Who's building CoreWeave's AI data center in Denton, Texas

Denton's CoreWeave AI data center was a bitcoin mine, and Core Scientific projects a $6.1 billion investment to convert it.

By Porter Stanley. Updated .

Core Scientific is turning its old bitcoin mine at 8171 Jim Christal Road in Denton, Texas, into AI data centers for CoreWeave. Two Texas state filings list $745 million in construction, the sum of a $635 million conversion and a $110 million data hall. T5 Data Centers is the contractor on the city's building permits, which total $217.2 million, the sum. Core Scientific's Nov. 5, 2026 SEC filing lists Denton at about 260 MW leased and about 260 MW billing. 10 firms are named on the job; the list below has all 10.

$745MTexas state filings (the sum of two)
$217.2MCity of Denton permits (the sum of 19)
$85.6MBackup power storage permit (Walker Engineering)
10Firms named on the job

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on the CoreWeave Denton data center?

We list the 10 firms named on Core Scientific's Denton data center campus for CoreWeave, one row each, grouped by kind of firm, with where each name comes from.

1Permit on the recordJun 30, 2025

T5 Data Centers

Builder on the conversion of the old bitcoin mining buildings A to D and the Tech building, the new Building H and the office, plus trailers, fence, substation and laydown yard on the Core Scientific / CoreWeave AI data center campus on Jim Christal Road in Denton, TX

Core Scientific / CoreWeave AI data center campus, 8151-8171 Jim Christal Rd, Denton (Denton County), TX

Commercial permit 2502-0112, value $32,906,842.70, issued June 30, 2025; also the 2026 temporary occupancy permits for Buildings F and G and the office

Work: Builder on the conversion of the old bitcoin mining buildings A to D and the Tech building, the new Building H and the office, plus trailers, fence, substation and laydown yard

Who to call: T5 Data Centers
T5 Data Centers main line not published on its site

The opportunity: ALTERATION: BLDG ABCD&TECH NEW CONSTRUCTION: BLDG H, OFFICE (contractor T5 DATA CENTERS, owner CORE SCIENTIFIC). Its 'T5 Data Centers Construction' sign is on site in a Denton Record-Chronicle photo (April 2026). Newest T5 record: permit 2608-0566, office TCO, issued Aug. 17, 2026.

2Permit on the recordApr 29, 2025

Walker Engineering Inc

Electrical contractor installing the energy storage systems tied to the backup power (UPS), phase 2 on the Core Scientific / CoreWeave AI data center campus on Jim Christal Road in Denton, TX

Core Scientific / CoreWeave AI data center campus, 8151-8171 Jim Christal Rd, Denton (Denton County), TX

Electrical permit 2504-0259, value $85,600,000, issued April 29, 2025

Work: Electrical contractor installing the energy storage systems tied to the backup power (UPS), phase 2

Who to call: Walker Engineering Inc
Walker Engineering Inc office line
(Irving, TX)
(817) 540-7777

The opportunity: INSTALL ESSS ASSOCIATED WITH UPSS FOR BACKUP POWER -PHASE 2 (WALKER ENGINEERING INC (ELEC)).

3Named on a state filingNov 15, 2024

Ci Design, Inc.

Design firm on the state filing to convert the bitcoin mining buildings into data centers and build a new office on the Core Scientific / CoreWeave AI data center campus on Jim Christal Road in Denton, TX

Core Scientific / CoreWeave AI data center campus, 8151-8171 Jim Christal Rd, Denton (Denton County), TX

Texas state filing, estimated cost $635,000,000, 478,685 sq ft, registered Nov. 15, 2024

Work: Design firm on the state filing to convert the bitcoin mining buildings into data centers and build a new office

Who to call: Ci Design, Inc.
Ci Design, Inc. office line
(Baltimore, MD)
(410) 384-4244

The opportunity: Scope of Work: Convert bitcoin mining buildings into data centers - construct new office building. The TDLR filing shows (410) 348-4244; the firm's own site shows 410.384.4244. Dallas office line (800) 978-5606.

