What did Bally's promise for the A's ballpark?
On Nov. 19, 2026, Bally's chairman Soo Kim told Nevada's Gaming Control Board that Bally's will cover an initial $250 million to build several of the stadium's non-gaming parts. Bally's is responsible for the northwest plaza entrance. He called the funding talks with the A's and the land owner complicated.
The board's chair, Mike Dreitzer, said he had significant concerns about one of the most iconic corners on the Strip. The Stadium Authority takes up the plaza on Dec. 3.
The plaza is the walkway from the Strip and Tropicana Avenue to the stadium's main entrance, which sits more than 35 feet above the ground. Bally's says it is a 12-month job that must start by January 2027 to finish for the 2028 opening. The land owner set aside $125 million and is willing, with conditions, to go to $250 million, and an A's adviser said developers are working on a contingency plan for the plaza.
- No builder is named for the plaza or podium in any record we read.
- A $90 million Bally's podium garage filing beside the ballpark is still in review as of Nov. 23, 2026.
How far along is the A's ballpark?
As of Nov. 12, 2026, the ballpark was more than halfway built, with nearly $700 million spent. Crews had set 3 of its 5 steel roof trusses, and the last is expected before the end of the year.
The 33,000-seat stadium sits under 5 roof arches that span nearly 700 feet, the tallest about 290 feet up. The construction target is Feb. 29, 2028, about 15 months of work from mid-November, for the 2028 season.
- Bomel Construction holds the foundation jobs for the southeast garage, $23,143,190, and the central utility plant, $9,895,460.
- ENGEO is the geotechnical agency on the ballpark's inspection record.
Who is on the A's central utility plant permits?
On Oct. 27, 2026, Clark County issued 3 trade permits for the foundation of the A's central utility plant, with its first lift and deep utilities. Bomel Construction is the contractor on that foundation job. Harris Las Vegas holds the mechanical and plumbing permits, and Morse Electric holds the electrical permit.
Each permit repeats the foundation job's value, $9,895,460. That isn't the plant's cost or a firm's contract. The plant's own building, with its core, shell and buildout, is a separate $15,849,460 filing that names no contractor yet.
Two weeks earlier, on Oct. 14, the same 2 firms got the plumbing and electrical permits for the southeast garage's foundation. We found no press naming Harris or Morse on the ballpark.
- Harris Las Vegas also holds the ballpark's core and shell and interior buildout mechanical permits from March 2026.
- Murray Company holds the ballpark's plumbing permits and says it has the design assist plumbing scope.
- Harris Rebar Las Vegas, a different company from Harris Las Vegas, is approved to fabricate rebar for the plant and garage foundations.
What's being bought at the A's ballpark, and when?
The construction manager told the Stadium Authority's oversight committee on May 5, 2026 that it had more than $1 billion in awarded work and 525 to 550 craft workers on site daily. The minutes say structural steel was bought early from a single supplier.
The newest work is in the ground: the plant's and garage's foundations, first lifts and deep utilities. A permit for walk-in coolers at the ballpark was filed on Oct. 23, 2026.
- Plant building. A $15,849,460 filing for its core, shell and buildout went in Aug. 24, 2026 and is waiting on the applicant.
- Garage superstructure. A $78,177,164 filing for levels P1 to P6 went in Sept. 14, 2026 and is waiting on the applicant.
- Bally's garage. A $90 million podium garage for the resort beside the ballpark is still in review as of Nov. 23, 2026.
We found no public bid list or bid date for any of this work.
Who the Las Vegas Stadium Authority hired before
The Stadium Authority also owns Allegiant Stadium, and the same builder and architect of record from the Raiders' stadium are back on the A's ballpark.
- Mortenson | McCarthy joint venture: builder on Allegiant Stadium, the Raiders' stadium, Las Vegas, NV, 2020. Also on this job.
- HNTB: architect of record on Allegiant Stadium, Las Vegas, NV, 2020. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 32 firms on this job.
How do the ways into the A's ballpark compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Selling to Bomel Construction | A call to Bomel's main office | Concrete, rebar, forming and site suppliers | The contractor on the plant's and garage's foundation jobs, $33 million together | Foundations come early, and some of the buy may be done |
| Selling to Harris | A call to Harris's Las Vegas office | HVAC, pipe, valve, hanger, insulation and controls suppliers | The firm on the plant's and garage's foundation mechanical and plumbing permits | The permits list no equipment, and some may be bought |
| Selling to Morse Electric | A call to Morse's Las Vegas office | Electrical distributors, conduit and gear reps | The firm on every ballpark electrical permit we read | Most core and shell work was permitted in early 2026 |
| The small local business goal | Mortenson | McCarthy's 15% target, met through its trade partners' sub-tiers | Small local suppliers and subs | A reason for trade partners to add local sub-tiers | It runs through the trade partners, not a public form |
| The Strip plaza entrance | Bally's plaza and podium, before the Stadium Authority Dec. 3 | Concrete, steel, paving and site trades | A 12-month job Bally's says must start by January 2027 | No funding deal or builder is settled yet |
| The next filed buildings | The plant's building and the garage superstructure, filed and waiting | Trades that want the next stage | Work no trade is named on yet | No contractor or bid date is on the record |
| The design team | BIG, HNTB and Thornton Tomasetti | Manufacturers and spec reps | A chance to get a product into the drawings | Most of the ballpark's design is set |
Who should go after the A's ballpark, and who shouldn't?
| Concrete, rebar and forming suppliers | Bomel Construction holds the southeast garage's $23,143,190 foundation job and the plant's $9,895,460 foundation job. |
|---|
| HVAC and mechanical suppliers | Harris holds the plant's foundation mechanical permit, issued Oct. 27, 2026, and the ballpark's core and shell mechanical. |
|---|
| Pipe, valve and plumbing suppliers | Harris holds the plumbing permits on the plant's and garage's foundations. |
|---|
| Concrete and site trades that want the next stage | The plant's building, the garage superstructure and Bally's plaza entrance all name no builder yet. |
|---|
| Firms that need a public bid date | This isn't the job for you yet, because we found none. |
|---|
What should you do next on the A's ballpark?
- Call Bomel Construction if you sell concrete, rebar or forming.
- Call Harris's Las Vegas office if you sell HVAC, pipe or valves.
- Call Morse Electric's Las Vegas office if you sell electrical gear or conduit.
- If you're a small local supplier, pitch the trade partners on the construction manager's 15% goal.
- Watch the Stadium Authority's Dec. 3 meeting on the plaza entrance.
- Open the full list and watch the plant's building and garage superstructure filings.
Questions people ask about the A's Las Vegas ballpark
Who is building the A's Las Vegas ballpark?
The Mortenson | McCarthy team, as construction manager at risk, according to Mortenson's project page and the Stadium Authority oversight committee's May 5, 2026 minutes.
How much does the A's ballpark cost?
$2.1 billion, in November 2026 reports. It was $1.5 billion in 2023, and the team said in December 2025 it had risen to $2 billion from a $1.75 billion goal. Nearly $700 million had been spent by Nov. 12, 2026.
When does the A's ballpark open?
It is set to open for the 2028 MLB season, with a construction target of Feb. 29, 2028, about 15 months of work from mid-November 2026.
How far along is the A's ballpark?
More than halfway built as of Nov. 12, 2026. Three of its 5 roof trusses are up, the last is expected before the end of the year, and nearly $700 million has been spent.
What did Bally's commit to the A's ballpark?
On Nov. 19, 2026, Bally's chairman Soo Kim told Nevada's Gaming Control Board that Bally's will cover an initial $250 million to build several of the stadium's non-gaming parts. Bally's is responsible for the northwest plaza entrance. Board chair Mike Dreitzer said he had significant concerns. The Stadium Authority takes up the plaza on Dec. 3.
