What is being built on I-45 in Houston?
The I-45 North Houston Highway Improvement Project rebuilds I-45 from downtown Houston north to Beltway 8. It also rebuilds the downtown freeway loop, where I-45, I-69, I-10 and SH 288 meet. The Texas Department of Transportation (TxDOT) owns the job.
Downtown, I-45 will be moved off the west side of downtown to run beside I-69 and I-10. The Pierce Elevated would no longer serve traffic. TxDOT broke ground at Pitch 25 in East Downtown on Oct. 28, 2024, and called it one of the largest infrastructure projects in Texas.
How much will the I-45 rebuild cost?
TxDOT calls the project a $13 billion effort. It is a program figure, not money spent. TxDOT's October 2026 estimates for the ten Segment 3 contracts downtown total about $7.5 billion.
The biggest of those are 3C-2, the I-10/I-45/I-69 interchange, at $2.2 billion; 3D-1 at $1,534,414,000; 3C-4 at $1,036,000,000; and 3A at $850,600,000. The two contracts under way were awarded at $695.5 million (3B-2) and $121.9 million (3B-1).
Who is building the I-45 project now?
Williams Brothers Construction holds Segment 3B-2, which rebuilds and widens I-69 from SH 288 to I-45. Crews are building it below ground level, with a pump station, storm sewers and three new arch bridges at Elgin, Tuam and McGowen streets. It won the job on Sept. 5, 2024 with a $695.5 million bid. The only other bidder, Webber, bid $1.25 billion, and TxDOT's estimate was $615.8 million. The bid called for 893,391 cubic yards of roadway digging and 2,001 working days.
Harper Brothers Construction holds Segment 3B-1, a $121.9 million drainage job from St. Emanuel Street to Buffalo Bayou. Its detention pond between Runnels Street and Buffalo Bayou will hold nearly 76 million gallons of stormwater. Crews set 8-foot pipes into a hole 50 feet deep.
How far along is the I-45 work?
TxDOT's payment reports dated Nov. 8, 2026, for work through Oct. 25, show 3B-2 at 34.7% done with $247.9 million paid, and 3B-1 at 73.1% done with $98.7 million paid. That is $346.6 million paid to the two builders, the sum.
The Alabama Street bridge over I-69 came down in May 2026, and the new bridge is due in February 2027. TxDOT expects 3B-1 to finish in early 2028 and 3B-2 in 2033.
Who is bidding the $2.2 billion I-45 interchange?
The next big piece is 3C-2, the I-10/I-45/I-69 interchange, a design-build contract TxDOT estimates at about $2.2 billion. On Oct. 23, 2026, TxDOT posted the three teams that sent qualifications: Fluor Enterprises, Kiewit Infrastructure South and WBCCI, LLC, whose partner is Williams Brothers.
TxDOT plans a conditional award in March 2028. Its procurement summary names 25 engineering, survey and program firms that have worked on 3C-2 and may not join a bidding team. They are on the list below.
Why was the I-45 project paused?
The Federal Highway Administration (FHWA) paused the project in June 2021 over a civil-rights (Title VI) investigation. Harris County had sued over the project's environmental review.
TxDOT signed an agreement with Harris County on Dec. 22, 2022, and the suit was dismissed in January 2023. It signed one with the City of Houston on Dec. 19, 2022 and a Voluntary Resolution Agreement with the FHWA on March 5, 2023. Construction began in October 2024. TxDOT's Nov. 17, 2026 public meeting covered Segments 1 and 2 and its work under that federal agreement.
Who TxDOT hired before
TxDOT's Houston District keeps going back to Williams Brothers, which built its I-610/SH 288 connectors and SH 35 freeway, and to designer IDCUS, which drew SH 35 before NHHIP's 3B segments.
- Ferrovial Construction and Webber: builder (design-build JV) on SH 99 Grand Parkway Segment B-1, about $1.47B, southeast of Houston, TX, 2026.
