What are the Browns building in Brook Park?
The Cleveland Browns are building a new enclosed stadium, New Huntington Bank Field, at 18300 Snow Road in Brook Park, Ohio. The site is the old Ford plant next to Cleveland Hopkins Airport, part of a 178-acre district. The team owner, the Haslam Sports Group, is the developer.
The stadium will hold 67,500 seats and can host events of up to 75,000, under a see-through roof. 70% of the seats will sit below ground level, so the crews are digging a bowl 80 feet deep. HKS is the architect.
How much does the new Browns dome cost?
A November 2026 news report puts the stadium at about $2.6 billion. The earlier estimate was $2.4 billion, and many older reports still use it. About half the budget, $1.3 billion, is labor.
The funding plan reported in May 2026 splits the cost into about $1.76 billion from the Haslam Sports Group, $600 million from the state and $245 million from Brook Park.
Why is the state's $600 million on hold?
On March 9, 2026, a Franklin County magistrate's injunction blocked the state's plan to pay its $600 million share from unclaimed funds. That money is still on hold.
Brook Park had not approved its $245 million share as of May 2026, and in November the Browns still had no development agreement with the city. The team owner is building anyway.
How far along is the Browns dome?
Mass excavation started on March 2, 2026, and the groundbreaking was April 30. By mid-November the crews had moved about a million cubic yards of dirt and had 19 feet left to dig, with the bottom expected in mid-December 2026.
Steel goes up in spring 2027. The plan is substantial completion in the second quarter of 2029 and opening for the 2029 NFL season. On Nov. 9, 2026, Ohio EPA issued the stadium's sewer permit to HSG BP Development, LLC.
Who is building the new Browns stadium?
A joint venture of AECOM Hunt and Turner Construction Company is the construction manager. Turner's Cleveland general manager is on the site. Independence Construction is an active member of the construction management team.
On the dig, Independence Excavating did the enabling and site work, DiGeronimo is the local partner on the site work, and Independence Construction and Michels Construction are doing the mass excavation. The builders' August 2026 outreach deck also names The AKA Team, Ozanne and Next Generation Construction as association partners, with no trade stated.
How many workers will the Browns dome need?
About 160 workers are on site six days a week now. Once the inside trades start, the team expects over 2,000 workers on site every day, with a goal of 75% from Northeast Ohio.
The joint venture's GMP bid package, open from Sept. 8 to Oct. 2, 2026, covered finishes, roofing, glass, audio-visual, landscaping and more. Around the stadium, Brook Park's consulting engineer, Osborn Engineering, presented the city's multi-phase road plan: new ramps, wider local roads and new walkways.
Who the Haslams hired before
Haslam Sports Group has used Turner twice: on the Columbus Crew stadium and on the Browns' 2014 stadium renovation. DiGeronimo is developing their Berea district next to the Browns' training campus.
- DiGeronimo Companies: developer of the district on District 46 at the CrossCountry Mortgage Campus, the Browns' Berea training-campus expansion (about 16 acres), Berea, OH, announced 2024, opening expected early 2027. Also on this job.
- Turner Construction Company: design-build, in a joint venture with Smoot Construction on Lower.com Field, the Columbus Crew stadium (20,000 seats), Columbus, OH, 2019-2021. Also on this job.
- Corna Kokosing Construction: builder on OhioHealth Performance Center, the Columbus Crew training facility, Columbus, OH, opened 2021.
- Turner Construction Company: construction manager on FirstEnergy Stadium (now Huntington Bank Field) two-phase renovation, Cleveland, OH, 2014. Also on this job.
- Independence Excavating: removal work (scoreboards, upper end zone seating, steel) under the Turner-Ozanne team on FirstEnergy Stadium (now Huntington Bank Field) modernization, Cleveland, OH, 2014. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 11 firms on this job.
How do the ways into the Browns dome compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the new Browns stadium in Brook Park | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Browns dome?
| Concrete, steel and site suppliers | Michels, Independence Construction and Independence Excavating on the 80-foot mass excavation, with steel starting in spring 2027. |
|---|
| Finish, roofing, glass and audio-visual trades | The AECOM Hunt-Turner joint venture runs the bid packages; its GMP package, open Sept. 8 to Oct. 2, 2026, covered finishes, roofing, glass, audio-visual and more. |
|---|
| Every trade that staffs up | Over 2,000 workers a day are expected once the inside trades start, with a 75% Northeast Ohio workforce goal. |
|---|
What should you do next on the Browns dome?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on New Huntington Bank Field, the Browns stadium in Brook Park.
- Watch for the next bid packages from the AECOM Hunt-Turner joint venture as steel and the inside work start in 2027.
Questions people ask about the Browns dome
How much does the new Browns dome cost?
About $2.6 billion, per a November 2026 news report, up from the earlier $2.4 billion estimate. The funding plan reported in May 2026 splits it into about $1.76 billion from the Haslam Sports Group, $600 million from the state and $245 million from Brook Park. About half, $1.3 billion, is labor.
Who is building the new Browns stadium in Brook Park?
