What is the Wallis Annenberg Wildlife Crossing?
It is a bridge for animals, not cars. It crosses all 10 lanes of the 101 Freeway west of Liberty Canyon Road in Agoura Hills, in Los Angeles County. A second span crosses Agoura Road. Caltrans calls it the world's largest wildlife crossing.
The bridge over the 101 is about 210 feet long and 174 feet wide. It sits on 82 precast girders and took 26 million pounds of concrete. Its top is covered in 6,000 cubic yards of living soil and native plants. The two sections stretch 1,250 feet, with 10-foot walls to cut the freeway noise. Caltrans says the crossing will serve over 300,000 drivers a day.
How much does the wildlife crossing cost?
The budget grew from an initial $92 million to $114 million. Caltrans' own project page still shows about $92 million. In February 2026 the California Transportation Commission put up the final $18 million to finish it.
Much of the money is private. The Annenberg Foundation gave $25 million, and about 6,000 members of the public donated. Caltrans runs the job with the National Wildlife Federation.
Who built the wildlife crossing?
Seven builders bid the bridge (contract 07-307104) on March 8, 2022. C. A. Rasmussen, Inc. of Valencia was low at $22,719,732.30, about $2.8 million under the state's estimate of $25,541,391.10. Skanska, Security Paving, Flatiron West, Griffith, Granite and Ames also bid. Work began June 8, 2022.
Rasmussen's bid lists its subcontractors: Comet Electric (electrical), Coreslab (the precast girders), Integrity Rebar (reinforcing steel), Pacific Waterproofing (deck waterproofing) and Griffith Company (most of items 42 to 80). In 2025 Rasmussen's project manager also named Malcolm Drilling as a key subcontractor. On busy days up to 40 Rasmussen and subcontractor workers are on site, and the crew logged over 50,000 field hours by early 2025.
What is the last contract on the crossing?
On Aug. 6, 2026, Caltrans opened 3 bids for contract 07-1A7204, wildlife fencing and outriggers that keep animals off the freeway and steer them to the bridge. Interstate Civil Construction of Wrightwood was low at $1,289,417.40, about 23% over the state's estimate of $1,050,650.
Work began Sept. 4, 2026 and is due Dec. 18, 2026. Caltrans' construction record listed it 34% done. The main contract, 07-307104, was listed 78% done, with an estimated end of Aug. 18, 2027.
When does the wildlife crossing open?
The span over the 101 was finished in June 2025. The span over Agoura Road and the planting came next. The official opening ceremony is Dec. 2, 2026.
Animals did not wait. In early November 2026, wildlife cameras caught a coyote on the bridge.
Who designed the wildlife crossing?
Living Habitats, the Chicago practice of designer Robert Rock (now Rock Design Associates), leads the design. HNTB did the structural engineering, Olsson the soil science, LimnoTech the hydrology and Spiegel Aihara Workshop the architecture.
The lead designer's team list also names Pachyderm Acoustics for noise modeling, WC3 for irrigation and SymbioRoots for soil fungi. 19 firms in all are on the list below.
Who Caltrans District 7 hired before
Caltrans' Los Angeles district keeps seeing the same builders: C. A. Rasmussen came in as low bidder on at least three more District 7 jobs since 2023, and Griffith on one in northern Los Angeles County.
- C. A. Rasmussen, Inc.: builder (low bidder) on Job in Los Angeles from Route 1 to Devonshire Street, $40.6M, Los Angeles, CA, 2023. Also on this job.
- C. A. Rasmussen, Inc.: builder (low bidder) on Route 138 in Llano, $28.9M, Llano, CA, 2026. Also on this job.
- C. A. Rasmussen, Inc.: builder (low bidder) on Road job in Somis from Sand Canyon Road to near Balcom Canyon Road, Somis, Ventura County, CA, 2025. Also on this job.
- Griffith Company: builder (low bidder) on Job in Los Angeles County from the Lake Hughes Road undercrossing to south of Vista del Lago, Castaic area, LA County, CA, 2025. Also on this job.
- Flatiron West, Inc.: builder (low bidder) on Route 210 in Los Angeles from I-5 to the Wheatland Avenue undercrossing, $135.5M, Los Angeles, CA, 2020.
These are earlier or other jobs for the same owner. They are not counted in the 19 firms on this job.
How do the ways into the wildlife crossing compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Annenberg wildlife crossing | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The builder's next Caltrans jobs | A place on C. A. Rasmussen's or Griffith's team for their next District 7 bids | Subcontractors and suppliers in Southern California | Repeat work with a builder Caltrans keeps hiring | This crossing is near its end; most of its buying is done |
Who should go after the wildlife crossing?
| Fence, steel and site suppliers | Interstate Civil Construction's $1.29 million wildlife fencing contract, under way to Dec. 18, 2026, and C. A. Rasmussen's site and habitat work. |
|---|
| Concrete, rebar and electrical suppliers | Coreslab (precast girders), Integrity Rebar (reinforcing steel) and Comet Electric, all on Rasmussen's winning bid. |
|---|
| Builders, equipment and landscape firms | C. A. Rasmussen has also been low bidder on other Caltrans Los Angeles-district jobs, and its machine dealers are named on this one. |
|---|
What should you do next on the wildlife crossing?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Wallis Annenberg Wildlife Crossing in Agoura Hills.
