Who's building Google's data center in Van Buren Township, Michigan

Google's $2 billion data center in Van Buren Township is stopped after Wayne County ordered work halted, saying its developer never got a county construction permit.

By Porter Stanley. Updated .

Google is building a data center campus of up to 1 gigawatt, called Project Cannoli, at Haggerty Road and I-94 in Van Buren Township, Wayne County, Michigan. Google has given no cost, but its developer, Panattoni, says site construction would bring $2 billion in contracts to businesses in Wayne County. Detroit-based Walbridge is set to build it. On Nov. 20, 2026, Wayne County ordered all work stopped, saying Panattoni never got a county construction permit; work stopped the next day. 12 firms are named on the job; the list below has all 12.

$2BContracts Panattoni says the job brings to Wayne County firms
Nov. 20Wayne County's stop-work order
1 GWPlanned power, up to 1 gigawatt
12Firms named on the job

Get all 12 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 12 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 12 firms on the Google Van Buren Township data center?

We list the 12 firms named on Google's Project Cannoli data center in Van Buren Township, one row each, strongest tie first, with what each one does on the job and where its name comes from.

1Named in the newsOct 15, 2026

Walbridge

Builder set to build the campus, a news report says; Panattoni's named construction partner on the job on Google's Project Cannoli data center in Van Buren Township, Wayne County, MI

Google's Project Cannoli data center campus, Haggerty Rd and I-94, Van Buren Township (Wayne County), MI

Panattoni says site construction would bring $2 billion in contracts to businesses in Wayne County; about 1,500 construction jobs during the build

Work: Builder set to build the campus, a news report says; Panattoni's named construction partner on the job

Who to call: Walbridge
Walbridge office line
(Detroit, MI)
(313) 963-8000

The opportunity: Panattoni's Adam Kramer 'emphasized his company's partnership with Detroit-based contractor Walbridge Construction' (Oct. 15, 2026). Walbridge, the lead contractor on Oracle and OpenAI's Stargate data center in Saline Township, 'is set to build the Google site, too' (Oct. 14, 2026).

2Named in the newsNov 24, 2026

Panattoni Development Company

Developer managing construction of the campus for Google; the firm named on Wayne County's stop-work order on Google's Project Cannoli data center in Van Buren Township, Wayne County, MI

Google's Project Cannoli data center campus, Haggerty Rd and I-94, Van Buren Township (Wayne County), MI

Site plan case VBT-25-041, final approval Oct. 14, 2026 (5-1); 6 buildings, 973,247 sq ft footprint on 282.2 acres

Work: Developer managing construction of the campus for Google; the firm named on Wayne County's stop-work order

Who to call: Panattoni Development Company
Panattoni Development Company office line
(Dallas, TX)
(214) 367-3008

The opportunity: Wayne County's Department of Public Services 'says the developer, Panattoni, never secured proper county construction permits.' Panattoni says 'our team is working directly with county officials to review the items outlined.' The site plan lists Panattoni's Dallas office at (214) 367-3008.

3Latest recordAug 20, 2026

Corby Energy Services, Inc.

Utility contractor on ITC's right-of-way work for the campus, with a temporary laydown yard at Haggerty Road and I-94 on Google's Project Cannoli data center in Van Buren Township, Wayne County, MI

Google's Project Cannoli data center campus, Haggerty Rd and I-94, Van Buren Township (Wayne County), MI

Township temporary land use case VBT-26-013; laydown yard Oct. 15, 2026 to Sept. 30, 2027

Work: Utility contractor on ITC's right-of-way work for the campus, with a temporary laydown yard at Haggerty Road and I-94

Who to call: Corby Energy Services, Inc.
Corby Energy Services office line
(734) 547-0340

The opportunity: A township memo in the Oct. 14, 2026 planning commission packet: 'Corby Energy reached out to us inquiring about using the property as a lay down yard for utility work associated with the ITC right of way work for the data center project.'

What is Google building in Van Buren Township, Michigan?

Google is building a data center campus in Van Buren Township, Wayne County, about four miles west of Detroit Metro Airport. Township records call it Project Cannoli. The site is 282 acres between I-94 and I-275, east of Haggerty Road and west of Hannan Road.

The final site plan shows six buildings with a total footprint of 973,247 sq ft on 282.2 acres: three data center buildings, two network service buildings and an office. About 150 acres will be built on and about 130 left open. A 345 kV switching station, which DTE and ITC applied for, sits on the site. Google expects it to start drawing power by late 2027, at up to 1 gigawatt.

How much is the Google Van Buren Township data center?

Google has given no cost. Panattoni's Adam Kramer said site construction would bring $2 billion in contracts to businesses in Wayne County, and news reports call it a more than $2 billion project.

Wayne County approved a $125 million local tax break, 50% for 12 years. Commissioners overrode the county executive's veto of it by a 13-0 vote. The deal also brings $15.4 million to the township and a $15 million county benefits fund. Panattoni says the build will create about 1,500 construction jobs, and at least 51 permanent jobs are guaranteed.

Why did Wayne County stop work on the Google data center?

On Friday, Nov. 20, 2026, Wayne County's Department of Public Services issued a stop-work order. It says the developer, Panattoni, never got a county construction permit, and that the work hit county drains, easements and road right-of-way. "This unauthorized activity creates significant risks of flooding," the county said.

On the Thursday before the order, county officials tried to inspect the site and were denied access, a news report says. Work stopped Saturday morning, Nov. 21. Panattoni says "our team is working directly with county officials to review the items outlined." Work stays stopped until the county issues a construction permit and drain agreements.

How far along is the Google Van Buren Township data center?

The township gave final site plan approval on Oct. 14, 2026, by a 5-1 vote. Crews had already cleared trees and graded the site, and foundation pouring for the buildings began the week of Oct. 26. The state issued wetland, stream crossing and air permits, and Wayne County issued soil erosion permits, but not the county construction permit the order says is missing.

The power side is in a fight of its own. State regulators approved DTE's 20-year contracts for the campus on Oct. 1, 2026. Attorney General Dana Nessel asked for a rehearing on Oct. 30. If Google gets out of the deal, it owes a $2.5 billion termination payment.

Who is building the Google Van Buren Township data center?

Panattoni Development Company is the developer and manages construction for Google. Detroit-based Walbridge, the lead contractor on Oracle and OpenAI's Stargate data center in Saline Township, is set to build the Google site, a news report says, and Panattoni calls it its construction partner on the job.

On the power side, ITC is building a 345 kV switching station and two 345 kV feeds for the campus, with work along the I-94 service drive, with work expected to last at least until the end of the year. Corby Energy Services is a utility contractor on ITC's right-of-way work and has a laydown yard at Haggerty Road and I-94 through September 2027. DTE Electric is the utility and applied, with ITC, for the on-site switching station.

Which engineers are on the Google Van Buren Township data center?

Kimley-Horn is the civil engineer and landscape architect on the site plans and did the noise studies for Panattoni. PEA Group did the land survey, Schnabel Engineering is the geotechnical engineer, and Tetra Tech wrote the trip generation report.

Three firms work for the township, not the builder: Fishbeck is the township's engineer, McKenna is its planner, and Soundscape Engineering peer-reviewed Kimley-Horn's noise study for Fishbeck. No concrete, steel, electrical or mechanical subcontractors are public yet. 12 firms in all are on the list below.

Who Google hired before

Google spreads its data center campuses across a handful of big national builders, often two at once on one campus. None of them is named at Van Buren; here the developer Panattoni brought in Detroit's Walbridge, Michigan's other megacampus builder (Saline Township's Stargate).

  • Mortenson: builder on Paysage data center campus, Cedar Rapids, IA, 2025-2026.
  • JE Dunn Construction: builder on Midlothian data center, MDN5A/6A, Midlothian, TX, 2026.
  • Whiting-Turner: builder on Midlothian data center, first buildings and MDN 3A, Midlothian, TX, 2018-2024.
  • Holder Construction: builder on Fort Wayne data center campus, Fort Wayne, IN, 2024.
  • H. J. Russell & Company: builder (JV partner) on Midlothian MDN 3A, Midlothian, TX, 2024.

These are earlier or other jobs for the same owner. They are not counted in the 12 firms on this job.

How do the ways into the Google Van Buren Township data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Google's Project Cannoli data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobWork is stopped until Wayne County issues a construction permit; start with the firms whose trade matches what you sell

Who should go after the Google Van Buren Township data center?