Why does the plaza entrance matter?
It is the walkway from the Strip and Tropicana Avenue to the stadium's main entrance, which sits more than 35 feet above the ground. Bally's says it is a 12-month job that must start by January 2027 to finish for the 2028 opening.
Who owns the A's ballpark?
The Las Vegas Stadium Authority owns it, and the A's operate it. The county's records list Athletics StadCo, LLC as the tenant and Tropicana Land LLC as the land owner.
What is the A's central utility plant?
A separate building on the site. The county's Oct. 27, 2026 permits cover its foundation, first lift and deep utilities, and its building is a separate filing. No source we read says which systems it holds.
Who is building the A's ballpark's foundations?
Bomel Construction is the contractor on the southeast garage's $23,143,190 foundation job and the central utility plant's $9,895,460 foundation job. ENGEO is the geotechnical agency on the ballpark's inspection record.
Who is the mechanical contractor on the A's ballpark?
Harris Las Vegas is on the mechanical and plumbing permits for the plant and garage foundations, and on the ballpark's core and shell and interior mechanical permits.
Who is the electrical contractor on the A's ballpark?
Morse Electric holds every electrical permit on the ballpark we read, including the plant's and garage's foundations, issued Oct. 27 and Oct. 14, 2026.
How do subcontractors and suppliers get on the A's ballpark?
Through the trade firms on the county's permits. The construction manager reports a 15% small local business target and requires its trade partners to report what they'll award to small local sub-tiers.
Can I bid on the A's ballpark?
We found no public bid list or bid date for any remaining package.
What's next on the A's ballpark?
The Stadium Authority takes up the plaza entrance on Dec. 3. The plant's building, a $15.8 million filing, and the southeast garage's superstructure, a $78.2 million filing, are waiting on the applicant. Their trade permits will name the next firms.
Where is the central utility plant?
The county's grading permit puts it in the southeast part of the site, beside the southeast garage. One July 2026 news report said northwest, and we follow the record.
What are the risks of chasing this job?
The core and shell work was permitted in early 2026, structural steel was bought early from a single supplier, and the permits list no equipment. We found no public bid date.
How we built this list
We read Clark County's public permit records for the ballpark (re-read Nov. 23, 2026), the Stadium Authority's Nov. 4, 2026 agenda book and its oversight committee's May 5, 2026 minutes, the design firms' releases, the firms' own pages where we could, and press coverage through Nov. 19, 2026. A row is on the list only if a record ties it to the ballpark or its site. Trade permits repeat their building job's value, so we never add them, and $9,895,460 is the plant's foundation job, not the plant. A row with no bid date is never marked open. First published Nov. 7, 2026. Updated Nov. 23, 2026 with Bally's $250 million plaza commitment, the halfway mark, the $2.1 billion cost and 2 new firms on the record, Bomel Construction and ENGEO. We'll update this page when a new permit, firm or bid date appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 23, 2026- Clark County permit records
- The Nevada Independent, Nov. 19, 2026
- The Nevada Independent, November 2026
- Casino.org, Nov. 12, 2026
- Construction Review Online, Nov. 13, 2026
- Las Vegas Stadium Authority, agenda book, Nov. 4, 2026
- Las Vegas Stadium Authority, committee book, Aug. 17, 2026
- The Nevada Independent
- Thornton Tomasetti, June 26, 2025
- Murray Company, Oct. 29, 2025
- Harris, Locations
- The Morse Group, Contact
- BIG, Athletics Las Vegas Ballpark
- Mortenson, Las Vegas Athletics Ballpark
- Thornton Tomasetti, roof milestone
- News 3 Las Vegas, Oct. 7, 2026
- Bomel Construction
- ENGEO, Contact
- McCarthy, Las Vegas
- HNTB, Las Vegas
- Las Vegas Paving, Contact
- Mortenson: Allegiant Stadium
- HNTB: Allegiant Stadium