What's in the Commanders stadium's second bid package?
The Clark | Mortenson | SmootDC bid portal marks its second package, IGMP #2, as accepting bids now. Its documents went out Oct. 16, 2026, and bids are due Nov. 12, 2026.
The package lists nine scopes with that due date: controls, core and shell electrical, elevators and escalators, exterior glass, core and shell HVAC and plumbing, metal wall panels, scoreboards, temporary site wet utilities and sprinklers.
Foundations sit in the same package on their own line. The portal says their documents have an anticipated release date of Nov. 15, and it posts no due date for them. Only prequalified subcontractors invited through BuildingConnected can bid.
What do DC's records show at the RFK site?
DC issued a permit on Sept. 10, 2026 at 2400 East Capitol St NE for 19 hollow stem soil borings to a maximum depth of 100 feet, plus 24 shallower soundings, to gather geotechnical information. It names the property owner, not a drilling firm.
DC approved a revision to the RFK stadium storm sewer relocation plans on Oct. 15, 2026. The original permit says moving the storm sewer network is the first stage for the stadium district.
EPA's stormwater construction record for RFK STADIUM names Clark/Mortenson/Smoot, a joint venture, as operator, with coverage effective Oct. 14, 2026.
On the wider campus, DC's purchase orders show Capitol Paving of DC on the RFK Connector Road ($465,635, from July 17, 2026) and Jacobs Engineering Group on Phase I infrastructure and roadway design ($950,000, from Aug. 20, 2026). We found no press coverage naming either one or the boring permit.
Who can bid on the new Commanders stadium?
Only prequalified prime subcontractors. The portal's first step is the Trade Contractor Interest Form, then a talk with the builders' team and an invitation to the Subcontractor Qualification Application in BuildingConnected and TradeTapp.
The builders' slides say trade partners are judged on capabilities, a commercially useful function, the schedule, price, labor compliance, experience, BIM and quality control.
The job requires 40% participation by DC Certified Business Enterprises, with a 50% goal, across all sub tiers, professional services and supplier contracts. It also carries a Project Labor Agreement and DC's First Source hiring rules.
How do the ways into the Commanders stadium compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The builders' prequalification | The Trade Contractor Interest Form, a talk with the team, then the Subcontractor Qualification Application in BuildingConnected and TradeTapp | Subcontractors who want to bid a package as a prime | Invitations to bid the builders' packages | Only prequalified firms are invited, and we found no deadline for prequalifying |
| Selling to the invited bidders | A call to the firms bidding your trade's package | Suppliers, manufacturers' reps and lower-tier subs | A firm pricing stadium work with a dated deadline | We found no public bidder list, so ask the builders and your trade's usual DC primes |
| The builders' procurement inbox | [email protected], for questions on the process, the packages and the schedule, and the project phone (202) 854-0323 | Any firm with a question about a package or its date | An answer from the procurement team | It isn't a bid, and the portal lists named contacts per scope that we leave off |
| DC Certified Business Enterprise status | Certification with DC's Department of Small and Local Business Development | DC-based small and local firms | Standing toward the builders' 40% CBE requirement | Certification takes time and isn't a bid |
| The designers | HKS on the stadium, and Jacobs on the campus's Phase I infrastructure and roadway design | Product reps who get specified | A chance to get a product in the drawings | Neither firm's specifying role is stated, and the second package is already out |
Who should go after the Commanders stadium, and who shouldn't?
| Piling, drilling and foundation contractors and suppliers | Foundation documents are expected Nov. 15, 2026, and the builders' timeline shows deep foundations. |
|---|
| Envelope, MEP, elevator and scoreboard firms already prequalified | Their second-package bids are due Nov. 12, 2026. |
|---|
| Concrete, precast, steel, waterproofing and site utility firms | The third package is anticipated in February and March 2027, so prequalify now. |
|---|
| Firms that aren't prequalified and want an open public bid this week | This isn't the job for you yet: only invited, prequalified firms can bid, and nothing here is a public bid. |
|---|
What should you do next on the Commanders stadium?
- Email [email protected] before Nov. 15 to ask whether the foundation documents still go out that day and how a firm is considered.
- Fill out the builders' Trade Contractor Interest Form from cmsjv.com/bid-portal.
- If you're a DC firm, check your Certified Business Enterprise status with DSLBD.
- Open the full list and mark the third package's February 2027 document release.
Questions people ask about the new Commanders stadium
Who is building the new Commanders stadium?