Concrete, steel and site suppliersWalbridge, which is set to build the campus; foundations were being poured from late October.
Electrical, power and underground utility repsITC and Corby Energy Services on the 345 kV tie-in and underground feeds, and DTE Electric on the on-site switching station, on a campus planned for up to 1 gigawatt.
Engineering, survey and testing firmsKimley-Horn, PEA Group, Schnabel Engineering and Tetra Tech on the builder's side; Fishbeck, McKenna and Soundscape review the plans for the township.

What should you do next on the Google Van Buren Township data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Google's Project Cannoli data center at Haggerty Road and I-94 in Van Buren Township.
  3. Watch for Wayne County's construction permit, which restarts the work.

Questions people ask about the Google Van Buren Township data center

How much is the Google Van Buren Township data center?

Google has given no cost. Panattoni, the developer, says site construction would bring $2 billion in contracts to businesses in Wayne County, and news reports call it a more than $2 billion project. Wayne County approved a $125 million tax break for it.

Why did Wayne County stop work on the Google data center?

On Nov. 20, 2026, Wayne County's Department of Public Services issued a stop-work order. It says the developer, Panattoni, never got a county construction permit, and that crews worked in county drains, easements and road right-of-way. The county said: "This unauthorized activity creates significant risks of flooding." Work stopped Saturday, Nov. 21.

Who is building the Google data center in Van Buren Township?

Panattoni Development Company is the developer, and Detroit-based Walbridge is set to build it. ITC and Corby Energy Services are doing the power line work along the I-94 service drive. 12 firms are named on the job, listed above.

Where is the Google Van Buren Township data center?

It is on 282 acres east of Haggerty Road, north of the I-94 service drive, west of Hannan Road and south of I-275 in Van Buren Township, Wayne County, Michigan, about four miles west of Detroit Metro Airport.

What is Project Cannoli?

Project Cannoli is the name on Van Buren Township's records for Google's data center campus. The township gave final site plan approval on Oct. 14, 2026, by a 5-1 vote.

How big is the Google Van Buren Township data center?

Six buildings with a total footprint of 973,247 sq ft on 282.2 acres: three data center buildings, two network service buildings and an office. About 150 acres will be built on and about 130 left open. It is planned for up to 1 gigawatt of power.

How far along is the Google Van Buren Township data center?

Crews cleared trees, graded the site and began pouring foundations the week of Oct. 26, 2026. All work stopped on Nov. 21 after the county's stop-work order. It stays stopped until the county issues a construction permit and drain agreements.

When will the Google Van Buren Township data center open?

Google expects the data center to start drawing power by late 2027.

How many jobs will the Google Van Buren Township data center create?

Panattoni says about 1,500 construction jobs during the build, and at least 51 permanent jobs are guaranteed.

Why is Michigan's attorney general fighting the Google DTE deal?

State regulators approved DTE's 20-year power contracts for the campus on Oct. 1, 2026. Attorney General Dana Nessel asked for a rehearing on Oct. 30. If Google gets out of the deal, it owes a $2.5 billion termination payment.

What happens next on the Google Van Buren Township data center?

Panattoni says it is working directly with county officials on the items in the order. Work stays stopped until the county permit is issued. We'll update this page when a new permit or firm appears.

How we built this list

We read Van Buren Township's Project Cannoli page, its Oct. 14, 2026 planning commission packet, the April 2026 site plan set, and the township engineer's and planner's review letters, plus news reports and Panattoni's project page, all on Nov. 25, 2026. We kept each firm a public record or news report names on this campus. Fishbeck, McKenna and Soundscape Engineering are on the list because township records name them, but they review the plans for the township, not for Google or Panattoni. The $2 billion is Panattoni's figure for construction contracts, not a Google figure; Google has given no cost. The township's building permits are not online without an account, so no trade subcontractors (concrete, steel, electrical, mechanical) are public yet. Left out: Google (the owner), the landowner, the water authority (no construction role found), an economic development group, a firm in our own tracker with no record tying it to this job, a testing firm whose only work was at a different site in Ohio, and individuals. Phones are each firm's own main or office line from its own site or letterhead; Panattoni's is its Dallas office. Schnabel's and Tetra Tech's sites gave no main line, so we give their websites only. ITC's 345 kV switching station and feeds are from ITC's own project page. First published Nov. 25, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 12 firms, free

All 12 firms on the Google Van Buren Township data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.