CyrusOne is building DFW8, the second data center on its Fort Worth campus, at 9501 Asphalt Dr in north Fort Worth, Tarrant County, Texas. The city's building permit for the shell is $275 million, and a $257.1 million fit-out is filed with the state, about $532 million in all, the sum. The city issued the permit again on Nov. 16, 2026. Clune Construction is the general contractor of record. 18 firms are named on the job; the list below has all 18.

$532MDFW8 shell permit plus fit-out filing (the sum)
$275MCity shell permit, issued again Nov. 16, 2026
259,515Square feet on the permit
18Firms named on the job

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 18 firms on the CyrusOne Fort Worth data center?

We list the 18 firms named on CyrusOne's DFW8 data center campus in Fort Worth, one row each, grouped by kind of firm, with where each name comes from.

1Permit on the recordNov 16, 2026

Clune Construction Company, L.P.

General contractor of record on the DFW8 core and shell permit and on all 8 DFW8 generator-yard pad and screen-wall permits; also on DFW7's shell work and its $200 million tenant finish-out on CyrusOne's DFW8 data center in Fort Worth, Tarrant County, TX

CyrusOne's DFW8 data center (Building 2 of its Fort Worth campus), 9501 Asphalt Dr, Fort Worth (Tarrant County), TX

Shell permit, $275,000,000, first issued Sept. 17, 2025 and issued again Nov. 16, 2026; 8 generator-yard permits issued March 3, 2026 that add up to $4.5 million, the sum (four pads at $625,000 and four screen walls at $500,000); DFW7 finish-out, $200,000,000

Work: General contractor of record on the DFW8 core and shell permit and on all 8 DFW8 generator-yard pad and screen-wall permits; also on DFW7's shell work and its $200 million tenant finish-out

Who to call: Clune Construction Company, L.P.
Clune Construction Dallas office line
(Dallas, TX)
(972) 972-8403

The opportunity: City permit (CYRUS ONE DFW8 - BLDG #2): 'Plans Exam Contact information Michele Orellana Clune Construction 3208 Plainview Lane Argyle, TX', licensed professional Bldg - Contractor RB021953. Generator pad permits to and the DFW8 generator tank and battery fire permits ( to 00065, to 00151) name 'BRIAN O'SHEA CLUNE CONSTRUCTION COMPANY, L.P.' Clune was at the April 2025 groundbreaking, per news reports.

2Permit on the recordFeb 12, 2026

Walker Engineering, Inc.

Electrical contractor on the DFW8 electrical umbrella permit at 9501 Asphalt Dr, a state electrical contractor on CyrusOne's DFW8 data center in Fort Worth, Tarrant County, TX

CyrusOne's DFW8 data center (Building 2 of its Fort Worth campus), 9501 Asphalt Dr, Fort Worth (Tarrant County), TX

Electrical umbrella permit, issued Feb. 12, 2026; trade permits state no value

Work: Electrical contractor on the DFW8 electrical umbrella permit at 9501 Asphalt Dr, a state electrical contractor

Who to call: Walker Engineering, Inc.
Walker Engineering Dallas/Fort Worth office line
(Irving, TX)
(817) 540-7777

The opportunity: City permit (Electrical Umbrella Permit, 9501 Asphalt Dr): 'WALKER ENGINEERING INC 17307 1505 WEST WALNUT HILL LANE IRVING, TX, 75038... EK - State Electrical Contractor K017307 Owner: C1 FORT WORTH LLC.'

3Permit on the recordApr 10, 2026

TDIndustries, Inc.

Mechanical and plumbing contractor at DFW8 (mechanical, plumbing and backflow permits) and at DFW7, where it also put up the materials tent on CyrusOne's DFW8 data center in Fort Worth, Tarrant County, TX

CyrusOne's DFW8 data center (Building 2 of its Fort Worth campus), 9501 Asphalt Dr, Fort Worth (Tarrant County), TX

Mechanical permit, issued April 10, 2026; plumbing permit, issued March 31, 2026; backflow; DFW7 permits and tent

Work: Mechanical and plumbing contractor at DFW8 (mechanical, plumbing and backflow permits) and at DFW7, where it also put up the materials tent

Who to call: TDIndustries, Inc.
TDIndustries main line
(Fort Worth office on the permit)
(800) 864-7717

The opportunity: City permit (Mechanical Standalone Permit, 9501 Asphalt Dr): 'TD INDUSTRIES, INC. TACLA31729C 2601 NORTHERN CROSS BLVD SUITE 201 FORT WORTH, TX, 76137.': 'TDINDUSTRIES, INC. 40179... PM - Master Plumber.': 'CyrusOne DFW7 Tent for storage of materials.'

