Who's building Amazon's Lake Anna data center, part of its $11 billion Louisa plan

Amazon's data center next to the North Anna nuclear plant in Mineral, Virginia is part of an $11 billion plan, and the county is weighing new rules for worker camps.

By Porter Stanley. Updated .

Amazon Web Services is building the Lake Anna Technology Campus on a 153-acre site at Kentucky Springs Road and Haley Drive in Mineral, right next to Dominion's North Anna nuclear plant. Amazon's permit application describes seven data center buildings, more than 1.7 million square feet, and at least 420 megawatts (Lake Anna Life). It is part of Amazon's $11 billion plan for two Louisa County campuses through 2040 (Virginia Business); Amazon has not published a figure for Lake Anna alone. Clark Construction, through its Clark Technologies division, is the general contractor, and its project site put the campus at 60% complete this summer. 11 firms are named on the job; the list below has all 11.

$11BAmazon's plan for two Louisa campuses (Virginia Business)
1.7M sq ftSeven data center buildings planned
60%Complete as of summer 2026 (Clark)
11Firms named on the job

Get all 11 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 11 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 11 firms on Amazon's Lake Anna data center?

We list the 11 firms named on Amazon's Lake Anna data center, one row each, with where each name comes from.

1Latest recordJul 1, 2024

Clark Construction Group (Clark Technologies)

General contractor for the whole campus on Amazon's Lake Anna data center

AWS Lake Anna Technology Campus (Amazon code IAD 550), Kentucky Springs Road and Haley Drive, Mineral (Louisa County), Virginia

Work: General contractor for the whole campus

Who to call: Clark Construction Group (Clark Technologies)
Clark Construction Group (Clark Technologies) office line
(Bethesda, MD)
(804) 877-8817

The opportunity: VAR10U002 | Clark Construction Group, LLC | McLean | IAD 550 RGP | Kentucky Springs Rd | Mineral | 119.25 acres | Commercial

2Latest recordNov 18, 2024

MEB General Contractors

Design-build partner on Amazon's Lake Anna data center

AWS Lake Anna Technology Campus (Amazon code IAD 550), Kentucky Springs Road and Haley Drive, Mineral (Louisa County), Virginia

Work: Design-build partner

Who to call: MEB General Contractors
MEB General Contractors office line
(Chesapeake, VA)
(804) 749-6000

The opportunity: supervisors are set to approve a comprehensive agreement with Faulconer Construction, Timmons Group and MEB

3Named in the newsNov 17, 2026

Cedar Mountain Stone Corporation

Gravel / crushed stone supplier for the site on Amazon's Lake Anna data center

AWS Lake Anna Technology Campus (Amazon code IAD 550), Kentucky Springs Road and Haley Drive, Mineral (Louisa County), Virginia

Work: Gravel / crushed stone supplier for the site

Who to call: Cedar Mountain Stone Corporation
Cedar Mountain Stone Corporation office line
(Mitchells, VA)
(540) 829-7203

The opportunity: The gravel is sourced from Cedar Mountain Stone Corporation in southern Culpeper County.

What is Amazon building at Lake Anna?

Amazon Web Services is building the Lake Anna Technology Campus on 153 acres at the corner of Kentucky Springs Road and Haley Drive in Mineral, next to Dominion's North Anna nuclear plant. Amazon's 2023 permit application, as Lake Anna Life reported it, lists seven data center buildings, a 65,000-square-foot office building, two smaller specialty buildings and two substations: more than 1.7 million square feet and at least 420 megawatts.

Amazon has said it will invest $11 billion in Louisa County through 2040 for two data center campuses, Lake Anna and Northeast Creek (Virginia Business). That is a plan for both campuses over many years, not a construction contract, and Amazon has not published what Lake Anna alone costs.

Clark Construction's project site put the campus at 60% complete this summer, with more than 2 million work hours. It said the first data center building was set to open in August 2026, that the office building, access control building and pumphouse were done, and that ground had been broken on two more data center buildings.

Who gets what?

Amazon has not published a budget for Lake Anna alone, so we do not split it by trade: the $11 billion covers both Louisa campuses through 2040 and is an investment plan, not a construction cost.

One piece has a real price. Louisa County hired a design-build team of Faulconer Construction, Timmons Group and MEB to build water and sewer lines for both campuses, paid for by Amazon. It started as a $55 million base contract plus a $29 million allowance for changes, and after a $16.4 million rock removal change order in September 2025 it stands at about $104 million (Louisa County Board of Supervisors packet, Sept. 15, 2025). For Lake Anna it includes an 11-mile, 16-inch raw water line, due in January 2027 (Engage Louisa).

Which firms are on the job?

Clark Construction is the general contractor through Clark Technologies, and Virginia DEQ's stormwater permit for the site, covering 119.25 acres, is in Clark's name. Lake Anna Life reports that Shirley, a Northern Virginia firm, did the rough grading and that the gravel comes from Cedar Mountain Stone in Culpeper County. Dominion Energy and Rappahannock Electric Cooperative each own one of the two substations.

On the county's water work for the campus, Faulconer Construction, Timmons Group and MEB are the design-build team, and Johnson, Mirmiran & Thompson inspects and tests the work for the county. Wetland Studies and Solutions prepared Amazon's wetlands permit application and R. Christopher Goodwin & Associates surveyed the site for history before work began. No public record we found names the electrical, mechanical or fire protection subcontractors. 11 firms in all are on the list below.

How do the ways into Amazon's Lake Anna data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Amazon's Lake Anna data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after Amazon's Lake Anna data center?

Electrical distributors and gear repsClark's electrical work on seven data center buildings and two substations, owned by Dominion Energy and Rappahannock Electric Cooperative.
Pipe, pump and water repsThe county's 11-mile raw water line and pump station by Faulconer, Timmons Group and MEB, and the campus cooling water system.
Site, stone and concrete suppliersShirley's grading and Cedar Mountain Stone's gravel on a 153-acre site.

What should you do next on Amazon's Lake Anna data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Amazon's Lake Anna data center.

Questions people ask about Amazon's Lake Anna data center

How much is Amazon's Lake Anna data center?

Amazon has not published a Lake Anna-only figure. The campus is part of Amazon's $11 billion investment through 2040 for two Louisa County campuses, Lake Anna and Northeast Creek (Virginia Business).

Who is building Amazon's Lake Anna data center?

Clark Construction, through its Clark Technologies division, is the general contractor. 11 firms are named in all, listed above.

Where is Amazon's Lake Anna data center?

On 153 acres at Kentucky Springs Road (Route 652) and Haley Drive (Route 700) in Mineral, Louisa County, Virginia, next to the North Anna Power Station.

How big is the Lake Anna campus?

Amazon's permit application lists seven data center buildings, more than 1.7 million square feet in all, and at least 420 megawatts (Lake Anna Life).

When will the Lake Anna data center open?

Clark's project site said the first data center building was set to open in August 2026, with the campus 60% complete this summer.

How we built this list

We read Virginia DEQ's construction stormwater permits for the site (queried Nov. 17, 2026), Clark's Lake Anna Technology Campus project site, Lake Anna Life, Engage Louisa and Virginia Business, and kept each firm a record or story names on this campus or on the county's water work for it, marked as such. Louisa County's building permits were not read: the county's portal needs an account. No public source we found names the electrical, mechanical or fire protection subcontractors. We give no trade split, because no Lake Anna-only budget exists. Phones are each firm's own office line, except Cedar Mountain Stone (a lobbying record) and JMT (a news page). First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports