What is Amazon building in Madison County, Mississippi?
Amazon Web Services is building data center campuses at two sites in Madison County, just north of Jackson. The Canton campus sits on the Madison County Mega Site off Highway 22 and Nissan Parkway, on 927 acres. The Ridgeland campus sits on Highland Colony Parkway at West County Line Road, on 786 acres.
Site work at both sites began in fall 2023, before the January 2024 announcement. Amazon plans to at least double the Canton campus.
How much is the Amazon Madison County data center project?
Mississippi announced a $10 billion plan for the two Madison County campuses in January 2024. On Apr. 9, 2026, Amazon announced an additional $11 billion investment in Madison County. Together that is $21 billion, the sum. Both are planned investments that include equipment, not construction contracts.
Amazon's figure for all of Mississippi is $25 billion, which also covers projects in Warren and Hinds counties. One builder, Gray Construction, lists a $1.6 billion Amazon campus in Canton on its own page.
How far along are the Amazon Madison County data centers?
In September 2026, five data centers were running on the Canton site and seven more were under construction. In June 2026, the Ridgeland site was in the early stages of construction.
There is a fight over taxes. Amazon argued each finished Canton building is worth about $69 million. The county assessor said about $292 million each. On Aug. 17, 2026, the county supervisors turned down Amazon's appeal.
Water is a fight too. Under a private deal with the city, the Ridgeland campus can draw up to 3.67 million gallons a day, and its wastewater goes to Jackson for treatment. Amazon is putting $37 million into Ridgeland's water system.
Who is building the Amazon Madison County data centers?
AWS picked three general contractors by bid: Gray Construction of Lexington, Kentucky, W.G. Yates & Sons of Philadelphia, Mississippi, and Haskell of Jacksonville, Florida, per a September 2024 news report. Brasfield & Gorrie is also named among the contractors.
Amazon says more than 75 Mississippi companies work on construction and operations in Madison County.
Which trade firms are on the Amazon Madison County data centers?
Wages Civil, a Canton site and civil engineering firm, worked on the sites as work began in fall 2023. The concrete firms Canton Concrete and Delta Industries and the civil contractor Malouf Construction are named among the contractors, along with the engineering firms Neel-Schaffer and Waggoner Engineering. That report gives no scope for each site.
Entergy Mississippi powers the campuses, and Veolia is Amazon's partner on recycled wastewater for cooling at Canton. 12 firms in all are on the list below.
Who Amazon hired before
Amazon Web Services has used several big general contractors for its data center campuses, including Ryan in Indiana and Skanska in Virginia. Gray, one of the builders in Madison County, has also been Amazon's general contractor in central Ohio and Oregon.
- Ryan Companies: builder on Project Rise, the $7 billion AWS data center campus in Wheatfield, Wheatfield, IN, 2026.
- Skanska: builder on Buildings E and F ($300 million each) at Amazon's Quail Ridge data center campus, Aldie, VA, 2025.
- Gray Construction: builder on AWS data center campuses in Hilliard ($300 million first phase) and Plain City (three expansion buildings), Hilliard and Plain City, OH, 2024. Also on this job.
- Gray Construction: builder on Amazon data centers in Boardman, Oregon, and Jerome, Ohio, Boardman, OR and Jerome, OH, 2024. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 12 firms on this job.
How do the ways into the Amazon Madison County data centers compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Amazon's Madison County data centers | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Amazon Madison County data centers?
| Concrete, site and materials suppliers | Canton Concrete, Delta Industries and Malouf Construction, on two campuses of 927 and 786 acres with seven Canton buildings still going up. |
|---|
| Builders' suppliers and big subcontractors | Gray Construction, W.G. Yates & Sons and Haskell, the three general contractors AWS picked by bid, and Brasfield & Gorrie. |
|---|
| Power, water and engineering firms | Entergy Mississippi on power, Veolia on recycled water at Canton, and the engineering firms Wages Civil, Neel-Schaffer and Waggoner Engineering. |
|---|
What should you do next on the Amazon Madison County data centers?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Amazon's data centers in Canton or Ridgeland, Madison County.