What is CoreWeave building in Denton, Texas?

Core Scientific owns a campus at 8171 Jim Christal Road in Denton, Texas, next to the Denton Energy Center. It used the site to mine bitcoin. Now it is turning the buildings into AI data centers, and CoreWeave leases the computing space.

The Texas filing from Nov. 15, 2024 lists the job as "Convert bitcoin mining buildings into data centers," plus a new office building. It covers 478,685 sq ft. The land belongs to the City of Denton, which leases it to Core Scientific.

How far along is the CoreWeave Denton data center?

Core Scientific's SEC filing of Nov. 5, 2026 lists Denton at about 260 MW leased and about 260 MW billing, on a slide about its CoreWeave sites headed "Nearing full completion of the CoreWeave buildout." The city gave temporary occupancy to Buildings F and G on May 14, 2026, and to the office on Aug. 17, 2026.

Work is not over. A new $110 million data hall in Building A is filed to run from Sept. 2026 to May 2027. The newest city permit on the campus, from Sept. 1, 2026, is for an irrigation meter serving the office.

What is being bought on the CoreWeave Denton campus?

Two Texas state filings list $745 million, the sum: $635 million for the conversion and $110 million for the Building A data hall. These are owner estimates filed for review, not contract values. City of Denton permits on the campus total $217.2 million, the sum of 19 permits since Nov. 2024.

The two biggest city permits are for battery storage: $91 million for energy storage systems (Dec. 23, 2024) and $85.6 million for storage tied to the backup power, with Walker Engineering (April 29, 2025). T5 Data Centers' main conversion permit is $32.9 million.

Why did the CoreWeave Denton data center run on diesel?

The Denton Record-Chronicle reported on Nov. 2, 2026 that a defect in 93 transformers left the campus on eight diesel generators from April 9 to June 23, 2026.

Per the paper, the generators put out 384.13 tons of nitrogen oxides, against a yearly limit of 24.9 tons, and state enforcement by the Texas Commission on Environmental Quality is pending.

Who is building the CoreWeave Denton data center?

T5 Data Centers is the contractor on the $32.9 million main permit to convert Buildings A to D and the Tech building and to build Building H and the office. It also holds permits for trailers, the fence, the substation and the laydown yard. Its sign is on site in an April 2026 Denton Record-Chronicle photo.

Ci Design is the architect on the $635 million state filing, and Gensler is the design firm on the $110 million Building A data hall. Denton Municipal Electric supplies the power.

Which trade firms are on the CoreWeave Denton data center?

Walker Engineering is the electrical contractor on the $85.6 million backup power storage permit. DynaTen and Logical Solutions pulled construction trailer permits on the campus.

ADB Companies, MasTec Communications Group and TCS Communications hold right-of-way permits to bring fiber and telecom lines to the campus. 10 firms in all are on the list below.

How do the ways into the CoreWeave Denton data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the Core Scientific / CoreWeave Denton data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the CoreWeave Denton data center?

Electrical distributors and gear repsWalker Engineering on the $85.6 million backup power storage permit, and T5 Data Centers on the substation and buildings.
Mechanical, HVAC, controls and plumbing repsDynaTen and Logical Solutions, both on construction trailer permits at the campus.
Fiber, telecom and design suppliersADB Companies, MasTec and TCS Communications on fiber permits; Ci Design and Gensler on the state filings.

What should you do next on the CoreWeave Denton data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the Core Scientific data center on Jim Christal Road in Denton.

Questions people ask about the CoreWeave Denton data center

How much is the CoreWeave data center in Denton?

Two Texas state filings list $745 million in construction, the sum: $635 million to convert the bitcoin mining buildings, registered Nov. 15, 2024, and $110 million for the Building A data hall, registered Aug. 19, 2026. These are owner estimates, not contracts. City of Denton permits on the campus total $217.2 million, the sum of 19 permits.

Who is building the CoreWeave data center in Denton?

