What did Loudoun County issue on Aug. 21?
On Aug. 21, 2026, Loudoun County issued 43 Electrical (Commercial) permits at 42376 Patriot Park Dr, Leesburg, to Dynalectric, each titled "IAD 669" with AWS as owner. Four are medium-voltage switchgear permits: "IAD 669 OFFICE/PH 1 MVA SWITCHGEAR ELECTRICAL PERMIT", the MVB switchgear, and the MVD and MVE switchgear in phase 10. One is the office and phase 1 house service. The rest are two permits for each of the building's 18 phases.
The permits don't itemize gear or fixtures; each covers its phase's electrical work. Their value fields repeat the fit-out permits' figures, so they aren't a separate electrical price.
Dynalectric was on the building before Amazon's fit-out. It held the core/shell electrical permit (issued Feb. 20, 2025, finaled July 24, 2026) and the 600 amp fire pump service permit. On Nov. 6, 2026 it filed one more: a low-voltage security rough-in for the office and phase 1, not yet issued on Nov. 10.
Is this Amazon's building?
The building belongs to TA Realty's campus company, Nova 1 Owner LLC, which holds the shell permit: "Third building on the campus. CURRENT: CORE/SHELL 3-STORY FLEX WAREHOUSE AND COMMERICAL OFFICE. FUTURE PURPOSE OF SPACE: 3-STORY SINGLE TENANT COMPUTER DATA CENTER." That permit carries $72,775,650.83 for 413,099 sq ft and was issued Jan. 31, 2025 to E.E. Reed.
The 18 fit-out permits, "Data Center Architectural and Structural Tenant Fit-Out", list Amazon Data Services, Inc. as owner and E.E. Reed as contractor. They total $43,989,753 and were issued April 27 and May 22, 2026.
The press never named the tenant. Data Center Frontier reported TA Realty's 430 MW lease with "a premier global cloud services provider" (Nov. 28, 2023), and REBusiness described "a single, unnamed global cloud provider" when TA Realty sold the first two buildings (Feb. 6, 2026).
What else is moving on the campus?
Building 4, at 42590 Patriot Park Dr, follows the same pattern. Dynalectric got 38 electrical permits there on Aug. 24-25, 2026, including MVA, MVB, MVD and MVE switchboards. On Nov. 2, Power Solutions filed 15 low-voltage BMS and EPMS permits, and on Nov. 5 BFPE International filed 15 fire alarm permits; none was issued by Nov. 10.
Building 5, at 42630 Patriot Park Dr, has a $65,605,395 shell permit issued to E.E. Reed on Aug. 25, 2026. Dynalectric's core/shell and fire pump service electrical permits were filed Sept. 1 and were in review on Nov. 10. E.L. Blackwell Electric got the underground conduit permit on Nov. 6. No fit-out permit is filed yet.
The Project Celtics Phase 2 substation got its grading permit on Oct. 21, 2026, with E.E. Reed East Coast as contractor, and its stormwater permit for 9.15 acres on Oct. 28.
Where else is Dynalectric working?
ATI's records show the same electrician on other Northern Virginia data centers this fall: Amazon's IAD 182 in Sterling (grounding permit issued Oct. 7, 2026), Amazon's IAD 179 in Ashburn (MV-A and MV-B lineup permits, July 31), NTT's VA10 in Gainesville (a $20 million electrical permit, Oct. 12) and NTT's VA7 in Ashburn.
How do the ways into Amazon's Leesburg campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The electrician on the permits | A call to Dynalectric, on all 43 main electrical permits at building 3 and 38 at building 4 | Lighting, wire, switchgear and gear reps | A conversation with the firm wiring Amazon's fit-out on the campus | Its project staff aren't listed publicly, so start at the main line |
| The builder | A call to E.E. Reed, builder of the shells and Amazon's fit-outs | Trades and suppliers who sell to GCs | Who holds the scopes the permits don't name | Amazon's fit-out trades may already be let |
| The low-voltage firms | Calls to Power Solutions (HVAC controls, BMS and EPMS) and Securitas Technology (security) | Cable, controls and security reps | Firms with permits issued Nov. 2 and Nov. 4, and 15 more filed Nov. 2 for building 4 | Building 4's permits weren't issued as of Nov. 10 |
| The next building | Building 5, a $65.6 million shell with Dynalectric's electrical permits in review | Reps who want to be early | The work before Amazon files a fit-out | No fit-out permit is filed yet, so there's no date |
Who should go after the Leesburg campus, and who shouldn't?
| Electrical distributors, switchgear and lighting reps | Dynalectric holds the building's 43 main electrical permits, including four medium-voltage switchgear permits. |
|---|
| Low-voltage, controls and security reps | Power Solutions holds 18 HVAC-controls permits (issued Nov. 2) and filed 15 BMS and EPMS permits next door (Nov. 2); Securitas Technology holds 3 security permits (Nov. 4). |
|---|
| Fire alarm and sprinkler suppliers | BFPE International holds 36 fire alarm device permits and 36 sprinkler and fire alarm system permits on the building. |
|---|
| Who shouldn't bother | A rep looking for a public bid: these are private jobs with the trades already named on the permits. |
|---|
What should you do next on the Leesburg campus?
- If you sell lighting, wire, switchgear or gear, call Dynalectric's main line in Dulles and ask for the team on the Leesburg campus (IAD 669 and IAD 670).
- If you sell controls or low-voltage cable, call Power Solutions about the HVAC controls at building 3 and the BMS and EPMS permits filed for building 4.
- If you sell to builders, call E.E. Reed East Coast in Herndon about building 5.
- Open the full list for every permit and firm, with each company's line.
Questions people ask about Amazon's Leesburg data center
Who is the electrician on Amazon's Leesburg data center?
Dynalectric. Loudoun County issued it 43 electrical permits at 42376 Patriot Park Dr on Aug. 21, 2026, titled "IAD 669", with AWS as owner. They include the MVA and MVB switchgear (ELECC-2026-036577 and -036578), the MVD and MVE switchgear, the house service and two permits for each of the 18 phases. Dynalectric also held the building's core/shell electrical permit in 2025.
Is the Leesburg campus Amazon's?
TA Realty developed it; its Nova 1 Owner LLC holds the shell permits for buildings 3, 4 and 5, and it sold the first two buildings in Feb. 2026 (REBusiness). The fit-out permits for buildings 3 and 4 list Amazon Data Services, Inc. as owner, and the trade permits list AWS. TA Realty's 2023 announcement called its tenant "a premier global cloud services provider", and a Feb. 6, 2026 REBusiness story called it "a single, unnamed global cloud provider".
How much does the Leesburg data center cost?
Building 3's shell permit carries $72,775,650.83 and its 18 fit-out building permits total $43,989,753. TA Realty announced the whole campus in 2021 as "a new $1.8 billion secure data center campus in Leesburg." The trade permits repeat the fit-out values, so they are not added on top. TA Realty's 2021 figure was for a 300 MW plan; the 2023 lease covers 430 MW (Data Center Frontier, Nov. 28, 2023).
Who is building it?
E.E. Reed Construction (E.E. Reed East Coast, Herndon) holds the shell building permits for buildings 3, 4 and 5 and Amazon's fit-out permits for buildings 3 and 4. Gensler is the applicant on those permits.
How big is the campus?
Data Center Frontier reported a 430-megawatt lease "across five buildings, making up the entire 1.9 million square-foot project" (Nov. 28, 2023). Building 3 is 413,099 sq ft on its shell permit.
What's next on the campus?
Building 5 at 42630 Patriot Park Dr has a $65,605,395 shell permit (issued Aug. 25, 2026). Dynalectric's core/shell and fire pump service electrical permits there were filed Sept. 1 and were in review on Nov. 10, 2026. No fit-out permit is filed for it yet. A grading permit for the Project Celtics Phase 2 substation was issued Oct. 21, 2026.
Who does the low voltage?
Power Solutions LLC of Virginia holds 18 HVAC-controls permits at building 3 (issued Nov. 2, 2026) and filed 15 BMS and EPMS permits for building 4 on Nov. 2. Securitas Technology holds 3 security permits (Nov. 4). BFPE International holds the fire alarm permits.
When does it open?
We found no opening date in the records. Data Center Frontier reported in 2023 that construction of the campus "is expected to be completed in 2027."
How we built this list
We read every Loudoun County permit at 42376, 42590 and 42630 Patriot Park Dr, Leesburg, in ATI's records and on the county's public permit portal (LandMARC, read Nov. 10, 2026): building, zoning, electrical, mechanical, plumbing and fire records, their status, dates, values and named firms. We read TA Realty's 2021 and 2023 announcements as reported by REBusiness and Data Center Frontier, and REBusiness's Feb. 6, 2026 story on the first two buildings. We added the same electrician's other active Northern Virginia data center permits from ATI's records. A row is on the list only if a permit or a cited story ties it to the campus or to the electrician. We left every person's name, phone and email off the list and used company lines. First published Nov. 16, 2026. We'll update this page when building 5's electrical permits are issued and when a fit-out permit is filed for building 5.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 10, 2026- Loudoun County LandMARC, ELECC-2026-036577 (MVA switchgear)
- Loudoun County LandMARC, ELECC-2026-036637 (MVD switchgear)
- Loudoun County LandMARC, BLDC-2024-039132 (building 3 shell)
- Loudoun County LandMARC, BLDC-2026-013001 (building 3 fit-out, office and phase 1)
- Loudoun County LandMARC, ELECC-2024-062484 (building 3 shell electrical)
- Loudoun County LandMARC, ELECC-2026-053798 (filed Nov. 6, 2026)
- Loudoun County LandMARC, ELECC-2026-046615 (HVAC controls)
- Loudoun County LandMARC, ELECC-2026-036683 (building 4 house service)
- Loudoun County LandMARC, ELECC-2026-043070 (building 5 core/shell electrical)
- Loudoun County LandMARC, BLDC-2026-025845 (building 5 shell)
- Loudoun County LandMARC, GRADE-2025-000285 (Phase 2 substation grading)
- REBusiness, TA Realty to Develop $1.8B Data Center Campus in Leesburg, Virginia, May 4, 2021
- Data Center Frontier, TA Realty Leases 430 MW Across Entire Leesburg Data Center Campus, Nov. 28, 2023
- REBusiness, TA Realty Sells Two Hyperscale Data Centers Totaling 745,000 SF in Northern Virginia, Feb. 6, 2026
- Dynalectric Washington DC, contact page