What is being built at the Austin Convention Center?
The City of Austin closed its 1992 convention center at the end of March 2025 and tore it down. The center brings in hundreds of thousands of visitors for conventions, festivals and live events, and it is the home of SXSW. A new center is going up on the same five-and-a-half downtown blocks at 500 E. 3rd St.
The new building goes down, not out. The exhibit halls and loading docks sit below ground. The state registration lists 1,358,099 sq ft, and rentable space grows from about 365,000 to 620,000 sq ft. The roof will rest on 17 mass timber trusses, each about 180 feet long.
How much does the new Austin Convention Center cost?
The city's approved project budget is $1.6 billion, and the city says it has not changed since the council first approved it. The city's dashboard, current as of Oct. 31, 2026 and posted Nov. 24, shows $1.326 billion under contract and $373 million paid.
The four main building permits each state $812,383,209. The city split the main building permit into four parts, so that is one valuation repeated on each part, not four values to add up. The state registration lists an estimated construction cost of $1,260,000,000.
Opponents use a different number. Austin United PAC called it a "$5.6 billion, 32-year debt-financed project." That is the group's own figure for the cost with financing, not the city's budget.
Who is building the new Austin Convention Center?
JE Dunn Construction and Turner Construction formed a 50-50 joint venture to build it, with JE Dunn as managing partner. Turner announced the award on Nov. 7, 2023 as a $1.2 billion contract. On Oct. 23, 2025, the council added $450 million to that contract, for excavation, street and mobility work and for Austin Energy's district cooling plant next to the site.
Trifecta Services Company took down the old 881,400 sq ft building under a demolition permit from Apr. 17, 2025. Fuerte Electric moved Cap Metro rail equipment for the job in late 2025.
Which permits has the city issued for the new center?
On Oct. 19, 2026, the city issued JE Dunn Construction the four main building permits, 2026-137243 to 2026-137246 BP, one for each area of the building. The four areas add 876,455 new sq ft over 5 floors.
The trade permits came next. The Porter Co. got the plumbing permits for all four areas on Nov. 4, 2026. Prism Electric got electrical permits 2026-137243, 2026-137245 and 2026-137246 EP for Areas 1, 3 and 4 on Nov. 9. The Area 2 electrical permit and the mechanical permits were not issued yet when we checked on Nov. 25.
How far along is the Austin Convention Center rebuild?
As of Oct. 31, 2026, the job was 22.48% done by dollars, and excavation was 99.71% complete. Crews hauled out 951,000 cubic yards of soil, with an average of more than 400 trucks a day leaving the site for about 12 months.
Vertical steel began in September 2026 and three cranes are up. Crews poured concrete overnight in the pit on Nov. 24 and 25. The final mass timber lift will raise three trusses at once in a 240,000-pound pick.
A trade magazine reported on Nov. 25, 2026 that the project remains on schedule and on budget as of fall 2026. The city plans substantial completion in December 2028 and a projected opening in spring 2029.
Why did a group try to stop the Austin Convention Center?
Austin United PAC ran a petition to force a public vote on the project. The petition fell short. A judge sided with the city in February 2026, and the PAC said it would push for a November election.
On April 2, 2026, the Texas Supreme Court turned down the group's request. Work kept going the whole time, and the dig is now done.
Who designed the new Austin Convention Center?
LMN Architects of Seattle leads the design in a joint venture with Page Southerland Page, now part of Stantec. Page is the design firm on the state registration. Jobe Corral Architects is an associate architect.
Magnusson Klemencic Associates leads structural engineering, and M-E Engineers leads the mechanical, electrical and plumbing design. Ten Eyck handles the landscape, Horton Lees Brogden the lighting, Atelier Ten sustainability and Studio Matthews the signs. Project Control works for the city on cost and schedule. 16 firms in all are on the list below.
Who the Austin Convention Center hired before
The city has hired these builders on its convention center campus before: the 2000 expansion, the convention hotel next door (built for the city's hotel corporation), and this fall's garage repair at its other venue, paid from the convention center's capital budget.
