What is Compass building on the old Sears site?
Compass Datacenters is building five data centers at 5400-5600 Trillium Blvd in Hoffman Estates, the land that used to be 3333 Beverly Road, home of the Sears headquarters. Each building is one story and about 250,000 square feet, with yards on both sides for backup generators, cooling and power gear (Village of Hoffman Estates). That is about 1.25 million square feet of data center in all.
ComEd is building a new substation on the site with five 100 MVA transformers, and two new underground high-voltage lines will feed it from a substation south of I-90 (Village of Hoffman Estates). Compass has not named a tenant.
Compass estimates the campus will bring about $10 billion in local investment once it is finished (Commercial Property Executive). That is Compass's own estimate of what the whole campus will bring, not a construction contract or a permit value, so we do not split it by trade.
How far along is it?
Fast. Chicago Construction News reported on Oct. 27, 2026 that Power Construction had topped out the fifth and final building, less than 12 months after construction started on the first foundation, according to Compass. More than 800 workers came to Power's lunch and raffle. "Y'all built the best building we've had in our portfolio," Compass CEO Chris Crosby told them.
On Nov. 9, 2026, the village said Buildings 1 and 2 are on schedule for final occupancy by early 2027. Permits for Buildings 3, 4 and 5 have been issued and the work inside them is under way (Village of Hoffman Estates).
Why the Sears headquarters matters
The Sears headquarters was about 2.4 million square feet. Its demolition contractor called it one of the 30 largest structures in the world by floor space (Barrington Hills Observer, from the Daily Herald). At its peak about 9,000 people worked there. Sears sent them home when COVID hit in March 2020, and they never came back.
American Demolition of Carol Stream started emptying the buildings in April 2024 (Compass Datacenters), and the crushed concrete was used again as fill on the site. Not every neighbor is happy: at a July 2026 village hearing on a different data center, one resident said of the Sears demolition, "Those explosions shook my house even though I am over a mile away" (Village of Hoffman Estates).
Which firms are on the job?
Power Construction is the builder of all five buildings. Kimley-Horn is the civil engineer and filed the site plan with the village, and DLB Associates wrote the campus's community impact statement. On the power side, ComEd owns the new substation, Sargent & Lundy is its engineer, Mostardi Platt studied its sound and V3 Companies drew its site plans. HBK Engineering designed the two underground lines, Meade Electric dug ComEd's test holes on the village streets, and BLA, Inc. inspects that work for the village, under a contract of up to $246,805.
11 firms in all are on the list below, each with its main office line where the firm publishes one.
How do the ways into Compass's Hoffman Estates data center campus compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Compass's Hoffman Estates data center campus | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Compass's Hoffman Estates data center campus?
| Electrical and power suppliers | Power Construction and ComEd, on five data centers with a new substation of five 100 MVA transformers. |
|---|
| Mechanical, cooling and generator reps | Power Construction, with Buildings 3, 4 and 5 now in inside fit-out and each building flanked by generator and cooling yards. |
|---|
| Civil, survey and underground utility firms | Kimley-Horn, HBK Engineering and BLA, Inc., on the site work and the two new underground ComEd lines. |
|---|
What should you do next on Compass's Hoffman Estates data center campus?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Compass's Hoffman Estates data center campus.
Questions people ask about Compass's Hoffman Estates data center campus
How much is the Compass data center in Hoffman Estates worth?
Compass estimates about $10 billion in local investment once the campus is finished (Commercial Property Executive). That is its own estimate, not a construction cost; no permit values were readable.
Who is building the Compass data centers in Hoffman Estates?
Power Construction of Chicago is the builder. Kimley-Horn is the civil engineer, and ComEd is building the substation. 11 firms are named in all, listed above.
When will the Compass Hoffman Estates campus open?
The village said on Nov. 9, 2026 that Buildings 1 and 2 are on schedule for final occupancy by early 2027, and Buildings 3, 4 and 5 have their permits with inside work under way.
What happened to the Sears headquarters in Hoffman Estates?
It was torn down to make room for the Compass campus. The 2.4 million square foot complex once held about 9,000 workers and sat empty after March 2020 (Barrington Hills Observer, from the Daily Herald).
Who is the tenant at the Compass Hoffman Estates data center?
Compass has not named a tenant.
How we built this list
We read the Village of Hoffman Estates board and commission packets on the Compass campus and the ComEd work that serves it (Feb. 2025 to Nov. 2026), Compass's own blog and the news, and kept every firm an opened source ties to this job (read Nov. 17, 2026). The village's online permit search sits behind a CAPTCHA, which we did not get past, so no permit values or permit holders were read, and Daily Herald pages sit behind one too. No public source names an electrical, mechanical, precast, steel or fire protection subcontractor inside the fence, so beyond the builder, the demolition firm, ComEd and Meade Electric (ComEd's test holes on village streets), the list is design, engineering and inspection firms from village filings. American Demolition's work on the Sears buildings is finished. Compass Surveying, the land surveyor on the plat, was bought by Kimley-Horn in August 2026, so it counts under Kimley-Horn. Sargent & Lundy's role is read from the substation sound study it ordered. The $10 billion is Compass's local investment estimate, not a construction cost, so we do not split it by trade. Phones are each firm's own office line; we found none for ComEd or DLB Associates. First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 18, 2026- Chicago Construction News: Power Construction tops out the fifth data center building in Hoffman Estates (Oct. 27, 2026)
- Chicago Construction News: Compass Datacenters marks milestone with Building 1 topping-off (Feb. 2026)
- Commercial Property Executive: $10B data center campus kicks off near Chicago (June 17, 2024)
- Village of Hoffman Estates: Planning, Building & Zoning Committee packet (Nov. 9, 2026)
- Village of Hoffman Estates: Planning & Zoning Commission packet, Compass site plan PLN24-0011 (Feb. 5, 2025)
- Village of Hoffman Estates: Village Board packet (Feb. 17, 2025)
- Village of Hoffman Estates: Plan Commission packet, ComEd substation site plan (June 4, 2025)
- Village of Hoffman Estates: Village Board packet, ComEd license, south route (Dec. 1, 2025)
- Village of Hoffman Estates: Public Works & Utilities Committee packet, BLA, Inc. agreement (Dec. 15, 2025)
- Village of Hoffman Estates: Plan Commission packet (July 15, 2026)
- Barrington Hills Observer (from the Daily Herald): Demolition begins on mammoth Sears complex (Aug. 14, 2024)
- Compass Datacenters: Sears demolition, extending green construction concepts to a brownfield site (June 10, 2024)
- Kimley-Horn: Aurora, IL office (formerly Compass Surveying)