A joint venture of Clark Construction Group, Mortenson and Smoot Construction Company of Washington, DC, called Clark | Mortenson | SmootDC. The Washington Commanders announced it on Aug. 11, 2026. HKS is the architect.
Who is the general contractor on the Commanders stadium?
The Clark | Mortenson | SmootDC joint venture leads construction. It buys the work in bid packages it calls IGMP #1 to #4, and EPA's stormwater record for the site names the same joint venture as operator from Oct. 14, 2026.
How much does the new Commanders stadium cost?
Front Office Sports reported the deal as a $3.8 billion venue when the DC Council gave final approval on Sept. 17, 2025, with about $1.1 billion in public money. Bisnow reported the Commanders are putting $2.7 billion into the stadium. Other outlets have used $3.6 billion and $3.7 billion, and the builders' pages give no figure.
Where is the new Commanders stadium?
At the former RFK Stadium site, 2400 East Capitol St NE in Washington, DC, on the Anacostia River. The stadium anchors a 180-acre campus, and its district covers 30 acres.
When will the Commanders stadium be built?
Enabling work began in June 2026. The builders say stadium construction is anticipated to begin in spring 2027, with completion targeted for spring 2030.
When are the Commanders stadium bids due?
The builders' portal says bids for its second package are due Nov. 12, 2026, for scoreboards, exterior glass, metal panels, elevators and escalators, core and shell electrical, HVAC and plumbing, sprinklers, controls and temporary wet utilities. Foundation documents are expected Nov. 15, 2026, with no due date posted. Concrete, precast, steel, waterproofing and site utilities follow, with documents anticipated in February 2027 and bids in March 2027.
How do subcontractors get on the Commanders stadium?
Only prequalified subcontractors can bid. The portal's steps are the Trade Contractor Interest Form, a talk with the builders' team, then the Subcontractor Qualification Application in BuildingConnected and TradeTapp. Questions go to [email protected].
What's in the stadium's foundations package?
The portal lists Foundations in the second package with documents expected Nov. 15, 2026. It doesn't describe the scope. The builders' timeline shows a deep foundations phase, and a DC permit issued Sept. 10, 2026 at the site allows 19 soil borings to a maximum depth of 100 feet.
Do you have to be a DC business to work on the stadium?
No, but the builders require 40% participation by DC Certified Business Enterprises, with a 50% goal, across all sub tiers, professional services and supplier contracts. A CBE certification makes a firm more useful to every bidder.
What labor rules apply on the Commanders stadium?
A Project Labor Agreement with prevailing wage and benefits, a First Source target of 51% of new hires from DC, a 10% DC apprenticeship requirement with a 35% goal, and an apprenticeship program for any firm with $500,000 or more in contracts in 12 months.
What are the risks for a subcontractor?
The dates are the builders' estimates, the foundations date says anticipated, and only invited prequalified firms see the documents. The labor and CBE rules carry reporting and penalties, so price them in.
What comes after the foundations package?
The third package (concrete, stadium precast, steel, waterproofing and site wet and dry utilities) is anticipated with documents in February 2027 and bids in March 2027, and a fourth package for all other trades in July and August 2027.
How we built this list
We read the builders' bid portal in full, their news, team and contact pages, their Sept. 9, 2026 kick-off slides and CBE workshop sheet, DC's permit records and purchase orders for the RFK site, EPA's stormwater record for the site, and press from Front Office Sports, Bisnow, WJLA and ConstructConnect. A row is on the list only if a record ties it to the stadium or its campus. The portal's dates are the builders' schedule, so a month-only date is marked planned, and we left off every person's name, email and direct line. First published Nov. 9, 2026. We'll update this page when the foundation documents go out, the second package is awarded or the third package is dated.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 9, 2026- Clark | Mortenson | SmootDC, bid portal
- Clark | Mortenson | SmootDC, news and events (Aug. 11, 2026 release)
- Clark | Mortenson | SmootDC, team
- Clark | Mortenson | SmootDC, contact
- First & Goal kick-off slides and CBE workshop sheet, Sept. 9, 2026
- Front Office Sports, Sept. 17, 2025
- Front Office Sports, Jan. 15, 2026
- Bisnow, Aug. 11, 2026
- WJLA, Aug. 11, 2026
- EPA ECHO, RFK STADIUM (DCR1000ES)
- DC permits (SB2600182, BCIV2500224, BCIV2600134), DC open data
- DC purchase orders (PO742432, PO743773), DC open data