Questions people ask about the Amazon Madison County data centers
How much is Amazon spending on data centers in Madison County, Mississippi?
Mississippi announced a $10 billion plan for two Amazon data center campuses in Madison County in January 2024. In April 2026 Amazon announced an additional $11 billion investment in Madison County. Together that is $21 billion, the sum. These are planned investments, equipment included, not construction contracts.
Where are the Amazon data centers in Madison County?
There are two campuses. One is on the Madison County Mega Site off Highway 22 and Nissan Parkway in Canton, on 927 acres. The other is on Highland Colony Parkway at West County Line Road in Ridgeland, on 786 acres.
Who is building the Amazon data centers in Madison County?
A 2024 news report says AWS picked three general contractors by bid: Gray Construction, W.G. Yates & Sons and Haskell. Gray's own page lists a $1.6 billion Amazon campus in Canton. 12 firms are named on the job, listed above.
How many Amazon data centers are in Canton, Mississippi?
In September 2026, five data centers were running on the Canton site and seven more were under construction. Amazon plans to at least double the Canton campus.
What is the Amazon data center tax fight in Madison County?
Amazon argued each of its five finished Canton data centers is worth about $69 million. The county assessor said about $292 million each. On Aug. 17, 2026 the county supervisors turned down Amazon's appeal.
How much water will the Amazon Ridgeland data center use?
Under a private deal with the city, the Ridgeland data center can draw up to 3.67 million gallons a day, and its wastewater goes to Jackson for treatment. Amazon is putting $37 million into Ridgeland's water system.
How many companies work on the Amazon Madison County project?
Amazon says more than 75 Mississippi companies work on construction and operations in Madison County.
Is the Amazon Mississippi data center a $25 billion project?
$25 billion is Amazon's figure for all of Mississippi, including Warren and Hinds counties. The Madison County part is the $10 billion plan plus the $11 billion expansion.
What happens next on the Amazon Madison County data centers?
Seven more Canton data centers are under construction, the Ridgeland campus is being built, and the $11 billion expansion is still ahead. We'll update this page when a new firm appears.
How we built this list
We read Amazon's April 2026 release, the state's 2024 announcement, Gray Construction's own page and news reports from 2024 to September 2026, all on Nov. 21, 2026. We kept each firm a public record names on these two campuses. Most firms come from one September 2024 news report that lists contractors on both sites together and gives no scope for each site, so we do not guess their work beyond each firm's line of business. The $21 billion is the sum of two announced figures, $10 billion (2024) and $11 billion (2026), and both are planned investment, not contracts. Madison County has no public permit portal we could read. Left out: the owner, the county's economic development agency, equipment dealers and rental firms, a separate beverage plant on the same megasite, firms named only by a short name we could not tie to one company, and firms with no website of their own. Phones are each firm's own line from its own site; Gray, Haskell and Brasfield & Gorrie are head office lines, not Mississippi, and Veolia shows no main line on its site. First published Nov. 21, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 21, 2026- Amazon news release: $25 billion in Mississippi data centers (Apr. 9, 2026)
- Mississippi Development Authority: AWS to invest $10 billion (Jan. 2024)
- Magnolia Tribune: Construction industry steps up for AWS (Sept. 8, 2024)
- Gray Construction: ENR Top Starts (May 20, 2025)
- InvestigateTV / WLOX: How data centers shift the landscape (Sept. 24, 2026)
- Mississippi Free Press: Madison County denies Amazon's valuation appeal (Aug. 19, 2026)
- Mississippi Free Press: Inside the private deal between Amazon and Ridgeland water (Sept. 17, 2026)
- Mississippi Today via DeSoto County News: Where Amazon's Mississippi data centers stand (June 9, 2026)
- Construction Review Online: $7bn Project Rise, Amazon breaks ground on Indiana data center campus in Wheatfield (2026-11-16)
- Industrial Info Resources: Tech industry, transport needs fuel Skanska's work across U.S. (2025-07-22)
- Industrial Info Resources: Amazon furthers investment in Ohio data centers (2024-12-18)
- Industrial Info Resources: Gray Construction has hand in $11 billion worth of projects (2024-02-15)