- Williams Brothers Construction: builder on I-610/Cambridge, $117M, with eight direct connect tie-ins at I-610/SH 288, Houston, TX, 2025. Also on this job.
- Williams Brothers Construction: builder on SH 35 Griggs Road to I-45/Spur 5, $93.9M, Houston, TX, 2023. Also on this job.
- IDCUS: designer on SH 35 Griggs Road to I-45/Spur 5, Houston, TX, 2024. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 30 firms on this job.
How do the ways into the I-45 rebuild compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the I-45 North Houston Highway project | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The contracts still to be awarded | A place on a team going after the 3C-2 interchange or a later Segment 3 contract | Builders and big subcontractors | A share of contracts TxDOT estimates at $157.5 million to $2.2 billion each | No award yet; firms on TxDOT's 3C-2 conflict list may not join a bidding team |
Who should go after the I-45 rebuild?
| Concrete, pipe, rebar and site suppliers | Williams Brothers on the $695.5 million I-69 job, with 893,391 cubic yards of digging bid, a pump station and three arch bridges; Harper Brothers on the drainage job with 8-foot storm pipes and box culverts. |
|---|
| Engineering, survey and testing firms | IDCUS, Aviles and AECOM on the active segments, and the 25 firms TxDOT names on its 3C-2 interchange work. |
|---|
| Builders and big subcontractors | The $2.2 billion 3C-2 interchange, where Fluor, Kiewit and Williams Brothers sent qualifications, and later downtown contracts such as 3D-1 ($1.53 billion) and 3C-4 ($1.04 billion). |
|---|
What should you do next on the I-45 rebuild?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the I-45 North Houston Highway Improvement Project, Segment 3B-2 or 3B-1.
- Watch TxDOT's Dec. 10, 2026 Segment 3 meeting and the 3C-2 interchange award, planned for March 2028.
Questions people ask about the I-45 rebuild
How much will the I-45 rebuild in Houston cost?
TxDOT calls the I-45 North Houston Highway Improvement Project a $13 billion effort. It is a program figure, not money spent. TxDOT's October 2026 estimates for the ten Segment 3 contracts downtown total about $7.5 billion.
Who is building the I-45 project?
TxDOT owns the job. Williams Brothers Construction holds the $695.5 million Segment 3B-2 contract on I-69, and Harper Brothers Construction holds the $121.9 million Segment 3B-1 drainage contract. 30 firms are named on the job, listed above.
How far along is the I-45 construction?
TxDOT's reports dated Nov. 8, 2026 show Segment 3B-2 at 34.7% done with $247.9 million paid, and Segment 3B-1 at 73.1% done with $98.7 million paid.
Who bid on the I-45 Segment 3B-2 contract?
Two firms. Williams Brothers Construction bid $695.5 million and Webber bid $1.25 billion on Sept. 5, 2024. TxDOT's own estimate was $615.8 million.
Who is going after the I-45 downtown interchange contract?
Three teams sent qualifications for the 3C-2 design-build contract, the I-10/I-45/I-69 interchange, on TxDOT's list posted Oct. 23, 2026: Fluor Enterprises, Kiewit Infrastructure South and WBCCI, LLC, with Williams Brothers. TxDOT estimates it at about $2.2 billion and plans a conditional award in March 2028.
Why was the I-45 project paused?
The Federal Highway Administration paused it in June 2021 over a civil-rights (Title VI) investigation, and Harris County had sued over the environmental review. TxDOT then signed agreements with Harris County, the City of Houston and the FHWA, and construction began in October 2024.
When will the I-45 work finish?
TxDOT expects Segment 3B-1 to finish in early 2028 and Segment 3B-2 in 2033. TxDOT plans to sign the 3C-2 interchange contract in 2028, with that work running about seven and a half years.
When is the next I-45 public meeting?
TxDOT holds a virtual public meeting on Segment 3 on Dec. 10, 2026, from 5 to 7 p.m. Comments are due Jan. 5, 2027. Its last meetings, on Segments 1 and 2, were Nov. 17 and 18, 2026.
