Which DFW Airport bids are open, and when do they close?
DFW Airport's public bid board, on Bonfire, listed 13 open solicitations when we read it on Nov. 7, 2026. By their titles, 9 are construction or trade work, and 4 aren't: art conservation, an AI emergency platform, a racial profiling audit and investment consulting.
PA2315, Supply of Pre-Mixed and Volumetric Concrete, closes Dec. 1, 2026. The airport's Energy Transportation Asset Mgmt department posted it, so the airport is the buyer, and a supplier bids it directly rather than through a builder.
The soonest trade bid to close is PA2292, Roadside Marking Services, on Nov. 16, 2026, and the latest is PA2247, for accessible loading zones at Terminal B, on Dec. 10. The list shows no scope, quantity or value for any of them. Those sit on each bid's detail page, behind a bot check, and we didn't read them. The board stores close times with no time zone, so we give dates only.
Who is building DFW Airport's Terminal C?
DFW calls its Terminal C rebuild an approximately $3 billion project, done in partnership with American Airlines, inside a capital plan of nearly $9 billion. In August 2024 it said the whole terminal is expected to be complete in 2030.
Phase 1 went to a design-build joint venture of Austin Commercial, Azteca Enterprises and Alpha & Omega, with HOK and Muller & Muller on the design team. DFW's fact sheet lists Phases 2 and 3 as construction manager at risk. A Texas stormwater notice dated Sept. 25, 2026 names Suffolk - 3i, A Joint Venture as the operator on those phases, and Suffolk said in 2021 that it was selected with 3i Contracting.
Phase 2, the terminal's northern third, carries $503,250,000 on its state accessibility filing, which runs from June 1, 2026 to Sept. 30, 2028.
- Garage C. A state filing lists a new 6-level garage at Terminal C at $111,176,519, the first garages and roadways package.
- Garage B. A state filing lists its renovation at $24,496,607, from June 1, 2026 to July 30, 2027, with no builder named.
- PA2140. Terminal C Garage and Roadways North is on the open list, closing Nov. 24, 2026, and we couldn't read whether it is a construction, construction manager or design solicitation.
Which firms are already working at DFW Airport?
On Dec. 4, 2025, the airport board raised the not-to-exceed total for Terminal F and its Skylink station to $1.12 billion, with Innovation Next+, a joint venture whose members include Archer Western and Turner, set to finish Aug. 16, 2027. The same meeting approved EAS Contracting at up to $29.7 million for the west airfields' electrical system, and Alstom Transport USA at up to $22.6 million for a new Skylink station.
On May 7, 2026, the board approved Archer Western at $479,330 to repair the walkway bridge between Terminals C and D, Alstom at $3.95 million for Skylink's public address system, and Batson-Cook on the South Remote parking lot, which adds 1,500 spaces.
Texas construction stormwater notices also name Reyes Tx on Runway 18L-36R, Roadworx on airfield remediation, Urban Infraconstruction on slope remediation and Atmos Energy on a Terminal F gas main.
None of this work is an open bid. These are the firms already buying for airport jobs, and a notice or approval doesn't show what they've already bought.
How do the ways into DFW Airport work compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| DFW's supplier portal | Bonfire, the airport's public bid portal, plus [email protected] | Suppliers and trade firms that can contract with the airport | Each open bid, and notices of new ones that match your details | Bidders can't discuss an open bid with airport staff, and we didn't read the detail pages |
| The Terminal C builder | Suffolk - 3i, A Joint Venture, named on the state's stormwater notice for Phases 2 and 3 | Trade subs and suppliers for the terminal | A route to the construction manager on the terminal's northern third | We found no public bid page for this job |
| Firms already on airport work | Firms named in board approvals and state notices, like EAS Contracting, Archer Western, Reyes Tx or Roadworx | Suppliers and lower-tier subs | A conversation with a firm working at the airport now | An approval or notice doesn't show what's already bought |
| The designers | HOK on Terminal C Phase 2 and the garages, Corgan on the south Skylink escalator and canopy | Manufacturers and spec reps | A chance to get a product into the drawings | Phase 2's state filing starts June 1, 2026, so some specs may be set |
Who should go after DFW Airport's bids, and who shouldn't?
| Ready-mix and volumetric concrete suppliers | PA2315 buys pre-mixed and volumetric concrete for the airport, and it closes Dec. 1, 2026. |
|---|
| Striping, airfield electrical and utility pipe firms | The open list has trade bids in each, starting with Roadside Marking Services on Nov. 16, 2026. |
|---|
| Firms selling into Terminal C | Suffolk - 3i is on the state's notice for Phases 2 and 3, and the Phase 2 filing runs to Sept. 30, 2028. |
|---|
| Firms that need a scope and value up front | This isn't the place to start, because the open list shows neither and we didn't read the detail pages. |
|---|
What should you do next on DFW Airport's bids?
