What is being built at the Brent Spence Bridge?
The Brent Spence Bridge carries I-71 and I-75 over the Ohio River between Cincinnati, Ohio and Covington, Kentucky. It opened in 1963 and now carries far more traffic than it was built for. It is called one of the worst traffic bottlenecks in the United States. More than $1 billion in freight passes through the corridor each day.
Ohio and Kentucky are building a new cable-stayed companion bridge just west of the old one. The old bridge stays open and gets work for local traffic, like its emergency shoulders back, new ramps and paths for walking and biking. The job also rebuilds more than 30 overpasses or underpasses in Ohio and a dozen in Kentucky.
How much does the Brent Spence Bridge project cost?
The construction phase is $4.05 billion, per the Kentucky governor's office in May 2026. In March 2026 the total estimate was reported at $4.4 billion, which takes in earlier design, engineering and demolition. That was up about $700 million from the $3.6 billion reported before.
Two federal grants pay $1.63 billion. The states cover the rest from state money or financing. Each state pays for its own highway work, and they share the cost of the new bridge. Leaders say this means no one will pay a toll to cross.
Who is building the Brent Spence companion bridge?
The Walsh Kokosing Joint Venture is the design-build team. It is led by Walsh Construction of Chicago and Kokosing Construction of Westerville, Ohio. AECOM is the lead designer, working with Jacobs. Jacobs is also the Independent Companion Bridge Engineer, and Parsons is the independent design quality firm.
The team expects about 6 million work hours and more than 700 tradespeople, with up to 1,000 at peak.
How far along is the Brent Spence Bridge project?
Crews broke ground on May 8, 2026. The first crane barge reached the river in June. By mid-October, crews had torn down part of Longworth Hall and the 2nd Street ramps in Cincinnati. Over September and October, The Great Lakes Construction Co. set all 27 steel beams, nearly 1.3 million pounds, on the Linn Street Bridge over I-75. That work opens space for new links to the companion bridge.
Ohio is closing the Gest Street ramp to Seventh Street for good on or after Dec. 1, and taking down part of the 19 Broadcast Plaza parking garage, to make room. On the Kentucky side, more ramp and road closures into Covington are coming in the months ahead. The companion bridge is set to open in 2031, with approach work mostly done by 2033.
Which other firms are working on the Brent Spence Bridge?
J&B Steel Erectors, a third-generation woman-owned firm, installs rebar on the corridor. True Inspection Services does construction engineering and inspection in Ohio and Kentucky.
In the 2025 early works, Renascent tore down the ARTIMIS building, wedged between I-75 and I-71, as a subcontractor to Walsh Kokosing, and divers with BioSurvey Group moved native mussels upstream before river work. 10 firms in all are on the list below.
Who ODOT and KYTC hired before
Ohio's and Kentucky's transportation departments have handed their biggest bridge jobs to the same firms on this project. Walsh built Louisville's downtown Ohio River crossing for Kentucky and Cleveland's westbound Innerbelt Bridge for Ohio, with Kokosing, Great Lakes and Jacobs on other big ones.
- Walsh Construction: design-build lead contractor on Ohio River Bridges Downtown Crossing (Abraham Lincoln Bridge and the downtown Louisville interchange), Louisville, KY, 2013-2016. Also on this job.
- Jacobs: designer (lead design for the Walsh design-build team) on Ohio River Bridges Downtown Crossing, Louisville, KY, 2013-2016. Also on this job.
- The Great Lakes Construction Co.: design-build, in the Trumbull-Great Lakes-Ruhlin (TGR) joint venture on Eastbound George V. Voinovich (Innerbelt) Bridge over the Cuyahoga River, Cleveland, OH, started 2013. Also on this job.
- Kokosing Construction Company: design-build contractor on Columbus Crossroads phase 1, the I-670/I-71 interchange rebuild, a $200 million design-build contract, Columbus, OH, 2014 (industry awards). Also on this job.
- Walsh Construction: design-build contractor (designer HNTB) on Westbound I-90 Innerbelt Bridge (now the George V. Voinovich Bridge), a $278.4 million first span, Cleveland, OH, awarded 2010. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 10 firms on this job.
How do the ways into the Brent Spence Bridge project compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Brent Spence Bridge Corridor Project | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Brent Spence Bridge project?
| Steel, rebar and concrete suppliers | Walsh Kokosing on the $4.05 billion construction phase, J&B Steel Erectors on rebar, and Great Lakes Construction on the Linn Street Bridge. |
|---|
| Engineering, survey and testing firms | AECOM and Jacobs on design, Parsons on design quality, and True Inspection Services on inspection. |
|---|
| Demolition, site and environmental firms | Renascent and BioSurvey Group in the 2025 early works, with more demolition and closures in Cincinnati and Covington ahead. |
|---|
What should you do next on the Brent Spence Bridge project?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Brent Spence Bridge Corridor Project between Cincinnati and Covington.
- For small-business work, call the Walsh Kokosing small-business line, 877-BSB-7175.
Questions people ask about the Brent Spence Bridge project
How much does the Brent Spence Bridge project cost?
