What is Nebius building in Independence, Missouri?
Nebius is building an AI data center campus, which it calls an AI factory, at 251 N Bly Road in the EastGate Commerce Center in Independence. The site sits near Little Blue Parkway and Missouri 78 in Jackson County. It is Nebius's first gigawatt-scale campus in the U.S., and a different site from its data centers in Birmingham, Alabama and Vineland, New Jersey.
The first building is about 490,000 sq ft and 200 MW. The full plan is up to four buildings and 1.2 GW on about 400 acres. NorthPoint Development sold the 398-acre site to Nebius on Dec. 5, 2025. Nebius broke ground on May 12, 2026, as residents protested outside the fence.
How much is the Nebius Independence data center?
The city puts land and site work for the 400-acre campus at $6.6 billion, plus tens of billions of dollars in equipment. Nebius itself calls the site a multi-billion-dollar investment across four buildings.
On March 2, 2026, the city council voted 5-2 to approve up to $150.6 billion in Chapter 100 bonds for the campus. That is a ceiling for the bonds, not the cost of the job. The deal also sets a $651 million payment in lieu of taxes over 20 years.
The 12 city permits on the site add up to $1,120,926,816, the sum. One foundation permit has the same value as another and may be a duplicate filing; without it, the sum is about $1.0 billion. Each permit value is what was declared to the city for that work, not Nebius's total spend.
Which city permits are on the Nebius campus?
The biggest is 2026-02480, $700,659,985 for the inside of Building 1, issued Oct. 2, 2026 to ARCO National Holdings. Its permit fee alone was $9,284,471.50. The Building 1 shell, 2026-01973, is $106,320,497, issued Aug. 13. Two foundation permits, 2026-01395 and 2026-01844, are $118,765,000 each.
The power gear has its own permits at 301 N Bly Road: a $31,691,000 permit for the 161 kV substation (2026-02544), issued Nov. 3, and a $10,417,000 permit for the 161 kV switchyard (2026-02541), issued Oct. 5. Building 1 also has an $8,779,970 fire sprinkler permit and a $6,439,504 pump house permit. An $18,149,260 fire alarm permit filed Oct. 27 is not yet issued.
Who is building the Nebius Independence data center?
ARCO National Construction is the general contractor for Phase 1. ARCO says it will deliver the first building, and it is the only contractor named on the site's city permits. The substation and switchyard permits name no outside contractor. No trade subcontractor is named in any public record we found.
Nebius's January 2026 city presentation named its delivery team: HKS as architect, Affiliated Engineers, a mechanical, electrical and plumbing engineering firm, and NorthPoint Development. NorthPoint is also overseeing the rerouted Bly Road, with Superior Bowen as lead contractor.
About 1,200 construction jobs are expected, mostly through local union building trades. Nebius says about 400 electricians will be on site at peak.
Why are neighbors suing over the Nebius data center?
On Aug. 12, 2026, the Independence GUARD Alliance filed a 16-count, 52-page lawsuit in Jackson County Circuit Court, hoping to stop the job. It names the city, Nebius's Missouri ADC Holdings and Independence Power Partners. A hearing on a restraining order was set for Oct. 22; we found no ruling, and ARCO keeps building.
Bly Road is the only road in and out of the neighborhood next to the campus. It closed April 1, 2026 for the reroute and partly reopened Nov. 6. More than seven months after it closed, the work is still not done. A Nov. 6 letter from NorthPoint, signed with Superior Bowen, says it should finish the first week of December.
Where will the Nebius campus get its power?
The campus connects to Independence Power & Light, the city's own utility, under an energy service agreement signed Dec. 5, 2025. The plan is 800 MW through the utility and 400 MW made on site.
The 800 MW is to come from Independence Power Partners, a privately financed gas plant at the retired Blue Valley Power Plant site: 225 MW in its first phase with 15 turbines, and up to about 800 MW. United Energy Trading and Exigent Energy own it together. Until it opens, NextEra supplies about $10.7 million of energy from June 2026 to May 2027, and Evergy about $5.6 million from June to November 2027. 11 firms in all are on the list below.
