What is Aligned building in Shippingport, Pennsylvania?
Aligned Data Centers broke ground on Sept. 10, 2026 on Project Phoenix, a 2 GW data center campus in the Shippingport Industrial Park in Shippingport, Beaver County. It sits next to the old Bruce Mansfield coal plant, one of Pennsylvania's largest coal plants until it closed in 2019.
The plans show three data center buildings totaling nearly 2 million sq ft, a warehouse, an administrative building and an onsite power plant. Aligned bought about 650.9 acres for about $223 million in July 2026. Aligned expects about 3,000 construction jobs and 640 full-time jobs.
How much is the Aligned Shippingport data center?
Aligned says Project Phoenix will anchor about $10 billion in regional economic investment. That is Aligned's own estimate of investment in the region. It is not a construction contract, and Aligned has not said what the buildings cost.
The building permits, SHI 26-136, SHI 26-137 and SHI 26-138, carry no published value. The firm figures we can see are the land, about $223 million, and National Fuel's gas line to the site, about $50 million.
How will the campus get its power?
Aligned says Project Phoenix will use its own power on site, not the local grid. The state's proposed air approval lists about 1.2 GW of solid oxide fuel cells, eight 4,680 hp and three 1,483 hp diesel emergency generators, and 64 temporary generators during construction. Bloom Energy makes the fuel cells.
Gas comes through National Fuel's Shippingport Lateral, about 7 miles of 24-inch pipe with 205,000 dekatherms a day of firm capacity. The state plans to approve the air permit, with the site's emissions held to no more than 59 tons of NOx and 98 tons of CO a year, and holds a public hearing on Dec. 3, 2026.
How far along is the Aligned Shippingport data center?
Shippingport Borough Council approved the Phase 1 grading permit on Jan. 28, 2026. On March 31, by a 3-2 vote, it let Aligned run rock crushers 24 hours a day, 7 days a week if needed for the length of construction. The state has issued Phase 1 stormwater permit PAC040198.
Council approved the Phase 2 plans unanimously on Sept. 21, 2026, contingent on outstanding outside agency permits. Kokosing Industrial filed a Notice of Commencement on Oct. 8 and Holder Construction Group filed a second one on Oct. 28. Trumbull Corporation started mass excavation on Nov. 2. Plumbing, HVAC and supply firms filed notices from Nov. 10 to Nov. 19.
What are the fights over Project Phoenix?
Neighbors objected when the borough moved Phase 2 ahead. One, from Midland, said: "I feel they're popping up everywhere like Dollar General stores." In March, council's vote to allow 24-hour rock crushing passed 3-2.
The stream permit, E0405226-004, would permanently impact 9,162 linear feet of streams, 20.69 acres of floodway and 0.11 acre of wetland along Haden Run and Squirrel Run. The air permit hearing is Dec. 3, 2026, 6 to 8 p.m., at the Shippingport Community Building.
Who Aligned hired before
Aligned has hired Holder before: Holder is the general contractor on Aligned's IAD-03 data center expansion in Sterling, Virginia, the same builder now at Shippingport. Aligned has also used Turner and Skanska on other campuses.
- Holder Construction: builder on Aligned IAD-03 Tenant Fit-Out B ($80 million) and two-story addition, Sterling, VA, 2025-2026. Also on this job.
- Gensler: architect on Aligned IAD-03 Tenant Fit-Out B and addition, Sterling, VA, 2025.
- Turner Construction: builder (design-build) on Aligned Salt Lake City Data Center SLC-02, 240,000 sq ft, West Jordan, UT, 2021.
- Skanska: construction manager on Aligned Data Centers conversion of a vacant facility into a 550,000 sq ft data center, Arizona, earlier.
These are earlier or other jobs for the same owner. They are not counted in the 12 firms on this job.
How do the ways into the Aligned Shippingport data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Aligned's Project Phoenix in Shippingport | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Aligned Shippingport data center?
| Mechanical, plumbing and HVAC reps | Poole & Kent on HVAC equipment, W.G. Tomko on plumbing and HVAC under Holder, and SSM Industries buying plumbing material through Hajoca's Pittsburgh branch. |
|---|
| Site, pipe and stone suppliers | Trumbull on mass excavation under Kokosing and Stefanik's on site work, on a campus whose stream permit would permanently impact 9,162 feet of streams and 20.69 acres of floodway. |
|---|
| Electrical and power gear reps | Bloom Energy's about 1.2 GW of fuel cells and National Fuel's 24-inch gas line, plus 11 diesel emergency generators in the air permit. |
|---|
What should you do next on the Aligned Shippingport data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Aligned's Project Phoenix data center in the Shippingport Industrial Park.
Questions people ask about the Aligned Shippingport data center
How much is the Aligned Shippingport data center?
Aligned says Project Phoenix will anchor about $10 billion in regional economic investment. That is Aligned's estimate, not a construction cost; the cost of the buildings is not public. Aligned paid about $223 million for the land.
Is Project Phoenix a $10 billion data center?
Only as Aligned's estimate of regional economic investment. The building permits carry no published value, and no construction contract amount is public.
Who is building the Aligned data center in Shippingport?
Kokosing Industrial is the contractor on the three building permits, and Holder Construction Group is the contractor on a second state notice. Aligned named both as construction partners. 12 firms are named on the job, listed above.
