Who is building AT&T's Plano headquarters?
Texas's environmental agency lists Austin Commercial, LP of Dallas as the operator on the construction stormwater authorization for the site, filed as Project Eagle at Legacy Drive and Parkwood Boulevard. Coverage began Aug. 17, 2026 for 60.19 acres, with work estimated to run to March 30, 2029.
A second operator, a joint venture filed as "At Jv," took coverage on the same 60.19 acres on Oct. 15, 2026. Its mailing address is the Dallas post office box the state lists for Austin Commercial, and no record we read names its members.
That record is stormwater permit coverage, which a site operator needs before it disturbs land. It isn't a contract, and no contract value for Austin Commercial is public. None of the news coverage we read names a general contractor.
Southwest Demolition Services held the state's stormwater coverage for demolition at 5400 Legacy Drive, the old EDS campus, with work estimated to end Nov. 11, 2026. That record doesn't name AT&T.
What are the 11 buildings registered for AT&T's Plano campus?
KDC Legacy Eagle HQ Development One, LLC, the owner, registered 11 buildings with Texas for accessibility review on Oct. 14, 2026. Each names Gensler as the design firm, gives Dec. 1, 2026 as the start date and March 31, 2029 as the completion date, and describes new, privately funded construction.
These are accessibility registrations, not building permits. Plano's permit portal was down when we checked on Nov. 7, 2026, so we read no city building permit for the campus.
- Building 4. About 679,000 square feet of office space, at a $201 million estimated cost, the largest on the campus.
- Five more offices: Buildings 1, 2, 3, 6 and 7 run from 225,000 to 318,000 square feet each, at $68.9 million to $115.4 million. Building 7 adds a fitness center.
- Building 8. About 215,700 square feet of office lobby and food hall, at a $57.7 million estimated cost.
- Utility plant. About 32,000 square feet of central utility plant for the whole campus, at a $75.8 million estimated cost.
There's no Building 5 on the record. The 11 estimated costs add up to $1,052,300,000. That's the sum of the owner's estimates, not a contract value.
What concrete is being bought for AT&T's Plano headquarters?
The 3 parking garages are the campus's biggest concrete job: about 2.8 million square feet by the registrations' own descriptions, with $271.6 million in estimated costs between them.
- Garage C: About 1,178,000 square feet of cast-in-place concrete, at $120.1 million, on Alexander G Bell Blvd.
- Garage B: About 1,096,000 square feet of precast concrete, at $95.9 million.
- Garage A: About 553,000 square feet of precast concrete, at $55.6 million.
- Box culverts: Plano's planning commission approved the final site plan on Sept. 21, 2026, after dry detention ponds were changed to box culverts. No record says whether they're precast or poured.
No record names a ready-mix supplier, a precaster or a concrete subcontractor, and we found no concrete batch plant filed for the site. The garages are scheduled to start Dec. 1, 2026, which is the owner's estimate, not a bid date.
Who else is named on AT&T's Plano headquarters?
KDC is the developer, and its owner company is on all 11 registrations. Press coverage names Gensler and SWA Group on design, with SWA as the landscape architect, and Kimley-Horn as the engineering consultant. JPMorgan Chase is providing KDC a $400 million construction loan.
Plano's planning commission approved the campus's preliminary site plan on May 4, 2026, for office, a day care center and a commercial antenna support structure on 54.2 acres. The city later approved setbacks for a 280-foot sculpture that can hold a stealth commercial antenna.
How do the ways into AT&T's Plano headquarters compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Austin Commercial | The operator on the site's state construction stormwater authorization since Aug. 17, 2026 | Concrete, site utility and building product sellers | A conversation with the builder on the state's record | No contract or price for it is public, and we found no bid list for this campus |
| Austin Commercial's prequalification form | The partner prequalification form linked from its partnerships page | Subcontractors new to Austin Commercial | Your firm on file with the builder | The page doesn't say prequalifying puts you on this job |
| KDC | The developer, and the owner on all 11 state registrations | Firms that sell to owners and developers | The party paying for the campus | An owner usually buys most materials through its builder |
| Gensler | The design firm on every state registration | Product reps who need to be specified | A chance to be written into the drawings | Specification isn't a sale, and its document dates aren't public |
| Kimley-Horn and SWA Group | The engineering consultant and the landscape architect named in press coverage | Storm pipe, culvert, paver and site furnishing reps | A specification door for the site work | Neither is on a state record, and their exact scopes aren't stated |
Who should go after AT&T's Plano headquarters, and who shouldn't?
| Concrete and rebar suppliers | Garage C is about 1,178,000 square feet of cast-in-place concrete, and all 3 garages are scheduled to start Dec. 1, 2026. |
|---|
| Precast concrete producers | Garages A and B are registered as precast, about 1,649,000 square feet together, and no precaster is named. |
|---|
| Mechanical and electrical contractors and suppliers | The central utility plant that will serve the campus carries a $75.8 million estimated cost. |
|---|
| Firms that need an open bid with a date | This isn't the job for you yet: we found no public bid, plan room or due date for the campus. |
|---|
What should you do next on AT&T's Plano headquarters?