- Jay-Reese Contractors, Inc.: builder on Palmer Events Center Garage Structural Repairs, paid from the Austin Convention Center's capital budget, Austin, TX, 2026.
- SpawGlass Contractors Inc: builder on Addition to the Austin Convention Center ($66.6M permit), the 2000-2002 expansion, Austin, TX, 2000.
- Landmark Organization: builder on Hilton Austin, the convention center hotel ($52M shell permit), Austin, TX, 2002.
These are earlier or other jobs for the same owner. They are not counted in the 16 firms on this job.
How do the ways into the Austin Convention Center rebuild compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Austin Convention Center rebuild | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The builder's later packages | A bid to the JE Dunn/Turner joint venture on work it has not yet bought | Trade subcontractors and suppliers | A share of the job; a city deck from April 2026 expected a fifth package of about $113 million | We found no public list of open packages, so ask the joint venture what is still open |
Who should go after the Austin Convention Center rebuild?
| Electrical distributors and gear reps | Prism Electric on the new building's electrical permits (Areas 1, 3 and 4), and Fuerte Electric from the Cap Metro rail work. |
|---|
| Plumbing and mechanical reps | The Porter Co., with the plumbing permits for all four areas. No mechanical permit is issued yet, so the mechanical work is still ahead. |
|---|
| Steel, concrete and timber suppliers | The JE Dunn/Turner joint venture, now pouring foundations, setting steel and getting ready to lift 17 mass timber roof trusses. |
|---|
What should you do next on the Austin Convention Center rebuild?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Austin Convention Center rebuild at 500 E. 3rd St. in Austin.
- Watch for the Area 2 electrical permit and the mechanical permits, which were not issued as of Nov. 25, 2026.
Questions people ask about the Austin Convention Center rebuild
How much does the new Austin Convention Center cost?
The city's approved project budget is $1.6 billion, and the city says it has not changed since the council first approved it. As of Oct. 31, 2026, $1.326 billion was under contract and $373 million was paid.
Who is building the new Austin Convention Center?
A 50-50 joint venture of JE Dunn Construction and Turner Construction, with JE Dunn as managing partner, is the construction manager at risk. It was awarded a contract of up to $1.2 billion in 2023, and the council added $450 million on Oct. 23, 2025, partly for street work and an Austin Energy cooling plant. 16 firms are named on the job, listed above.
When will the new Austin Convention Center open?
The city plans substantial completion in December 2028 and a projected opening in spring 2029. The old building closed at the end of March 2025 and has been torn down.
How far along is the Austin Convention Center rebuild?
The city's dashboard, current as of Oct. 31, 2026, puts it at 22.48% done by dollars, with excavation 99.71% complete. Vertical steel began in September 2026 and three cranes are up. A trade magazine reported on Nov. 25 that it remains on schedule and on budget as of fall 2026.
Is the Austin Convention Center a $5.6 billion project?
No. $5.6 billion is the figure used by Austin United PAC, the group that tried to force a vote, for what it called a 32-year debt-financed project. The city's approved project budget is $1.6 billion.
Did Austin voters get to vote on the convention center?
No. A petition to force a public vote fell short. A judge sided with the city in February 2026, and on April 2, 2026 the Texas Supreme Court turned down the group's request.
What are the building permits for the new Austin Convention Center?
Four main building permits, 2026-137243 to 2026-137246 BP, were issued to JE Dunn Construction on Oct. 19, 2026. Each states a valuation of $812,383,209, which is one valuation repeated on each of the four parts, not four values to add up.
Who has the electrical and plumbing permits?
Prism Electric received electrical permits for Areas 1, 3 and 4 on Nov. 9, 2026. The Porter Co. received plumbing permits for all four areas on Nov. 4, 2026. No mechanical permit for the new building was issued as of Nov. 25, 2026.
How big is the new Austin Convention Center?
