What is Bally's building in Chicago?
Bally's is building Chicago's first permanent casino on the site of the Chicago Tribune's former Freedom Center printing plant at Halsted Street and Chicago Avenue in River West. Crews began tearing the plant down in August 2024; CBS Chicago put the casino and hotel complex at $1.7 billion, with a 500-room hotel tower, a 3,000-seat theater and six restaurants.
In December 2025, in its 2026 budget, the City Council made video gambling legal in Chicago bars and restaurants. Bally's said that broke its agreement with the city, halted work on parts of the resort, including the 34-story, 500-room hotel, the concert venue and restaurants, and laid off 12% of the 1,500 workers there (WTTW, Sept. 9, 2026). Two weeks later its chairman called reports that construction had stopped inaccurate: work continues every day with about 1,000 tradespeople, Bally's is changing the order in which some parts are delivered, and the casino remains on track for early 2027, opening with about 100 hotel rooms (Yogonet, Sept. 23, 2026).
Who gets what?
The City of Chicago's permits state what each phase costs: $198.0 million for the foundations and structure, $396.2 million for the core and shell, and $585.2 million for the inside, including the $580 million interior buildout permit Gilbane Building Company holds. Otis Elevator's elevator and escalator permits repeat one figure, $21.9 million, and its first escalator permit states $12.2 million; the riverwalk and park permit states $22.6 million.
No one has published Bally's own trade split. By the math on RSMeans' typical split for mixed-use buildings, the building permits' $1.18 billion breaks into about $134 million of electrical work, $152 million of air and heat (mechanical), $41 million of plumbing and $619 million for the frame, walls, glass and finishes.
Which firms are on the permits?
We read every City of Chicago building permit at 705 W Chicago Ave (open data) on Nov. 15, 2026 and kept each contractor named on a permit issued since Nov. 15, 2025 that is still open: 13 firms. Gilbane Building Company is the general contractor; Gurtz Electric, Titan Electric and Jamerson & Bauwens are the electrical contractors on the interior buildout, with O'Sullivan Plumbing and Premier Mechanical; Otis Elevator and Smart Elevator hold the elevator permits; F.H. Paschen, Blackrock Construction and Aldridge Electric are on the retaining walls and the riverwalk.
How do the ways into Bally's Chicago compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the permits | A call to the firm's office, asking for the Bally's Chicago team | Every supplier, distributor and sales rep | A conversation with a firm already working on the casino | Start with the firms with the newest permits |
Who should go after Bally's Chicago?
| Electrical distributors and gear reps | 5 electrical firms hold open permits, three of them on the $580 million interior buildout. |
|---|
| HVAC, plumbing and elevator reps | O'Sullivan Plumbing, Premier Mechanical, Advance Mechanical, Otis Elevator and Smart Elevator hold open permits. |
|---|
| Building, masonry and landscape suppliers | Gilbane's interior buildout, Blackrock's retaining walls and the $22.6 million riverwalk and park (F.H. Paschen, Aldridge Electric). |
|---|
What should you do next on Bally's Chicago?
- Pick the firms whose permits match what you sell, and call them this week.
- Ask for the team on Bally's Chicago.
Questions people ask about Bally's Chicago casino
How much does Bally's Chicago cost?
$1.7 billion for the casino and hotel complex (CBS Chicago).
When does Bally's Chicago open?
Bally's says the casino is on track to open in early 2027, with about 100 hotel rooms at first and the hotel later expanding to 500 (Yogonet, Sept. 23, 2026).
Who is building Bally's Chicago?
Gilbane Building Company is the general contractor and holds the $580 million interior buildout permit. The full list of 13 firms on open permits is above.
Why did Bally's pause the hotel?
After the City Council legalized video gambling terminals in Chicago bars and restaurants (in its 2026 budget, December 2025), Bally's halted work on the hotel, concert venue and restaurants, saying the move breaches its agreement with the city (WTTW, Sept. 9, 2026). Bally's later said it is changing the order of the work, not stopping it, and the hotel opens with about 100 rooms (Yogonet, Sept. 23, 2026).
How we built this list
We read every City of Chicago building permit at 705 W Chicago Ave (open data) on Nov. 15, 2026 and kept the contractors named on a permit issued since Nov. 15, 2025 and still open (owners, architects, engineers and expediters are left out). Dollar figures are the permits' own stated costs, each phase once; the trade split is the math on RSMeans' typical shares. Phones are each company's own office line. First published Nov. 15, 2026. We'll update this page as the city issues new permits at Bally's Chicago.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.