What's the form contractors can fill out for the Audi plant in Georgia?
The form is on the website of the Mid-Georgia Gateway Joint Development Authority, the 3-county authority over the Audi site. Its contact page asks "What is your question about?" and offers "Contractors and vendors" as a choice.
The form is an inquiry. The page says your details "are used only to reply to you, are not added to a mailing list." It promises no bid and gives no timeline. We didn't test it.
We found no Audi vendor page and no bid list for the plant. No builder is named, so this form is the one door for contractors we could find that's tied to the site.
The authority matters because of the money behind it. Macon-Bibb County's record says a May 26, 2026 contract provides "for the funding of various public works necessary for the development of an industrial megasite." Macon-Bibb's share is $7,000,000. Each of the 3 counties pledged up to $7 million, for up to $21 million. That money also covers marketing and land, so it isn't all construction.
- Who runs it: Mid-Georgia Gateway Joint Development Authority
- Where: Mggjda.com/contact
- The choice to pick: "Contractors and vendors"
- What it isn't: A bid list or a bid invitation
- Agendas and minutes: Mggjda.com/stay-connected
What's being bought for the Audi plant in Fort Valley, Georgia?
Georgia expects Audi to start grading in 2027 and construction in 2028. No package, bid date or builder is published for either one. The $4 billion is total investment, so it isn't a construction budget.
The state also proposed a training center, reported at $73.5 million in unsigned draft agreements. Georgia says Georgia Quick Start will "design a designated training facility." We found no site or builder for it.
The firmest numbers sit at the site's gate, in road and utility work planned before Audi. Georgia's file for Highway 96 goes back to a 2003 plan. It now shows "two proposed roundabouts" along the site's boundary "for the primary and truck entrances." These are state and utility jobs, so none of them is an Audi contract.
- Grading at the plant: Planned for 2027, size not published
- Factory construction: Planned for 2028, about $4 billion total investment
- Training center: $73.5 million in unsigned drafts, no date
- Highway 96 widening, planned before Audi: $73,168,870.31 estimated, target let date Sept. 15, 2029
- Highway 96 right of way, planned before Audi: $9,918,480, target date March 22, 2027
- Highway 96 utility relocations, planned before Audi: $12,192,948.33 estimated
- SR 49 Connector extension, planned before Audi: $72,911,234 estimated, 2.8 miles of new road
- Wastewater expansion: Up to 6 million gallons a day, preliminary design, 36 months to build
How do the ways into the Audi plant in Georgia compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The authority's contact form | A form on the authority's website | Any contractor or vendor | A message to the authority over the site | It's an inquiry, so it isn't a bid list, and it gives no timeline |
| The authority's agendas | A page of board agendas and minutes | Firms tracking when decisions come | Advance notice of board meetings | It has no bids, and the Oct. 23 minutes aren't posted |
| Georgia DOT prequalification | An application to the state | Highway contractors and subs | A place on the state's list for the gate roads | It covers road work planned before Audi, not the plant, and the target let date is 2029 |
| Volkswagen Group's supplier platform | A registration on its global platform | Parts and production suppliers | A supplier account with Audi's parent | It's global, it doesn't mention Georgia, and it isn't for construction firms |
| Calling a named firm on the road | A call to AtkinsRéalis | Survey, geotech and environmental firms | A conversation with the road's design lead | It's named on the road only, and nothing says it's hiring |
Who should go after the Audi plant, and who shouldn't?
| Earthwork and site contractors | Start with the form, because grading is the first scheduled work on the plant. |
|---|
| Paving, aggregate and concrete suppliers | The Highway 96 file has real quantities, including 71,010 tons of base asphalt, but the target let date is 2029. |
|---|
| Water, gas and utility contractors | The Fort Valley Utility Commission serves the site and owns most of the utility work on the road. |
|---|
| Firms that need a bid date this year | This isn't the job for you yet, because we found no bid date for the plant. |
|---|
What should you do next on the Audi plant?
- Fill out the authority's form if you do site, civil or building work.
- Check the authority's agendas before each board meeting.
- Finish Georgia DOT prequalification if you want the road work.
- Get the full list and call the offices named for your trade.