What is CyrusOne building in Fort Worth?

CyrusOne is building a data center campus on Asphalt Drive in north Fort Worth, in Tarrant County. DFW8 is its second building, at 9501 Asphalt Dr. The first, DFW7, is next door at 9401. The campus substation is across the road at 9400.

The city's permit describes DFW8 as a one-story data center with a two-story office, made of precast panels on a steel frame, with equipment yards to the north and south. The permit lists 259,515 sq ft: 242,170 sq ft of data center floor and a 17,345 sq ft office.

CyrusOne says the campus is set for 200 MW. It sits beside Chisholm Grid, a 100 MW battery site run by Eolian. Reusing that site's grid gear let CyrusOne break ground in April 2025. CyrusOne said on Jan. 13, 2026 that this lets it deliver capacity to customers starting in 2026.

How much is the CyrusOne Fort Worth data center?

CyrusOne has given no total cost. The city's permit for the DFW8 shell carries a $275,000,000 job value. The same permit lists $100 million as the value without the mechanical, electrical and plumbing work.

On Sept. 24, 2026, CyrusOne filed a $257,109,000 fit-out of DFW8's data halls, support spaces, office and generator yard with the state. Add it to the shell permit and DFW8 is about $532 million, the sum. A $300 million fit-out filing from May 2026 may be an earlier version of the same work, so we do not add it.

Across both buildings, four state filings add up to about $807 million, the sum: $275 million and $257.1 million for DFW8, and $200 million and $75 million for DFW7. The 8 generator-yard permits on DFW8 add up to about $4.5 million, the sum.

How far along is the CyrusOne Fort Worth data center?

The DFW8 shell permit was filed April 11, 2025 and first issued Sept. 17, 2025. The city asked for plan corrections 10 times between April 2025 and October 2026. It approved a plan change on Nov. 6, 2026 and marked the permit issued again on Nov. 16. Another plan change came in on Nov. 18.

On March 3, 2026 the city issued Clune 8 permits for the DFW8 generator yard: four $625,000 pads and four $500,000 screen walls. In September 2026, fire permits for four generator yards and the battery pods followed.

The state fit-out filing says the work runs from Oct. 1, 2026 to Oct. 30, 2027. Next door, DFW7 was filed with the state in September 2024 as a $200 million, 190,400 sq ft data center.

Who is building the CyrusOne Fort Worth data center?

Clune Construction is the general contractor of record on the DFW8 shell permit and on all 8 generator-yard permits. Clune is also on DFW7's shell and its $200 million tenant finish-out. Clune and the utility Oncor were at the April 2025 groundbreaking, per news reports.

JHET Architects of Dallas is the design firm on every DFW8 state filing. Winston Services is the third-party building inspector on the shell permit.

Which trade firms are on the CyrusOne Fort Worth data center?

On DFW8, Walker Engineering holds the electrical umbrella permit. TDIndustries holds the mechanical and plumbing permits. Wright Construction holds the plumbing umbrella permit and the underground fire line. Northstar Fire Protection has the sprinkler permit, with 3,397 heads and a fire pump, and a $1 million fire alarm permit with 1,000 devices.

The generator permits name 14 Cummins 2,250 kW generators in each of 4 service yards, 56 in all, the count, plus a 1,500 kW Cummins unit in each of yards 3 and 4. The battery permits name 14 Fibrebond pods in each of 3 yards. Burns & McDonnell builds the campus substation, including a $28.7 million foundation permit.

On DFW7 next door, city permits name Power Plus, Moss Utilities, Wallco Retaining Walls, Allied Universal Technology Services, Sema Wireless and Choate USA, and MTU engines in a generator yard. 18 firms in all are on the list below.

Who CyrusOne hired before

CyrusOne reuses its Dallas design firm, JHET Architects, across its Texas campuses, and spreads its general contractors around: Rogers-O'Brien in Freestone County, Alston in Illinois, and Clune here.

