What is Amazon building at Lake Anna?
Amazon Web Services is building the Lake Anna Technology Campus on 153 acres at the corner of Kentucky Springs Road and Haley Drive in Mineral, next to Dominion's North Anna nuclear plant. Amazon's 2023 permit application, as Lake Anna Life reported it, lists seven data center buildings, a 65,000-square-foot office building, two smaller specialty buildings and two substations: more than 1.7 million square feet and at least 420 megawatts.
Amazon has said it will invest $11 billion in Louisa County through 2040 for two data center campuses, Lake Anna and Northeast Creek (Virginia Business). That is a plan for both campuses over many years, not a construction contract, and Amazon has not published what Lake Anna alone costs.
Clark Construction's project site put the campus at 60% complete this summer, with more than 2 million work hours. It said the first data center building was set to open in August 2026, that the office building, access control building and pumphouse were done, and that ground had been broken on two more data center buildings.
Who gets what?
Amazon has not published a budget for Lake Anna alone, so we do not split it by trade: the $11 billion covers both Louisa campuses through 2040 and is an investment plan, not a construction cost.
One piece has a real price. Louisa County hired a design-build team of Faulconer Construction, Timmons Group and MEB to build water and sewer lines for both campuses, paid for by Amazon. It started as a $55 million base contract plus a $29 million allowance for changes, and after a $16.4 million rock removal change order in September 2025 it stands at about $104 million (Louisa County Board of Supervisors packet, Sept. 15, 2025). For Lake Anna it includes an 11-mile, 16-inch raw water line, due in January 2027 (Engage Louisa).
Which firms are on the job?
Clark Construction is the general contractor through Clark Technologies, and Virginia DEQ's stormwater permit for the site, covering 119.25 acres, is in Clark's name. Lake Anna Life reports that Shirley, a Northern Virginia firm, did the rough grading and that the gravel comes from Cedar Mountain Stone in Culpeper County. Dominion Energy and Rappahannock Electric Cooperative each own one of the two substations.
On the county's water work for the campus, Faulconer Construction, Timmons Group and MEB are the design-build team, and Johnson, Mirmiran & Thompson inspects and tests the work for the county. Wetland Studies and Solutions prepared Amazon's wetlands permit application and R. Christopher Goodwin & Associates surveyed the site for history before work began. No public record we found names the electrical, mechanical or fire protection subcontractors. 11 firms in all are on the list below.
How do the ways into Amazon's Lake Anna data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Amazon's Lake Anna data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Amazon's Lake Anna data center?
| Electrical distributors and gear reps | Clark's electrical work on seven data center buildings and two substations, owned by Dominion Energy and Rappahannock Electric Cooperative. |
|---|
| Pipe, pump and water reps | The county's 11-mile raw water line and pump station by Faulconer, Timmons Group and MEB, and the campus cooling water system. |
|---|
| Site, stone and concrete suppliers | Shirley's grading and Cedar Mountain Stone's gravel on a 153-acre site. |
|---|
What should you do next on Amazon's Lake Anna data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Amazon's Lake Anna data center.
Questions people ask about Amazon's Lake Anna data center
How much is Amazon's Lake Anna data center?
Amazon has not published a Lake Anna-only figure. The campus is part of Amazon's $11 billion investment through 2040 for two Louisa County campuses, Lake Anna and Northeast Creek (Virginia Business).
Who is building Amazon's Lake Anna data center?
Clark Construction, through its Clark Technologies division, is the general contractor. 11 firms are named in all, listed above.
Where is Amazon's Lake Anna data center?
On 153 acres at Kentucky Springs Road (Route 652) and Haley Drive (Route 700) in Mineral, Louisa County, Virginia, next to the North Anna Power Station.
How big is the Lake Anna campus?
Amazon's permit application lists seven data center buildings, more than 1.7 million square feet in all, and at least 420 megawatts (Lake Anna Life).
When will the Lake Anna data center open?
Clark's project site said the first data center building was set to open in August 2026, with the campus 60% complete this summer.
How we built this list
We read Virginia DEQ's construction stormwater permits for the site (queried Nov. 17, 2026), Clark's Lake Anna Technology Campus project site, Lake Anna Life, Engage Louisa and Virginia Business, and kept each firm a record or story names on this campus or on the county's water work for it, marked as such. Louisa County's building permits were not read: the county's portal needs an account. No public source we found names the electrical, mechanical or fire protection subcontractors. We give no trade split, because no Lake Anna-only budget exists. Phones are each firm's own office line, except Cedar Mountain Stone (a lobbying record) and JMT (a news page). First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 18, 2026- Louisa County Board of Supervisors packet: contract with Louisa County Infrastructure, LLC raised to $104,289,125 (Sept. 15, 2025)
- Virginia Business: Amazon cancels data center in Louisa County (July 28, 2025)
- Lake Anna Technology Campus project site (Clark Technologies), read Nov. 17, 2026
- Lake Anna Life: Amazon provides details for Lake Anna Tech Campus (fall 2023)
- Lake Anna Life: Amazon planning to commence work at Lake Anna Technology Campus (2024)
- Lake Anna Life: Lake Anna data center site will mark one-year anniversary (2025)
- Engage Louisa: supervisors set to greenlight AWS infrastructure (Nov. 18, 2024)
- Engage Louisa: DEQ cooling water permit for AWS (July 20, 2026)
- Engage Louisa: planning commission votes 4-3 on worker lodging (Nov. 16, 2026)
- Virginia DEQ construction stormwater permits (VAR10U002)
- MEB: Louisa Tech Sites Offsite Utilities (Jan. 8, 2025)