What is being built in Lancaster?
The Lancaster AI Hub is going up at 216 Greenfield Road, near Route 30, inside the old R.R. Donnelley and LSC printing plant. Chirisa Technology Parks and Machine Investment Group are the developers, and CoreWeave, the AI cloud company, is the only tenant. The site starts at 100 megawatts and can grow to 300 megawatts (ENR).
There are two buildings at Greenfield Road. Building 1 reuses the old plant's footprint of about 439,000 square feet. Building 2 is two stories and 735,128 square feet (WITF). Cranes set steel on building 1 in February 2026 and lifted rooftop chillers in April (LNP | LancasterOnline photos). It is targeted to open in summer 2027 (ENR).
Building 2 is in a fight. Residents appealed it, and on Sept. 21, 2026 a judge granted the developers' emergency motion to stay the zoning hearing (LNP | LancasterOnline). The state's comment period on 84 more backup generators for it closed Oct. 26, 2026 (PA Environment Digest).
What does the $6 billion pay for?
CoreWeave said it intends to commit up to $6 billion to equip the center (CoreWeave). That is the tenant's money for the computers and gear inside. It is not the cost of the building, even though some headlines call it a $6 billion data center.
The building money is the developer's. The developers say they have already spent $1.3 billion on building 1 (LNP | LancasterOnline). Building 2 is planned at up to $2.5 billion to build and equip (WITF). The developer calls the whole Lancaster AI Hub, with a second site on Harrisburg Pike, more than $10 billion (PR Newswire).
No one has published the job's trade split. By the math on Turner & Townsend's data center cost index, about $624 million of the $1.3 billion spent on building 1 is electrical work and about $429 million is pipes, heat and air.
Which firms are on the job?
Turner Construction and Wohlsen Construction build it as a joint venture (ACS Group, Turner's parent). The developers' release says Wohlsen, based in Lancaster, is leading the construction (PR Newswire). The developer's open house boards also show the logos of Gensler, JB&B, Thornton Tomasetti and ELA Group on the project team. Thornton Tomasetti did the noise study (LNP), and ELA Group is the consulting firm on the PPL switchyard plan (Lancaster County Planning).
The same boards list local trade partners getting subcontract work, among them I.B. Abel, Pagoda Electrical and H.B. Frazer on the electrical side, Stewart-Amos Steel, S.A. Comunale, G.C. Zarnas and Linecom, plus LVConcrete, e.h.c. Associates, Cardinal Point Security, LANConnect, United Rentals and Cintas. Under local manufacturers getting purchase orders they list YORK, Armstrong World Industries and Delaware Valley Concrete. The boards show logos only, so each firm's exact scope is not stated. PPL is building the new substation and switchyard (WITF).
The boards said $149 million had gone to subcontractors and vendors and that Phase 1 was only 15% awarded (November 2025). 29 firms in all are on the list below.
How do the ways into CoreWeave's Lancaster data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on CoreWeave's Lancaster data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after CoreWeave's Lancaster data center?
| Electrical distributors and gear reps | I.B. Abel, Pagoda Electrical, H.B. Frazer and Linecom on a site built for 100 to 300 megawatts. |
|---|
| Mechanical, chiller and pipe reps | S.A. Comunale, G.C. Zarnas and the rooftop chillers on building 1. |
|---|
| Steel, site and building suppliers | Stewart-Amos Steel, LVConcrete, Delaware Valley Concrete and the Turner and Wohlsen joint venture, with most of Phase 1 still to buy as of November 2025. |
|---|
What should you do next on CoreWeave's Lancaster data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on CoreWeave's Lancaster data center.
Questions people ask about CoreWeave's Lancaster data center
How much is CoreWeave's Lancaster data center?
CoreWeave said it intends to commit up to $6 billion to equip it, as the tenant. The developers say they have spent $1.3 billion on building 1, and building 2 is planned at up to $2.5 billion to build and equip.
Is the $6 billion the construction cost?
No. CoreWeave's own release says up to $6 billion to equip the center. The building figures come from the developer.
Who is building the CoreWeave data center in Lancaster?
A joint venture of Turner Construction and Wohlsen Construction. 29 firms are named in all, listed above.
Where is the Lancaster AI data center?
216 Greenfield Road, near Route 30, in Lancaster city, Pennsylvania, in the former LSC Communications East printing plant.
When will the Lancaster data center open?
Building 1 is targeted for summer 2027 (ENR). Building 2 waits on a residents' appeal; a judge stayed its zoning hearing on Sept. 21, 2026.
How we built this list
We read CoreWeave's release, the builders' releases, ENR, DCD, WITF, LNP | LancasterOnline, PA Environment Digest and the developer's November 2025 open house boards (read Nov. 17, 2026 from the Internet Archive copy; the project's own site sits behind a captcha), and kept each firm a source ties to this job. The design firms and the trade partners appear on the boards as logos only, so most roles on the job are inferred from what each firm does; LNP names Thornton Tomasetti's noise study, and a Lancaster County Planning review names ELA Group on the switchyard plan. We found no Lancaster city building permit portal online and opened no state permit naming a contractor. One firm on the boards is left out, Bala Consulting Engineers, because its own site could not be read to confirm its office line; the manufacturers the boards list as suppliers are on the list as suppliers. The trade split is the math on Turner & Townsend's published data center shares, applied to the $1.3 billion spent on building 1. Phones are each firm's own office line. First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 18, 2026- CoreWeave: multi-billion dollar commitment to AI infrastructure in Pennsylvania (July 15, 2025)
- DCD: CoreWeave plans $6bn data center in Lancaster (July 15, 2025)
- ENR: Turner-Wohlsen JV will build Pennsylvania data center for CoreWeave (July 2025)
- ACS Group: Turner to build a data center in Pennsylvania (July 21, 2025)
- PR Newswire: Lancaster AI Hub local economic impact data (Sept. 18, 2025)
- WITF: data center's second phase expected to cost up to $2.5 billion (Oct. 19, 2025)
- Lancaster AI Hub community open house boards (Nov. 2025, Internet Archive copy)
- LNP | LancasterOnline: judge cancels Greenfield Road data center zoning hearing (Sept. 22, 2026)
- PA Environment Digest: DEP invites comments on air quality plan approval (Sept. 25, 2026)