  • JHET Architects, PLLC: design firm on CyrusOne DFW10 shell and upfit, $750 million, Whitney, TX, 2024. Also on this job.
  • Rogers-O'Brien Construction Company, LLC: builder (stormwater operator) on CyrusOne Freestone campus, Fairfield, TX, 2026.
  • Alston Construction: builder (stormwater operator) on CyrusOne Sangamon County data center, Sangamon County, IL, 2026.
  • Dynalectric: electrical on CyrusOne NVA10 office build-out, Sterling, VA, 2026.

These are earlier or other jobs for the same owner. They are not counted in the 18 firms on this job.

How do the ways into the CyrusOne Fort Worth data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on CyrusOne's DFW8 data center on Asphalt DriveEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the CyrusOne Fort Worth data center?

Electrical distributors and power gear repsWalker Engineering on the DFW8 electrical permit, Burns & McDonnell on the substation, and Cummins and Fibrebond gear on a building with 56 generators of 2,250 kW.
Mechanical, plumbing and fire protection repsTDIndustries on DFW8's mechanical and plumbing permits, Northstar Fire Protection with 3,397 sprinkler heads, and Wright Construction on the underground fire line.
Concrete, site and building suppliersClune Construction on a $275 million shell and its generator pads, and Wallco Retaining Walls next door on DFW7.

What should you do next on the CyrusOne Fort Worth data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on CyrusOne's DFW8 data center at 9501 Asphalt Dr in Fort Worth.

Questions people ask about the CyrusOne Fort Worth data center

How much is the CyrusOne Fort Worth data center?

CyrusOne has given no total. The city's permit for the DFW8 shell is $275 million, and a $257.1 million fit-out is filed with the state, about $532 million, the sum. Four state filings for both buildings add up to about $807 million, the sum.

Who is building the CyrusOne data center in Fort Worth?

Clune Construction is the general contractor of record on the DFW8 shell permit and its 8 generator-yard permits. 18 firms are named on the job, listed above.

Where is the CyrusOne Fort Worth data center?

DFW8 is at 9501 Asphalt Dr in north Fort Worth, Tarrant County, Texas. DFW7 is next door at 9401 Asphalt Dr, and the campus substation is at 9400.

How big is CyrusOne DFW8?

The city permit lists 259,515 sq ft: 242,170 sq ft of data center floor and a 17,345 sq ft two-story office. CyrusOne says the whole campus is set for 200 MW.

When will CyrusOne DFW8 be done?

The state fit-out filing says the data hall work runs from Oct. 1, 2026 to Oct. 30, 2027.

Was the DFW8 permit just issued?

It was issued again. The city first issued the $275 million shell permit on Sept. 17, 2025, approved a plan change on Nov. 6, 2026 and marked it issued again on Nov. 16, 2026. Another plan change came in on Nov. 18.

Why could CyrusOne start so fast in Fort Worth?

The campus sits next to Chisholm Grid, a 100 MW battery site run by Eolian. CyrusOne says reusing that site's grid gear let it break ground in April 2025 and deliver capacity starting in 2026.

What generators are going into CyrusOne DFW8?

The city's tank permits name 14 Cummins 2,250 kW diesel generators in each of 4 service yards, 56 in all, the count, plus a 1,500 kW Cummins unit in each of yards 3 and 4.

How we built this list

We searched the City of Fort Worth's public Accela permit portal for 9400, 9401 and 9501 Asphalt Dr and for CyrusOne, DFW7, DFW8 and Project Boom on Nov. 22, 2026, and opened each key record by number, with its processing history. We read the state's TDLR filings for DFW7 and DFW8, CyrusOne's Jan. 13, 2026 release, Dallas Innovates, Converge Digest and Community Impact. We kept each firm a city record, a state filing or the news names on this campus; firms on DFW7 next door are marked as DFW7. Record dates are each permit's issue or filing date. The $532 million and $807 million are our sums of city and state filings, not CyrusOne's spend; we left out a $300 million fit-out filing that may be an earlier version of the $257.1 million one. Left out: the owner and the landowners, the battery site's owner, the permit expediter, the state accessibility reviewer, two electrical firms and a fiber firm at 9400 Asphalt Dr whose records do not name CyrusOne, and a reported tenant. Phones are each firm's own main or office line from its own site, except Wright Construction and Sema Wireless, whose lines are the contractor phone on the city permit, and JHET Architects, whose line is on the state filing. Cummins' and MTU's sites gave us no phone, so we give their websites only; we found no website for JHET Architects or Sema Wireless. First published Nov. 22, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 18 firms, free

All 18 firms on the CyrusOne Fort Worth data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.