- Call Austin Commercial at 214-443-5700 if you sell concrete, rebar or site utilities.
- Fill out Austin Commercial's partner prequalification form before the scheduled Dec. 1, 2026 start.
- Call Gensler's Dallas office if your product needs to be specified on the buildings or garages.
- Open the full list and call the firm named for your trade.
Questions people ask about AT&T's Plano headquarters construction
Who is building AT&T's new headquarters in Plano?
None of the news coverage we read names a general contractor. Texas's environmental agency lists Austin Commercial, LP as the operator on the site's construction stormwater authorization, with coverage from Aug. 17, 2026. A joint venture filed under Austin Commercial's mailing address became a second operator on Oct. 15, 2026.
Did Austin Commercial win the AT&T headquarters contract?
No public record says so. Austin Commercial is the operator on the site's state stormwater record, and no contract or price for it is public.
How much will AT&T's Plano headquarters cost?
Press coverage puts AT&T's Plano headquarters at $1.35 billion. The 11 state registrations carry $1,052,300,000 in estimated costs between them. That's the sum of the owner's estimates, not a contract value.
When does construction start on AT&T's Plano headquarters?
All 11 state registrations give a scheduled start of Dec. 1, 2026 and completion of March 31, 2029. Those are the owner's estimates.
How big are the parking garages at AT&T's Plano campus?
Garage C is about 1,178,000 square feet of cast-in-place concrete, at a $120.1 million estimated cost. Garage B is about 1,096,000 square feet of precast at $95.9 million, and Garage A is about 553,000 square feet of precast at $55.6 million.
Is the state filing a building permit?
No. The 11 filings are registrations for accessibility review under Texas's architectural barriers law. Plano's permit portal was down when we checked on Nov. 7, 2026, so no city building permit is on this list.
Who designed AT&T's Plano headquarters?
Gensler is the design firm on every state registration. Press coverage names SWA Group as the landscape architect and Kimley-Horn as the engineering consultant.
Is any work on AT&T's Plano campus out to bid?
We found no public bid, plan room or due date for the campus. Austin Commercial's partnerships page links a partner prequalification form, but it doesn't list bids for this job.
How do subcontractors and suppliers get on AT&T's Plano headquarters?
Call the builder on the state's record, Austin Commercial, at 214-443-5700, or fill out its partner prequalification form. Product reps can also reach Gensler's Dallas office about specification. None of these guarantees work.
What are the risks of chasing this work?
No contract is public, so Austin Commercial's role on each building isn't confirmed. Dec. 1 is an estimate and can move. No concrete supplier or precaster is named yet, and some packages may be bought before any record shows it.
What was on the site before?
The former EDS campus at 5400 Legacy Drive. Press coverage reports demolition started May 20, 2026, and the old EDS headquarters was imploded on Aug. 9, 2026.
What happens next on AT&T's Plano headquarters?
The registrations put the start at Dec. 1, 2026. We'll read Plano's building permits for the campus once the city's portal is back, and add any firm they name to this list.
How we built this list
We read the 11 public registrations for the campus with the Texas Department of Licensing and Regulation, the Texas Commission on Environmental Quality's construction stormwater records for the site, the City of Plano's planning commission results, the Texas Comptroller's franchise tax file, and press coverage. A row is on the list only if one of those records ties it to the campus or its address. Where we add estimated costs together, we say so, an estimated cost on a registration is never a contract value, and a row is marked as a bid only when a due date is published. We found none. Plano's permit portal was down when we checked on Nov. 7, 2026, so no city building permit is on this list. First published Nov. 8, 2026. We'll update this page when Plano's building permits for the campus can be read, a bid date appears, or a new state filing names a firm.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- TDLR, Project Eagle Garage C registration
- TDLR, Project Eagle Garage B registration
- TDLR, Project Eagle Garage A registration
- TDLR, Project Eagle central utility plant registration
- TDLR, Project Eagle Building 1 registration
- TDLR, Project Eagle Building 2 registration
- TDLR, Project Eagle Building 3 registration
- TDLR, Project Eagle Building 4 registration
- TDLR, Project Eagle Building 6 registration
- TDLR, Project Eagle Building 7 registration
- TDLR, Project Eagle Building 8 registration
- TCEQ, water quality general permits search (TXR1509ZE, TXR1542ZT, TXR1566XV)
- City of Plano, Planning and Zoning results, May 4, 2026
- KERA via KEDT, Sept. 22, 2026
- Connect CRE, Sept. 21, 2026
- Community Impact, March 19, 2026
- Community Impact, May 29, 2026
- Austin Commercial, partnerships
- CRE Daily, May 7, 2026