What are the biggest Dec. 1 jobs in Dallas-Fort Worth?
Project Jay, at an estimated $500 million, upgrades about 600,000 sq ft of a 1.2 million sq ft building at 1501 Distribution Dr. in north Fort Worth. Community Impact reported on Oct. 27, 2026 that Carrier's planned manufacturing and engineering center would be at that address.
Three data center registrations follow: Colovore Alliance, a 156,500 sq ft building at an estimated $430 million; DataBank's 443,679 sq ft DFW14 in Red Oak at $325 million; and the DAL130 campus in Westlake, with an $83 million data center, a $45 million water building and a $15 million access building.
AT&T's new headquarters campus in Plano registers 11 buildings for Dec. 1: 7 office buildings, 3 concrete garages and a central utility plant, $1.05 billion in all.
- Apartments. Trinity Green 4 and 2 Cityplace Apron buildings in Dallas, Vitruvian Park Block 301 in Addison, and townhomes in Waxahachie.
- Health care. Methodist Richardson's 3-story addition ($64 million), Medical City Fort Worth's garage and helipad ($41.1 million), Baylor Scott & White McKinney's dietary renovation, and 3 freestanding emergency rooms.
- Public work. Denton County's civil courts ($60 million), Mesquite ISD's new elementary ($58 million), Plano and DeSoto street work, a water district service center and a Parker County fire station.
- Retail and industrial. A Costco Business Center and fuel station in Haltom City, BMW of Arlington, Kroger shell lots in Plano, Alliance Westport warehouses and Point East Industrial in Frisco.
Every one gives Dec. 1, 2026 as its estimated start. They were registered from Feb. 19 to Nov. 4, 2026.
Who's building the Dec. 1 jobs in Dallas-Fort Worth?
The registrations name the owner, and for 63 of the 80 that's the only firm we found on a record.
At AT&T's campus, the Texas Commission on Environmental Quality's stormwater authorization names Austin Commercial, LP as operator, with coverage from Aug. 17, 2026. At Vitruvian Park in Addison, the authorization names Cbg Building Company LLC, with coverage from Oct. 5, 2026; two Dec. 1 registrations sit at that corner, 304 apartments with an attached concrete garage ($42 million) and a 3-story concrete-framed amenity building ($12 million). At Point East Industrial in Frisco, the authorization names Arco/Murray National Holdings.
ATI's copies of city permits name Brasfield & Gorrie on Baylor Scott & White McKinney's dietary renovation, OakHaven Construction on Bank OZK's Denton branch, and Blackland Valley Holdings on a DeSoto warehouse.
We found no news story naming a builder for the Vitruvian Park buildings, and none that lists these 80 jobs together.
How firm is a Dec. 1 start date on a Texas registration?
It's the owner's estimate, entered when the job is registered, and it can move. Mesquite ISD's bond page says its new school is anticipated to begin construction in 2027, later than its registration says. Vitruvian Park's stormwater notice gives an earlier start for site work, Oct. 19, 2026, and Point East Industrial's a later one, Dec. 14.
Fort Worth's $500 million building permit for 1501 Distribution Dr., applied for Oct. 27, 2026, read 'Void' when we last read it on Nov. 7, though the state registration stands. Treat Dec. 1 as the month the owner is aiming for, and ask the builder or owner where the job stands.
How do the ways into the Dec. 1 jobs compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The builder on the record | Call the firm a stormwater notice or permit names, like CBG Building Company at Vitruvian Park or Austin Commercial at AT&T's campus | Concrete, rebar, forming and site suppliers and subs | A conversation with the firm running the site | Only 17 of the 80 have a builder on a record we found |
| The owner | Reach the owner named on the state registration and ask who's building it | Firms that want in before a builder is picked | The builder's name, or a place on the owner's list | Many owners are single-project companies with no published phone line |
| Public owners' purchasing offices | Denton County, Mesquite ISD, the City of Plano, the City of DeSoto, the North Texas Municipal Water District, Parker County ESD 7 and Texas A&M | Firms registered as public vendors | Their bid notices and construction manager picks | We found no open bid on these jobs today |
| The state's stormwater notices | Texas's construction stormwater notices name the operator running a site | Sitework, erosion control and concrete sellers | The first firm on the ground, often before the building starts | Not every job files one, and a notice isn't a contract |
| City permits | The building permit names the contractor when it's filed | Every trade | The builder's name and a stated value | We found a permit naming a builder for only 4 of the 80 |
Who should go after the Dec. 1 jobs, and who shouldn't?
| Concrete, rebar and forming suppliers and subs | 53 of the 80 are new buildings. AT&T's campus registers 3 concrete garages, and Vitruvian Park an attached concrete garage and a concrete-framed amenity building. |
|---|
| Sitework, paving and underground utility firms | New pads, data center campuses, fuel stations, a DeSoto street and sewer rebuild and Plano's intersection work all start in the dirt. |
|---|
| Interior, MEP and finish trades | 24 renovations and additions, from Denton County's civil courts to Methodist Richardson, plus finish-outs like Evernorth's 88,972 sq ft space in Lewisville. |
|---|
| Firms that want an open public bid with a due date | This list isn't that yet: these are owners' start estimates, and we found no open bid on any of them. |
|---|
What should you do next on the Dec. 1 jobs?