Who Nebius hired before
Nebius's two other U.S. AI factories went to different builders: Hoar Construction and big Southeast trade firms in Birmingham, a local precast maker and fuel-cell and gas crews in Vineland. Independence is ARCO's job, so none of them is on this list yet.
- Hoar Construction: general contractor on Nebius BHM01 AI data center, phase 2 shell ($2.04B permit), Birmingham, AL, 2026.
- Marathon Electrical Contractors: electrical on Nebius BHM01 ($315M electrical permit), Birmingham, AL, 2026.
- Batchelor & Kimball, Inc.: mechanical on Nebius BHM01 ($303.1M mechanical permit), Birmingham, AL, 2026.
- Northeast Precast: builder (construction lead) on Nebius AI data center campus built by DataOne, Vineland, NJ, 2026.
- Bloom Energy: on-site fuel-cell power on Nebius AI data center campus (about 250 MW guaranteed fuel-cell capacity), Vineland, NJ, 2026.
- Kiely Family of Companies: natural gas infrastructure on Nebius AI data center campus built by DataOne, Vineland, NJ, 2026.
These are earlier or other jobs for the same owner. They are not counted in the 11 firms on this job.
How do the ways into the Nebius Independence data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Nebius data center at 251 N Bly Rd in Independence | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with ARCO and the firms whose trade matches what you sell |
Who should go after the Nebius Independence data center?
| Electrical distributors and gear reps | ARCO's $700.7 million Building 1 interior permit, a $31.7 million 161 kV substation and about 400 electricians on site at peak. |
|---|
| Site, concrete and road suppliers | Superior Bowen and NorthPoint Development on the Bly Road reroute, and ARCO's two $118.8 million foundation permits. |
|---|
| Power and gas suppliers | Independence Power & Light, and the Independence Power Partners gas plant at the old Blue Valley site, owned by United Energy Trading and Exigent Energy. |
|---|
What should you do next on the Nebius Independence data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask ARCO for the team on the Nebius AI factory at 251 N Bly Road in Independence.
- Watch for the fire alarm permit and new trade permits as Building 1 heads for the second quarter of 2027.
Questions people ask about the Nebius Independence data center
How much is the Nebius data center in Independence?
The city puts land and site work for the 400-acre campus at $6.6 billion, plus tens of billions of dollars in equipment. The 12 city permits on the site add up to about $1.12 billion, the sum. Nebius itself calls it a multi-billion-dollar investment.
Is the Nebius Independence campus a $150.6 billion project?
No. On March 2, 2026, the city council voted 5-2 to approve up to $150.6 billion in bonds for the campus. That is a ceiling for the bonds, not the cost of the job.
Who is building the Nebius data center in Independence?
ARCO National Construction is the general contractor for Building 1 and the only contractor named on the site's city permits. Superior Bowen leads the Bly Road reroute for NorthPoint Development. 11 firms are named on the job, listed above.
What is the biggest permit on the Nebius campus?
Permit 2026-02480, $700,659,985 for the inside of Building 1, issued to ARCO on Oct. 2, 2026. The permit fee alone was $9,284,471.50.
Where is the Nebius data center in Independence?
At 251 N Bly Road in the EastGate Commerce Center in Independence, Jackson County, Missouri, near Little Blue Parkway and Missouri 78. The substation is at 301 N Bly Road.
How big is the Nebius Independence data center?
The first building is about 490,000 sq ft and 200 MW. The full campus plan is up to four buildings and 1.2 GW on about 400 acres.
Why are neighbors suing over the Nebius data center?
The Independence GUARD Alliance filed a 16-count, 52-page lawsuit in Jackson County Circuit Court on Aug. 12, 2026, hoping to stop the job. It names the city, Nebius's Missouri ADC Holdings and Independence Power Partners. We found no ruling; work goes on.