- Watch the Dec. 2, 2026 opening and C. A. Rasmussen's next Caltrans bids.
Questions people ask about the wildlife crossing
How much does the Wallis Annenberg Wildlife Crossing cost?
The total budget is $114 million, up from an initial $92 million. The state put up the final $18 million in February 2026. The Annenberg Foundation gave $25 million, and about 6,000 members of the public donated.
Who is building the wildlife crossing?
C. A. Rasmussen, Inc. of Valencia is the general contractor. It won the bridge (contract 07-307104) in 2022 as low bidder at $22.7 million. Interstate Civil Construction holds the $1.29 million fencing contract. 19 firms are named on the job, listed above.
When does the wildlife crossing open?
The official opening ceremony is Dec. 2, 2026. In early November 2026, wildlife cameras caught a coyote on the bridge.
Where is the wildlife crossing?
Over US-101 (the Ventura Freeway) west of Liberty Canyon Road in Agoura Hills, Los Angeles County, California. A second span crosses Agoura Road.
How big is the wildlife crossing?
The bridge over the 101 is about 210 feet long and 174 feet wide, on 82 precast girders. With the span over Agoura Road it stretches 1,250 feet. It took 26 million pounds of concrete and 6,000 cubic yards of living soil.
Who are the subcontractors on the wildlife crossing?
Rasmussen's winning bid lists Comet Electric, Coreslab, Integrity Rebar, Pacific Waterproofing and Griffith Company. Its project manager also named Malcolm Drilling. Coastline Equipment, Quinn and Herrmann Equipment back the builder with machines.
Who designed the wildlife crossing?
Living Habitats (Rock Design Associates) leads the design, with HNTB for structural engineering, Olsson for soil, LimnoTech for hydrology, Spiegel Aihara Workshop for architecture, plus Pachyderm Acoustics, WC3 and SymbioRoots.
How many builders bid the wildlife crossing?
Seven bid the bridge on March 8, 2022. C. A. Rasmussen was low at $22,719,732.30, under the state's $25,541,391.10 estimate. Three bid the fencing on Aug. 6, 2026.
How can suppliers get on the wildlife crossing?
Call the firms already on the job, starting with C. A. Rasmussen and Interstate Civil Construction. The fencing contract runs to Dec. 18, 2026, and the main contract's estimated end is Aug. 18, 2027.
What happens next on the wildlife crossing?
The official opening is Dec. 2, 2026, the fencing is due Dec. 18, 2026 and the main contract's estimated end is Aug. 18, 2027. We'll update this page when a new contract or firm appears.
How we built this list
We read Caltrans' two bid summaries for the crossing (contracts 07-307104 and 07-1A7204), its construction record, project page and news release; the lead designer's team list and the National Wildlife Federation's 2020 release; and news and trade press, all on Nov. 22, 2026. We kept each firm a public record names on this project. Five are on the builder's own subcontractor list, one was named by the builder's project manager, and three are equipment dealers named as backing the builder, a vendor tie and not a subcontract. Griffith's role is the reading of its bid items; the bid record does not name the work. Left out: Caltrans (the owner), funders and public partners, the losing bidders and their subcontractors, utility owners whose lines were moved, a nonprofit design partner, equipment makers, and research institutes and individuals on the design team. No subcontractor list was published for the span over Agoura Road. Phones are each firm's own line from its own site, except Interstate Civil Construction's, which is from the bid record; Integrity Rebar's is from a business directory because its site blocked our reads; HNTB's is a company-wide line and Olsson's is its Lincoln headquarters line; and Malcolm Drilling, LimnoTech, Spiegel Aihara Workshop, Pachyderm Acoustics, WC3 and SymbioRoots show no line we could capture. First published Nov. 22, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 22, 2026- AP via Anchorage Daily News: Over a freeway near LA, animals can roam safely (Nov. 18, 2026)
- LAist: Coyote becomes first mammal seen using 101 wildlife crossing (Nov. 5, 2026)
- Caltrans District 7: US-101 Wallis Annenberg Wildlife Crossing project page (read Nov. 22, 2026)
- Caltrans District 7: World's largest wildlife crossing enters final phase of construction (June 25, 2025)
- Caltrans bid summary, contract 07-307104 (bids opened March 8, 2022)
- Caltrans bid summary, contract 07-1A7204 (bids opened Aug. 6, 2026)
- Caltrans construction record, contract 07-1A7204
- ABC7: California to provide $18 million to finish wildlife crossing (Feb. 8, 2026)
- Construction Equipment Guide: U.S. 101 wildlife crossing nears completion (Feb. 4, 2025)
- ENR: Southern California's wildlife crossing prepares for its debut (Aug. 19, 2025)
- ENR: Caltrans to break ground on Wallis Annenberg Wildlife Crossing (April 18, 2022)
- National Wildlife Federation: New look at wildlife crossing (Oct. 21, 2020)
- Living Habitats: Liberty Canyon Crossing team (read Nov. 22, 2026)
- Caltrans Bid Summary 07-322904, opened 2023-10-11
- Caltrans Bid Summary 07-286304, opened 2026-04-28
- Caltrans Bid Summary 07-369704, opened 2025-03-19
- Caltrans Bid Summary 07-370404, opened 2025-01-07
- Caltrans Bid Summary 07-3096U4, opened 2020-03-17