T5 Data Centers is the contractor on the main $32.9 million conversion permit and the building permits, and its sign is on site. Core Scientific owns the campus and CoreWeave leases it. 10 firms are named on the campus, listed above.

Who owns the Denton data center, Core Scientific or CoreWeave?

Core Scientific owns and runs the campus, and CoreWeave leases the computing space. The land belongs to the City of Denton, which leases it to Core Scientific.

Where is the CoreWeave data center in Denton?

It is at 8171 Jim Christal Road in Denton, Texas, next to the Denton Energy Center. City permits also use 8151, 8161 and 8165 Jim Christal Road.

Was the Denton data center a bitcoin mine?

Yes. The Texas filing from Nov. 2024 lists its scope as "Convert bitcoin mining buildings into data centers," plus a new office building. Core Scientific used the site for bitcoin mining before CoreWeave.

How big is the Denton data center?

Core Scientific and CoreWeave said in Feb. 2025 that the site's full computing load would be about 260 MW. Core Scientific's Nov. 5, 2026 SEC filing lists about 260 MW leased and billing. Power figures differ: the Denton Record-Chronicle reported a power deal of up to 391 MW (Sept. 23, 2026) and a contract for up to 394 MW (Nov. 2, 2026).

When will the Denton data center be finished?

Core Scientific's Nov. 5, 2026 SEC filing lists Denton at about 260 MW leased and about 260 MW billing, on a slide headed "Nearing full completion of the CoreWeave buildout." A new $110 million Building A data hall is filed to run from Sept. 2026 to May 2027.

Why did the Denton data center run on diesel generators?

The Denton Record-Chronicle reported on Nov. 2, 2026 that a defect in 93 transformers left the campus on eight diesel generators from April 9 to June 23, 2026. They put out 384.13 tons of nitrogen oxides, against a yearly limit of 24.9 tons, and state enforcement is pending, per the paper.

Who supplies power to the Denton data center?

Denton Municipal Electric, the city's utility. Its power purchase agreement with Core Scientific allows up to 391 MW, per the Denton Record-Chronicle.

What is the newest permit on the Denton campus?

On Sept. 1, 2026, the City of Denton issued a permit for an irrigation meter and tap serving the campus office at 8165 Jim Christal Road. The newest permit naming a firm on our list is T5 Data Centers' temporary occupancy for the office, Aug. 17, 2026. The November permit report is not out yet.

What happens next on the Denton data center?

The $110 million Building A data hall, designed by Gensler, is filed to finish in May 2027. Core Scientific has asked Denton Municipal Electric about leasing more city land south of the campus, per the Denton Record-Chronicle. We'll update this page when a new permit or firm appears.

How we built this list

We read both Texas state filings for 8171 Jim Christal Road and every City of Denton permit at 8151 to 8171 Jim Christal Road from Nov. 2024 to Oct. 2026 on Nov. 19, 2026; the November 2026 permit report is not out yet. We also read Core Scientific's Nov. 5, 2026 SEC filing, the joint Core Scientific and CoreWeave release of Feb. 26, 2025, the Denton Record-Chronicle and Community Impact, and kept each firm a filing, permit or news report names on this campus. The $745 million is the sum of two owner estimates, and the $217.2 million is the sum of 19 valued city permits; a permit's value is for the whole job, not one firm's share. Power figures differ by source, so we give each with its source. Left out: three landscape irrigation firms, a firm seen only in an unverified payment report, firms from the bitcoin mining years, individual reviewers on the filings, a plumbing firm whose city permits at 8161 Jim Christal Road (an address the city's Denton Energy Center power plant shares) point to work at the plant, the carriers the fiber firms worked for, and a different Core Scientific site in Hunt County. Phones are each firm's own line; MasTec's is its corporate main line, ADB's and TCS's are head office lines, Denton Municipal Electric's is the city's utility line, and T5 and DynaTen have no main line we could verify on their own sites. First published Nov. 19, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on the CoreWeave Denton data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.