The state registration lists 1,358,099 sq ft. Rentable space grows from about 365,000 to 620,000 sq ft, with the exhibit halls and loading docks below ground and 17 mass timber roof trusses about 180 feet long.
Who designed the new Austin Convention Center?
LMN Architects of Seattle leads the design in a joint venture with Page (now Stantec), the architect of record. The team also includes Magnusson Klemencic Associates for structure, M-E Engineers for MEP, and Jobe Corral Architects as associate architect.
What happens next on the Austin Convention Center?
Crews are pouring foundations, with overnight concrete pours on Nov. 24 and 25, and setting steel. The Area 2 electrical permit and the mechanical permits are still to come. We'll update this page when a new permit or firm appears.
How we built this list
We read the City of Austin's open permit data for the site (500 E. Cesar Chavez St. and 500 E. 3rd St.), the state building registration, the city's UnconventionalATX project site and its Oct. 31, 2026 dashboard, LMN's, Turner's, JE Dunn's and Trifecta's own pages, a city deck from April 2026, a Texas Supreme Court order and news reports, all on Nov. 25, 2026. We kept each firm a public record names on this project with a clear role. The permits name the builder, the electrical, plumbing and demolition firms; the design team comes from LMN's own project page. Contract values for the joint venture are for the whole team, not one firm's share. The $812,383,209 on each main building permit is one valuation repeated on each of the four parts and is never added up. Left out: the city and its departments (the owner), public utilities, outreach and strategy firms, an individual accessibility reviewer, the public artists, firms named only by short names (RLB, Square One, Garza, and the engineering sub-consultants), a plumbing firm that only capped lines at the old building, and a foundation firm named only in a post we could not open. No public record we found names a mechanical, fire or steel subcontractor. Phones are each firm's own line from its own site, except Page's, from the state registration, and Fuerte's, from its city permit; M-E Engineers' is its Houston office and LMN's, MKA's and Studio Matthews' are Seattle lines. Ten Eyck, Horton Lees Brogden, Atelier Ten and Project Control show no main line we could verify, so we give their websites only. First published Nov. 25, 2026. We'll update this page when a new permit, contract or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 25, 2026- City of Austin, UnconventionalATX: permitting process (Nov. 2026)
- City of Austin, UnconventionalATX: project dashboard as of Oct. 31, 2026 (posted Nov. 24, 2026)
- City of Austin, UnconventionalATX: site progress (Oct. 2026)
- City of Austin, UnconventionalATX: construction alerts, week of Nov. 22, 2026
- City of Austin, UnconventionalATX: project partners (read Nov. 25, 2026)
- City of Austin, UnconventionalATX newsletter Vol. 5 (July 2025)
- City of Austin open data: building permit 2026-137243 BP
- City of Austin open data: electrical permit 2026-137243 EP
- City of Austin open data: plumbing permit 2026-137243 PP
- City of Austin open data: electrical permit 2025-100315 EP
- City of Austin open data: demolition permit 2025-045449 BP
- Texas Department of Licensing and Regulation: TABS2026016783
- LMN Architects: Austin Convention Center Redevelopment project page (read Nov. 25, 2026)
- Turner Construction: $1.2 billion Austin Convention Center contract awarded (Nov. 7, 2023)
- JE Dunn: Austin Convention Center Redevelopment project page
- Trifecta Services Company homepage (read Nov. 25, 2026)
- Texas Contractor: JE Dunn and Turner dig deep to rebuild the Austin Convention Center (Nov. 2026)
- Construction Executive: Austin Convention Center gets an unconventional upgrade (Nov. 25, 2026)
- Community Impact: hundreds of millions approved for the convention center redevelopment (Oct. 24, 2025)
- Community Impact: court sides with Austin in convention center petition dispute (Feb. 16, 2026)
- Supreme Court of Texas: orders of April 2, 2026
- Austin City Council, Sept. 24, 2026 consent item
- City of Austin open data, permit 2000-008808 BP
- City of Austin open data, permit 2002-013947 BP