When will Bly Road reopen?
Bly Road closed April 1, 2026 for the reroute and partly reopened Nov. 6. NorthPoint's letter says the work should finish the first week of December 2026.
Where will the Nebius campus get its power?
From Independence Power & Light, the city's utility. 800 MW is to come from Independence Power Partners' new gas plant at the old Blue Valley Power Plant site. NextEra and Evergy supply power in the meantime.
How many jobs will the Nebius Independence data center create?
About 1,200 construction jobs, mostly through local union building trades, with about 400 electricians on site at peak.
What happens next on the Nebius Independence data center?
An $18,149,260 fire alarm permit filed Oct. 27, 2026 is not yet issued, and Building 1 is expected to be running by the second quarter of 2027. We'll update this page when a new permit or firm appears.
How we built this list
We read the City of Independence's permit status pages and open building permit data for 251 and 301 N Bly Rd and 22900 E M-78 Hwy, Nebius's city presentations (Dec. 8, 2025 and Jan. 12, 2026), Nebius's and ARCO's own pages, a Nov. 6, 2026 letter to Bly Road residents and news reports, all read Nov. 25, 2026. We kept each firm a public record names on this campus. The $1.12 billion is the sum of the declared values of the site's 12 valued city permits (a cancelled permit and three $0 foundation permits left out), not Nebius's spend; one foundation permit has the same value as another and may be a duplicate. The $150.6 billion is a bond ceiling, not a cost. Left out: Nebius and its Missouri ADC Holdings (the owner), DPR Construction (on Nebius's January team slide, but ARCO was named Phase 1 builder later and DPR's role is not stated), the owner's law firm and consultant, the lawsuit's lawyers, unions and the city. No electrical, mechanical or concrete subcontractor is named in any public record we found: ARCO pulls the permits, and the substation permits name no outside contractor. Phones are each firm's own line from its own site where we found one; Superior Bowen and United Energy Trading are headquarters lines, Evergy's is its general line, and we found no verified main line for ARCO, NorthPoint, HKS, IPL, Exigent or NextEra, or any website for Independence Power Partners. First published Nov. 25, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 25, 2026- Nebius: breaks ground on gigawatt-scale AI factory in Independence, Missouri (May 12, 2026)
- Nebius x Independence, Missouri project page (read Nov. 25, 2026)
- ARCO National Construction: Nebius Independence project page (read Nov. 25, 2026)
- ARCO National Construction: groundbreaking of the Nebius AI factory campus (May 18, 2026)
- City of Independence: Search Permit Status and open data building permits, read Nov. 25, 2026
- City of Independence: Nebius x Independence study session deck (Jan. 12, 2026)
- City of Independence: EastGate update presentation (Dec. 8, 2025)
- Kansas City Star via GovTech: Independence to reopen old power plant for AI data center (Jan. 28, 2026)
- KSHB 41: Independence approves hyperscale AI data center, issues $150 billion in bonds (March 2026)
- KCTV5: Independence City Council greenlights data center tax breaks, 5-2 vote (March 2, 2026)
- KSHB 41: Q&A with Nebius's VP of public affairs (May 5, 2026)
- KSHB 41: Nebius breaks ground amid community opposition (May 12, 2026)
- KCTV5: controversial data center moves forward in Independence (May 12, 2026)
- KSHB 41: Independence GUARD Alliance files lawsuit to halt construction (Aug. 13, 2026)
- KSHB 41: council to consider limiting truck traffic on Bly Road (Nov. 9, 2026)
- FOX4 Kansas City: Bly Road completion set for December (Nov. 23, 2026)
- NorthPoint Development and Superior Bowen letter to Bly Road residents (Nov. 6, 2026)
- City of Birmingham permit BLD2026-00724
- City of Birmingham permit ELE2026-00878
- City of Birmingham permit MEC2026-00852
- Nebius Vineland page (read 2026-11-22)
- ENR, 2026-09-23
- Kiely case study 'Vineland Data Center AI Campus'