How can subcontractors get on the I-45 rebuild?
Call the firms already on the job, starting with Williams Brothers on Segment 3B-2 and Harper Brothers on Segment 3B-1. For the $2.2 billion interchange, the way in is one of the three teams that sent qualifications. The 25 firms on TxDOT's 3C-2 conflict list may not join a bidding team.
Which engineering firms work on the I-45 project?
IDCUS is the design firm of record for Segments 3B-1 and 3B-2, Aviles Engineering wrote the 3B geotechnical report, and AECOM is lead designer for Segment 3C-4. TxDOT also names 25 engineering, survey and program firms on its 3C-2 work.
What happens next on the I-45 rebuild?
The new Alabama Street bridge is due in February 2027, TxDOT meets the public on Segment 3 on Dec. 10, 2026, and the 3C-2 interchange contract is set for a conditional award in March 2028. We'll update this page when a new contract or firm appears.
How we built this list
We read TxDOT's Oct. 28, 2024 news release; its payment reports for both active contracts dated Nov. 8, 2026; its November 2026 meeting exhibits for Segments 3B-1, 3B-2 and 3; the September 2024 bid tabulation; the 3C-2 request for qualifications page, procurement summary and industry workshop; the Nov. 17 and Dec. 10, 2026 meeting notices; a TxDOT procurement forum presentation; Texas accessibility registrations; the 3B geotechnical report in TxDOT's bid file; and AECOM's release, all read Nov. 25, 2026. We kept each firm a public record names on this project. Five have a stated role; 25 are on the list because TxDOT names them on its 3C-2 conflict list, and TxDOT does not say what each one did. The $346.6 million paid is the sum of the two payment reports. Left out: TxDOT and the City of Houston (owners), losing bidders (Webber on 3B-2; Posillico and MC2 Civil on 3B-1), the three 3C-2 teams as teams (Fluor and Kiewit are proposers, not hired), financial advisers, lawyers, a public relations firm, a utility, an accessibility reviewer and a supplier seen only in a photo. No subcontractor list is public. Phones are each firm's own line from its own site; AECOM's is its Dallas main line and LJA's is LJA Engineering's main line. We found no website for Harper Brothers Construction and no main line on the sites of several firms. First published Nov. 25, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 25, 2026- TxDOT: I-45 construction begins in Houston (Oct. 28, 2024)
- TxDOT: payment report, Segment 3B-2 contract 0027-13-200 (Nov. 8, 2026)
- TxDOT: payment report, Segment 3B-1 contract 0177-11-161 (Nov. 8, 2026)
- TxDOT: Segment 3B-2 exhibit, November 2026 public meetings
- TxDOT: Segment 3B-1 exhibit, November 2026 public meetings
- TxDOT: Segment 3 general update exhibit, November 2026
- TxDOT: Segment 3B-2 overview
- TxDOT: bid tabulations, September 2024 letting
- TxDOT: NHHIP 3C-2 request for qualifications (list posted Oct. 23, 2026)
- TxDOT: NHHIP 3C-2 project status and procurement summary (Feb. 27, 2026)
- TxDOT: NHHIP 3C-2 industry workshop (Aug. 10, 2026)
- TxDOT: I-45 presentation at the Greater Houston Business Procurement Forum
- TxDOT: Segments 1 and 2 public meeting notice (Nov. 17, 2026)
- TxDOT: December 10, 2026 public meeting notice
- TDLR: TABS2024020815, IH 69 (CSJ 0027-13-200)
- TxDOT: geotechnical baseline report, NHHIP IH 69 Segment 3B (April 2024)
- AECOM: selected as lead designer for NHHIP Segment 3C-4 (Oct. 8, 2024)
- ENR: Ferrovial, Webber Win $1.47B Grand Parkway Design-Build in Texas (May 14, 2026)
- Construction Equipment Guide: Williams Bros. Delivers I-610 Project On Time (Aug. 5, 2025)
- Construction Equipment Guide: Williams Brothers Constructs Houston Freeway (July 10, 2024)