms in all are on the list below.
Who Google hired before
Google has gone back to builders it used before: it picked Whiting-Turner in 2024 to build a $600 million data center in Wasco County, Oregon.
- Whiting-Turner: builder on Google's $600 million data center in Wasco County, Wasco County, OR, 2024. Also on this job.
- Holder Construction: builder on Google's Project Peanut data center, Chester, Chesterfield County, VA, 2026.
These are earlier or other jobs for the same owner. They are not counted in the 11 firms on this job.
How do the ways into the Google Botetourt data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Google's Project Raspberry data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Work is stopped by a court order until the county holds a new public hearing; start with the firms whose trade matches what you sell |
Who should go after the Google Botetourt data center?
| Generator, switchgear and power reps | 118 MTU backup generators of 2,800 kW each with Safety Power controls, and about $264 million of Appalachian Power grid work. |
|---|
| Mechanical, HVAC and cooling reps | EVAPCO cooling towers in the air permit filing (16 at Building 3), and Vanderweil, the building systems engineer. |
|---|
| Site, concrete and civil suppliers | Whiting-Turner, the builder on the 110-acre stormwater permit, with Kimley-Horn and Timmons on the site design. |
|---|
What should you do next on the Google Botetourt data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Google's Project Raspberry data center in Daleville, Botetourt County.
- Watch for the county's new public hearing, which the court ordered before work can go on.
Questions people ask about the Google Botetourt data center
How much is the Google Botetourt data center?
Google has not given a figure. The county's deal requires at least $1 billion of investment for each of three data centers, at least $3 billion in all, as reported.
Why did a judge stop the Google data center in Botetourt County?
On Nov. 23, 2026, a judge ruled the Board of Supervisors broke Virginia's open government law (FOIA) when it approved the deal on June 24, 2025, after discussing it in a closed session and voting without publicly identifying what it was approving. He voided the county's actions since then, ordered construction stopped and ordered a new public hearing.
Is construction stopped on the Google Botetourt data center?
The judge ordered it stopped on Nov. 23, 2026. Crews were still on site that afternoon, and the county said the wind-down could take several more days, possibly a week.
Who is building the Google data center in Botetourt County?
Google has not announced its builder. The state stormwater permit names The Whiting-Turner Contracting Company as the operator. 11 firms are named on the job, listed above.
Where is the Google Botetourt data center?
At the Botetourt Center at Greenfield, 1016 International Parkway, in Daleville, Botetourt County, Virginia.
What is Project Raspberry?
Project Raspberry is the name on the state and Army Corps records for Google's Botetourt County campus. Helio Capital LLC is the developer for Google.
How big is the Google Botetourt data center?
Three data center buildings of about 300,000 sq ft each, three substations and a 28,000 sq ft office on a 343.6-acre parcel.
How many backup generators will the Google Botetourt data center have?
The Oct. 30, 2026 air permit filing lists 118 MTU generators of 2,800 kW each, about 330 MW of standby power by the math.
When will the Google Botetourt data center open?
The county had expected the first building in 2028. The court's Nov. 23 order stopped work until the county holds a new public hearing.
How many jobs will the Google Botetourt data center create?
The county's deal calls for at least 50 full-time jobs per building, at least 150 in all, at a median salary of about $86,000, as reported.
What happens next on the Google Botetourt data center?
The court ordered a new public hearing. The state water and air permits and the Army Corps permit are still under review. We'll update this page when a new record or firm appears.
How we built this list
We read Virginia DEQ's Project Raspberry page and its posted documents, including the Oct. 30, 2026 air permit amendment and the June 26 response to the Army Corps; DEQ's stormwater permit layer; the Army Corps public notice; Botetourt County's Google page and news release; and news reports, all on Nov. 25, 2026. We kept each firm a public record or the news names on this campus. Botetourt County's building permits are not public online, so no county permit values are used. The $3 billion is the deal's minimum as reported ($1 billion per data center, three planned), not a Google figure. The 330 MW is the math (118 x 2,800 kW). MTU, Safety Power, Rehlko and EVAPCO are named in the air permit application as the equipment makers; it does not name dealers or installers, and EVAPCO's spec sheet names its customer only as confidential. Left out: the developer (Helio Capital), a wind farm that sells power to Google off site, the people in the lawsuit and their lawyers, a site work firm seen only in a photo, and two units listed 'or equivalent'. Phones are each firm's own line; Whiting-Turner's is its Baltimore headquarters, Appalachian Power's is its project line, and we found no main line on MTU's or Vanderweil's sites, so we give their websites only. First published Nov. 25, 2026. We'll update this page when a new permit, ruling or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 25, 2026- Cardinal News: judge halts Google data center construction in Botetourt County, orders public hearing (Nov. 23, 2026)
- Roanoke Rambler: a judge stopped Google's Botetourt data center (Nov. 24, 2026)
- WSET: judge rules Botetourt County Google data center deal violated law (Nov. 2026)
- Virginia DEQ: Google's Project Raspberry page and posted documents
- Virginia DEQ: Project Raspberry air permit application amendment (Oct. 30, 2026)
- Virginia DEQ: stormwater permits layer, VAR10X539
- Virginia DEQ: Timmons response to Army Corps comments, with the Kimley-Horn stormwater report (June 26, 2026)
- Army Corps Norfolk District: public notice NAO-2025-01857, Project Raspberry (March 10, 2026)
- WSLS 10: documents reveal key details of proposed Google data center in Botetourt County (March 12, 2026)
- Cardinal News: new details on Botetourt grid upgrades for Google data center (Sept. 16, 2026)
- Cardinal News: Army Corps chose not to hold a public hearing on the Google project (Oct. 30, 2026)
- Botetourt County: Google Data Center page
- Botetourt County news release, March 25, 2026
- Construction Dive, 2024-01-30
- Chesterfield County Accela record 20260728-060