Questions people ask about the Audi plant in Georgia
Who is building the Audi plant in Georgia?
No builder is named. We found no general contractor, design-builder or grading contractor in any record through Nov. 4, 2026.
Who is the general contractor on the Audi plant in Fort Valley?
None is named. Rivian picked its own builder in Georgia, and Hyundai's site authority publicly bid its grading. Either route is possible for Audi, and neither proves what Audi will do.
How do subcontractors get on the Audi plant in Georgia?
We found no bid list. The site authority's contact form has a "Contractors and vendors" option. It's an inquiry, and it promises no bid.
When is the Audi plant in Georgia bidding?
We found no public bid date. Georgia expects grading in 2027 and construction in 2028. No source says whether Audi or the authority lets the grading.
What happens after a contractor fills out the Audi site form?
The authority's page says your details are used only to reply to you and aren't added to a mailing list. It gives no timeline. We didn't test the form.
Is the Audi plant in Georgia final?
No. Volkswagen's supervisory board still has to decide. A Macon-Bibb County agreement says its industrial authority doesn't guarantee the project will close or proceed.
Where exactly is the Audi plant in Georgia?
It's planned for the Middle Georgia Megasite on Highway 96, about 1.5 miles east of Fort Valley, in Peach County. The site is about 1,500 acres. It isn't in Macon.
How much is Audi spending on the Georgia plant?
Audi plans about $4 billion. Reports on the state's records describe an option for $3 billion more and 3,000 more jobs. Audi has until the end of 2033 to use that option.
How much public money is going into the Audi plant?
Press reports on unsigned draft agreements count at least $958.4 million for the first phase. About $458.6 million of that is property tax savings, so it isn't a construction budget. Georgia hasn't published a final figure.
What road work is planned near the Audi plant in Georgia?
Georgia DOT plans to widen about 6 miles of Highway 96, with an estimated $73.2 million in construction and a target let date of Sept. 15, 2029. The state approved the design on Sept. 2, 2026. The state has planned this road since 2003, so it isn't an Audi contract.
When will the Audi plant in Georgia start production?
Georgia expects full production in 2031, at 200,000 vehicles a year. Audi says production starts in the early 2030s.
What are the risks of chasing the Audi plant in Georgia?
Volkswagen's board hasn't signed off, and we found no bid date. The form promises no bid, and the road work is years out. The training center and public money figures come from unsigned drafts.
How we built this list
We read the state's and Audi's announcements, a county commission record, the state's road files, and the authority's and utility's own pages. A row is on the list only if a source ties it to the plant or to the road and utility work at the site's gate. We left out hiring pages and nearby jobs with no stated tie, and we mark each row by how firm it is. A row with no bid date is never marked as bidding. First published Nov. 4, 2026. We'll update this page when a builder, a permit, Volkswagen's decision or a bid date appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 4, 2026- Governor of Georgia, Oct. 24, 2026
- Georgia Dept. of Economic Development, Audi of America
- Audi, press release
- Mid-Georgia Gateway JDA, Contact
- Mid-Georgia Gateway JDA, The Site
- Mid-Georgia Gateway JDA, Infrastructure
- Mid-Georgia Gateway JDA, Stay Connected
- Macon-Bibb County Commission packet, Nov. 3, 2026
- The Macon Newsroom, Nov. 4, 2026
- The Macon Newsroom, July 17, 2026
- Georgia DOT, PI 0008387
- Georgia DOT, Location and Design Report, Sept. 2, 2026
- Georgia DOT, Concept Report, Oct. 2025
- Georgia DOT, PI 0013678
- Georgia DOT, Construction Contractors
- Fort Valley Utility Commission, Bids
- Middle Georgia Mega Site utility exhibit, Aug. 2022
- Volkswagen Group, ONE.KBP
- Norfolk Southern, Oct. 27, 2026
- ENR
- AJOT, Reuters report
- Atlanta News First, Nov. 2, 2026
- North Atlanta Star, Nov. 3, 2026
- WGXA, Oct. 28, 2026
- SEDA, Bryan County Megasite invitation to bid
- Construction Dive, Rivian and Clayco