A joint venture of AECOM Hunt and Turner Construction Company is the construction manager, with Independence Construction on its team. Independence Excavating, DiGeronimo and Michels are on the site work and mass excavation. HKS is the architect. 11 firms are named on the job, listed above.
Why is the state's $600 million on hold?
On March 9, 2026, a Franklin County magistrate's injunction blocked the state's plan to pay its $600 million share from unclaimed funds. The Browns kept digging anyway. Brook Park had not approved its $245 million share as of May 2026, and in November the Browns still had no development agreement with the city.
How far along is the Browns dome?
Mass excavation started March 2, 2026 and the groundbreaking was April 30. In mid-November the team said it had 19 feet left to dig, with the bottom expected in mid-December. Steel starts in spring 2027.
When will the new Browns stadium open?
The plan is substantial completion in the second quarter of 2029 and opening for the 2029 NFL season.
How many workers will build the Browns dome?
About 160 workers are on site six days a week now. Once the inside trades start, the team expects over 2,000 workers on site every day. The goal is 75% of the workforce from Northeast Ohio.
How big is the new Browns stadium?
67,500 seats, which can host events of up to 75,000, under a see-through roof. 70% of the seats sit below ground level, in a bowl dug 80 feet deep, on a 178-acre site by Cleveland Hopkins Airport.
What permit did the Browns dome get last week?
On Nov. 9, 2026, Ohio EPA issued the stadium's sewer permit (permit to install DSWPTI-260939) to HSG BP Development, LLC, the team owner's development company.
How can subcontractors get work on the Browns dome?
Call the firms already on the job, starting with the AECOM Hunt-Turner joint venture, which runs the bid packages. Its GMP bid package, open from Sept. 8 to Oct. 2, 2026, covered finishes, roofing, glass, audio-visual, landscaping and more. More trade work comes as the inside work starts.
Who is doing the road work around the Browns stadium?
Brook Park's consulting engineer, Osborn Engineering, presented the city's multi-phase road plan around the stadium with the city: new ramps, wider local roads and new walkways. City and county leaders approved the plan, estimated at about $82 million, in December 2025.
Where is the new Browns stadium?
At 18300 Snow Road in Brook Park, Cuyahoga County, Ohio, on the old Ford plant site next to Cleveland Hopkins Airport.
How we built this list
We read the Browns' releases on the construction team, the start of mass excavation and the July build update; AECOM's groundbreaking release; the builders' Aug. 20, 2026 outreach deck; Ohio EPA's sewer permit; and news reports, all on Nov. 21, 2026. We kept each firm a public record names on this stadium or its public roads. Eight have a stated role; three are named only as association partners on the deck's construction team slide, and we do not guess their trade. Osborn Engineering is tied to the city's road work around the stadium, not the stadium building contract. The $2.6 billion is the whole stadium's reported cost, not any one firm's contract. Left out: the team owner and its development companies, the mixed-use district's developer, the hospitality partner, the site's past owners, a builder named in early reports but not hired, bidding software, and two firms with no website or phone of their own we could find. Phones are each firm's own line from its own site; AECOM Hunt and Michels are headquarters lines outside Ohio, and HKS's and Next Generation Construction's sites show no main line we could read. First published Nov. 21, 2026. We'll update this page when a new contract, permit or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 21, 2026- News 5 Cleveland: behind the construction fence at the Browns stadium site (November 2026)
- Ohio EPA: sewer permit to install DSWPTI-260939, Huntington Bank Field Brook Park (Nov. 9, 2026)
- Cleveland Browns: AECOM Hunt, Turner joint venture and Independence Construction to begin work (Oct. 2, 2025)
- Cleveland Browns: mass excavation begins in Brook Park (March 2, 2026)
- AECOM: groundbreaking of the new Huntington Bank Field (May 6, 2026)
- Cleveland Browns: progress on the build of the new Huntington Bank Field (July 30, 2026)
- AECOM Hunt and Turner: New Huntington Bank Field outreach event deck (Aug. 20, 2026)
- Front Office Sports: judge blocks plan to use unclaimed funds for new Browns stadium (March 2026)
- AP via WTOP: Haslam breaks ground on Browns' domed stadium (April 30, 2026)
- News 5 Cleveland: Browns announce construction team (Oct. 2, 2025)
- Cleveland 19: transportation committee approves $82M plan around the Browns stadium (Dec. 19, 2025)
- Cleveland 19: NOACA looks at traffic at the new Browns dome (May 15, 2026)
- Cleveland Browns: Berea City Schools, City of Berea, DiGeronimo Companies, Haslam Sports Group and University Hospitals partner on District 46 (2024-10-29)
- Turner: Turner celebrates groundbreaking at the Columbus Crew MLS stadium (2019-10-29)
- Columbus Crew: OhioHealth Performance Center a gamechanger for the Crew (2021)
- PRWeb (Turner): Turner Construction Company selected to manage FirstEnergy Stadium renovation (2014-02-18)
- Independence Excavating: Independence Excavating teams with Turner-Ozanne at First Energy Stadium