Who is doing the excavation at Project Phoenix?
Trumbull Corporation, as a subcontractor to Kokosing Industrial. Its mass excavation work started Nov. 2, 2026.
Who is doing the HVAC and plumbing at Project Phoenix?
W.G. Tomko is the plumbing and HVAC subcontractor to Holder, on site since Oct. 5, 2026. Poole & Kent, a mechanical contractor, filed a state notice for HVAC equipment, and SSM Industries is buying plumbing material for the job.
Where is Project Phoenix?
In the Shippingport Industrial Park, off Steel Curtain Dr and Church Ln in Shippingport, Beaver County, Pennsylvania, next to the closed Bruce Mansfield coal plant.
How will Project Phoenix get power?
From about 1.2 GW of gas-fed solid oxide fuel cells on site, made by Bloom Energy, not from the grid. National Fuel is building a 24-inch gas line to the site.
How big is Project Phoenix?
A 2 GW campus with three data center buildings totaling nearly 2 million sq ft, on a site of about 651 acres.
How many jobs will Project Phoenix create?
Aligned expects about 3,000 construction jobs and 640 full-time jobs.
When is the Project Phoenix air permit hearing?
Thursday, Dec. 3, 2026, 6 to 8 p.m., at the Shippingport Community Building. The state has said it intends to approve the permit.
What is the first step for a supplier?
Pick the firms whose work matches what you sell and call their offices, asking for the team on Aligned's Project Phoenix in Shippingport.
How we built this list
We read Pennsylvania's State Construction Notices directory (two Notices of Commencement and five Notices of Furnishing for the site), Shippingport Borough's council minutes for Jan. 28, March 31 and Sept. 21, 2026, the Pennsylvania Bulletin's air, stream, stormwater and general permit notices, Aligned's groundbreaking release, National Fuel's project page and news reports, all on Nov. 23, 2026. We kept each firm a state notice, the borough or the news names on this campus. Beaver County and Shippingport have no online permit portal, and the building permits carry no published value, so we give no permit sum. The $10 billion is Aligned's estimate of regional economic investment, not a construction cost. Left out: the owner and its investors, the land seller, a separate power plant project next door, the borough's engineer, regulators, a former prospective tenant, and five firms whose tie we could not prove: a blasting firm whose state permit does not name the project, a fireproofing firm named only in a newsletter, an electrical gear maker whose order is only likely for this site, a firm with a job post that does not name the client, and the surveyor of the land plat. Phones are each firm's own office line from its own site, except SSM's, from its builders' association listing, and United Rentals' national line. Holder, Kokosing, Poole & Kent, W.G. Tomko, Bloom and National Fuel numbers are head or regional offices, not Beaver County. First published Nov. 23, 2026. We'll update this page when a new notice, permit or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 23, 2026- Aligned Data Centers press release: Project Phoenix groundbreaking (Sept. 10, 2026)
- PA State Construction Notices: Notice of Commencement SCCM00016473, Kokosing Industrial (Oct. 8, 2026)
- PA State Construction Notices: Notice of Commencement SCCM00016565, Holder Construction Group (Oct. 28, 2026)
- PA State Construction Notices: Notice of Furnishing SCFN00016584, Trumbull (Nov. 2, 2026)
- PA State Construction Notices: Notice of Furnishing SCFN00016624, Poole & Kent (Nov. 10, 2026)
- PA State Construction Notices: Notice of Furnishing SCFN00016632, W.G. Tomko (Nov. 11, 2026)
- PA State Construction Notices: Notice of Furnishing SCFN00016647, SSM Industries and Hajoca (Nov. 13, 2026)
- PA State Construction Notices: Notice of Furnishing SCFN00016671, Stefanik's and United Rentals (Nov. 19, 2026)
- Shippingport Borough Council minutes, Jan. 28, 2026 hearing
- Shippingport Borough Council minutes, March 31, 2026 hearing
- Shippingport Borough work session minutes, Sept. 21, 2026
- Pennsylvania Bulletin Vol. 56 No. 44 (Oct. 31, 2026): air plan approval PA-04-00953A
- Pennsylvania Bulletin Vol. 56 No. 31: Chapter 105 permit E0405226-004
- Pennsylvania Bulletin Vol. 56 No. 35: NPDES PAC040198
- Pennsylvania Bulletin Vol. 56 No. 23 (June 6, 2026): Kokosing air general permits
- Data Center Frontier: From coal to compute (Sept. 30, 2026)
- National Fuel: Shippingport Lateral Project page
- Stocktwits: Bloom Energy and Project Phoenix (Sept. 15, 2026)
- FracTracker Alliance: Southwestern Pennsylvania data center proposals (Oct. 26, 2026)
- FracTracker Alliance: Project Phoenix site packet (Oct. 2026)
- WPXI: Neighbors express concerns as Shippingport leaders move Phase 2 data center plan (Sept. 21, 2026)
- Marcellus Drilling News: DEP ready to OK gas fuel cells for 2 GW Shippingport data center (Nov. 2, 2026)
- ATI article 'Who's wiring Aligned's Sterling data center' (aligned-data-center-sterling), Loudoun County permits
- Turner Construction: Aligned, Salt Lake City Data Center SLC-02
- Skanska USA: Aligned Data Centers, Data Center