- Register on DFW's supplier portal and open PA2315 before Dec. 1, 2026 if you sell concrete.
- Read each bid's detail page for scope, value and any pre-bid meeting, and ask questions only the way the solicitation says.
- Call the Terminal C builder and the firms on current airport work if you sell to subs.
- Open the full list for every open trade bid with its date, and the firms named on the airport's work.
Questions people ask about DFW Airport's bids
What bids does DFW Airport have open?
DFW Airport's public bid board listed 13 open solicitations when we read it on Nov. 7, 2026. By their titles, 9 are construction or trade work, closing between Nov. 16 and Dec. 10, 2026. The other 4 are art conservation, an AI emergency platform, a racial profiling audit and investment consulting.
When does DFW Airport's concrete bid close?
PA2315, Supply of Pre-Mixed and Volumetric Concrete, closes Dec. 1, 2026. The board stores the close time with no time zone, so check the time on the bid itself.
How much is DFW Airport's concrete bid worth?
The open list states no value or quantity. Those are on the bid's detail page, which sits behind a bot check, and we didn't read it.
How do you bid on DFW Airport work?
Register on DFW's supplier portal on Bonfire. DFW's procurement page says registering there is how you get notified about future solicitations that match your details.
Can you call DFW Airport about an open bid?
No. DFW's procurement page says bidders can't discuss any part of a released solicitation with airport personnel. Use the route the solicitation gives, and [email protected] is the airport's general procurement inbox.
How much does DFW's Terminal C rebuild cost?
DFW calls it an approximately $3 billion project, built in partnership with American Airlines, inside a capital plan of nearly $9 billion. Phase 2, the terminal's northern third, carries $503,250,000 on its state accessibility filing.
Who is the contractor on DFW Terminal C?
A Texas stormwater notice dated Sept. 25, 2026 names Suffolk - 3i, A Joint Venture on Terminal C Phases 2 and 3, which DFW's fact sheet lists as construction manager at risk. Phase 1 went to a design-build joint venture of Austin Commercial, Azteca Enterprises and Alpha & Omega.
When will DFW's Terminal C be finished?
DFW said in August 2024 that the whole terminal is expected to be complete in 2030. The Phase 2 state filing runs from June 1, 2026 to Sept. 30, 2028.
Is the Terminal C garage out to bid?
PA2140, Terminal C Garage and Roadways North, is on the open list and closes Nov. 24, 2026. We couldn't read its detail page, so we don't know if it is a construction, construction manager or design solicitation, or what it is worth.
Who is building Terminal F at DFW?
Innovation Next+, a joint venture of Archer Western, Turner, Phillips May, H. J. Russell and CARCON Industries. The airport board raised its not-to-exceed total to $1.12 billion on Dec. 4, 2025, with completion set for Aug. 16, 2027.
What are the risks of chasing DFW Airport's bids?
We didn't read any scope, value or pre-bid date, and an addendum can extend, change or cancel a bid without showing on the list. Bidders can't talk to airport staff about an open bid, and 4 of the 13 open items aren't construction.
What happens next on DFW Airport's bid board?
Roadside Marking Services closes first, on Nov. 16, 2026, and the Terminal B loading zones bid closes last, on Dec. 10. Terminal C Phase 2 is under way through 2028, and DFW says the 2 remaining garages will follow other phases of the terminal work.
How we built this list
We read DFW Airport's public open bid list on Nov. 7, 2026, DFW's Terminal C page and fact sheet, its 2024 capital plan release, Texas accessibility filings for airport projects, Texas construction stormwater notices at airport sites, and press reports of the airport board's approvals. The bid detail pages sit behind a bot check, and we didn't read them, so each open bid shows only its title, reference, department and close date. A row is on the list only if a record ties it to DFW Airport, and we don't add values together. Only bids with a close date still ahead are marked as public bids. First published Nov. 8, 2026. Bid dates can move by addendum, and we'll update this page when a bid closes, changes or is added.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- DFW Airport, open bid list on Bonfire, read Nov. 7, 2026
- DFW Airport, supplier portal
- DFW Airport, procurement
- DFW Airport, Terminal C
- DFW Airport, Terminal C fact sheet, October 2026
- DFW Airport, Aug. 29, 2024
- Texas TDLR, TABS2025022276, Terminal C Phase 2
- Texas TDLR, TABS2024003000, garage package 1
- Texas TDLR, TABS2024003006, garage package 3
- Texas TDLR, TABS2026028827, south Skylink escalator and canopy
- EPA ECHO, Terminal C stormwater notice
- TCEQ, stormwater permit search
- Community Impact, Dec. 12, 2025
- Community Impact, May 20, 2026
- Suffolk, Dec. 13, 2021
- Primera Engineering, Terminal C garages and roadways