The construction phase is $4.05 billion, per the Kentucky governor's office in May 2026. In March 2026 the total estimate was reported at $4.4 billion, up about $700 million from $3.6 billion. Two federal grants pay $1.63 billion.
Who is building the new Brent Spence Bridge?
The Walsh Kokosing Joint Venture, led by Walsh Construction and Kokosing Construction, is the design-build team. AECOM is the lead designer, with Jacobs. 10 firms are named on the job, listed above.
When will the Brent Spence companion bridge open?
It is set to open in 2031, with approach work mostly done by 2033.
Will the new Brent Spence Bridge have tolls?
No. Leaders say state and federal money share the cost so that no one traveling through has to pay a toll.
Where is the Brent Spence companion bridge?
Just west of the existing Brent Spence Bridge, over the Ohio River between Cincinnati, Ohio and Covington, Kentucky. The project runs along I-71 and I-75 from the Western Hills Viaduct in Ohio to Dixie Highway in Kentucky.
Will the old Brent Spence Bridge stay open?
Yes. It stays open and gets work for local traffic, like restored emergency shoulders, new ramps and paths for walking and biking.
How many workers will build the Brent Spence Bridge?
About 6 million work hours and more than 700 tradespeople, with up to 1,000 at peak, per the builder.
Why did the Brent Spence Bridge cost go up?
In March 2026 the total estimate was reported at $4.4 billion, up about $700 million from $3.6 billion. The total takes in earlier design, engineering and demolition, beyond the $4.05 billion construction phase.
What is happening on the Linn Street Bridge?
The Great Lakes Construction Co. is rebuilding it over I-75 to open space for links to the companion bridge. Crews finished setting all 27 steel beams, nearly 1.3 million pounds, in October 2026, and the work is set to wrap up in 2028.
What road closures are coming for the Brent Spence project?
Ohio is closing the Gest Street ramp to Seventh Street for good on or after Dec. 1, 2026. More ramp and road closures into Covington are coming in the months ahead.
How can subcontractors get on the Brent Spence Bridge project?
Call the firms already on the job, starting with the Walsh Kokosing Joint Venture, the design-build prime. The joint venture runs a small-business line, 877-BSB-7175.
How we built this list
We read the Kentucky governor's May 8, 2026 groundbreaking release, Walsh's groundbreaking release, the project's fact sheet and joint venture page, the project's monthly newsletters from October 2025 to October 2026, True Inspection Services' project page, an Ohio transportation bulletin on the Linn Street contract, and news reports from Construction Dive, WLWT and LINK nky, all on Nov. 21, 2026. We kept each firm a public record names on this project. The $4.05 billion is the construction phase for the whole team, not one firm's share; the $4.4 billion total and the $700 million rise are as reported. Renascent and BioSurvey Group are on the list for their 2025 early works. Great Lakes Construction holds a separate state contract inside the corridor. Left out: the two state owners, the federal funders, a recruiting firm and a training school that wrote about the job, a utility named only as a site, the builder of the 1963 bridge, and a testing firm seen only on a truck in a project photo. The design-build team says more than a dozen other firms support it, but it does not list them. Phones are each firm's own line from its own site; Walsh and Renascent are headquarters lines and Great Lakes is its Cincinnati office. Kokosing's site did not answer on Nov. 21, 2026. Kokosing, AECOM, Jacobs, Parsons and J&B Steel Erectors show no main line we could verify on their sites, so we give their websites. First published Nov. 21, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 21, 2026- Office of Gov. Andy Beshear: groundbreaking on the Brent Spence Bridge Corridor Project (May 8, 2026)
- The Walsh Group: Walsh Kokosing design-build team breaks ground (May 8, 2026)
- Construction Dive: Brent Spence Bridge groundbreaking and cost rise (March 2026)
- Brent Spence Bridge Corridor: fact sheet (read Nov. 21, 2026)
- Brent Spence Bridge Corridor: Walsh Kokosing Joint Venture page
- Brent Spence Bridge Corridor: October 30, 2026 newsletter
- Ohio Department of Transportation bulletin: Linn Street reconstruction project (Oct. 17, 2026)
- Brent Spence Bridge Corridor: September 30, 2026 newsletter
- Brent Spence Bridge Corridor: October 2025 newsletter
- Brent Spence Bridge Corridor: November 2025 newsletter
- True Inspection Services: Brent Spence Bridge Corridor Project (read Nov. 21, 2026)
- WLWT: Cincinnati ramp to Seventh Street closing for Brent Spence work (Nov. 3, 2026)
- LINK nky: more closures ahead as Brent Spence work reshapes Covington traffic (Nov. 9, 2026)
- The Walsh Group: Ohio River Bridges Downtown Crossing is complete (November 2016)
- The Walsh Group project page: Ohio River Bridges - Downtown Crossing
- Construction Digital: Trumbull-Great Lakes-Ruhlin (TGR) Innerbelt/George V. Voinovich Bridge
- Kokosing project page: I-670/71 Columbus Crossroads
- ENR: HNTB, Walsh win design-build for first leg of new Ohio span (2010-09-15)