- Open the full list and sort it by your trade and county.
- Call the builders already on a record first: CBG Building Company at Vitruvian Park, Austin Commercial at AT&T's campus, ARCO/Murray at Point East Industrial.
- For the other 63, ask the owner who's building it, and watch the city for the building permit.
- Register with the public owners' purchasing offices, Denton County and Mesquite ISD among them.
Questions people ask about the Dec. 1 jobs in Dallas-Fort Worth
What construction projects are scheduled to start in Dallas-Fort Worth on Dec. 1, 2026?
80 jobs of $1 million or more are registered with the Texas Department of Licensing and Regulation with an estimated start of Dec. 1, 2026. The biggest are Project Jay at 1501 Distribution Dr. in Fort Worth ($500 million), the Colovore Alliance data center ($430 million), DataBank's Red Oak data center ($325 million) and AT&T's 11-building Plano headquarters campus ($1.05 billion in all).
How much are the Dec. 1 jobs worth?
The owners' estimated costs for the 80 add up to $3,163,061,424, about $3.16 billion. These are estimates on a state registration, not contract values.
Who is building the Dec. 1 jobs?
The registrations name owners. We found a builder on a record for 17: Austin Commercial on the stormwater record for AT&T's campus (11 registrations), CBG Building Company on the stormwater record for Vitruvian Park in Addison (2), ARCO/Murray on Point East Industrial in Frisco, and Brasfield & Gorrie, OakHaven Construction and Blackland Valley Holdings on city permits.
Who is building Vitruvian Park Block 301?
The Texas Commission on Environmental Quality's stormwater authorization for Vitruvian Park, at Ponte Avenue and Bella Lane in Addison, names Cbg Building Company LLC as operator, with coverage from Oct. 5, 2026. It's not a contract, and it states no price.
Will these jobs really start on Dec. 1?
Not all of them. The date is the owner's estimate when it registered the job. Mesquite ISD's bond page says its Motley-Lawrence school is anticipated to begin construction in 2027, and Vitruvian Park's stormwater notice gives an earlier start for site work, Oct. 19, 2026.
What is a TDLR TABS registration?
It's the Texas Department of Licensing and Regulation's accessibility registration. Jobs with an estimated construction cost of $50,000 or more must be registered, and each registration lists the owner, the scope, an estimated cost and estimated start and finish dates.
Which trade do most of the Dec. 1 jobs need first?
Concrete and sitework. 53 of the 80 are new buildings from the ground up, worth $2.43 billion, and a new building starts with the pad and foundation.
Is AT&T's new headquarters on the list?
Yes. Its 11 Project Eagle registrations in Plano, 7 office buildings, 3 garages and a central utility plant, carry $1.05 billion of estimated cost and a Dec. 1 start. We covered the campus in its own report.
Is Carrier's Fort Worth plant on the list?
The biggest registration, Project Jay, is at 1501 Distribution Dr., the address Community Impact reported for Carrier's planned site. The registration names the owner, Alliance Westport No. 12 Ltd, not Carrier.
Is Costco building in Haltom City?
2 registrations set for Dec. 1 name a Costco in Haltom City: a 146,853 sq ft Costco Wholesale Business Center at an estimated $18.4 million, and a Costco fuel facility at $3.8 million. The owner on both is Louis Engler Properties LLC.
Are any of these jobs open for bids?
We found no open bid with a due date on any of the 80. Public owners on the list, like Denton County and Mesquite ISD, post their bids and construction manager picks through their purchasing offices.
What are the risks of chasing these jobs?
Start dates move, 63 of the 80 have no builder on a record yet, and a stormwater notice or permit can name a firm without saying what it's paid.
How we built this list
We read every registration in ATI's copy of the Texas Department of Licensing and Regulation's architectural barriers register (TABS) for Dallas-Fort Worth's 13 counties with an estimated cost of $1 million or more and an estimated start date of Dec. 1, 2026. That gives 80, registered from Feb. 19 to Nov. 4, 2026. Another 67 registrations under $1 million carry the same date and aren't listed. TDLR's public site answered with a server error when we tried to open its pages on Nov. 8, so the details come from ATI's stored copies, read from the register between Oct. 31 and Nov. 8. We then looked for a builder on each job in ATI's copies of city permits, the Texas Commission on Environmental Quality's construction stormwater notices, and the press. A builder is listed only when the record's address or site name matches the job. Dollar figures are the owners' estimated costs on the registrations, not contract values. First published Nov. 8, 2026. We'll update this page when a city issues a building permit or a stormwater notice names a builder on one of these jobs, and after Dec. 1 to say which ones started.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- Texas Department of Licensing and Regulation, TABS project search (registrations read from ATI's stored copy; the site answered 503 on Nov. 8)
- TCEQ, construction stormwater authorization TXR1519ZQ, Vitruvian Park
- TCEQ, construction stormwater authorization TXR1509ZE, Project Eagle
- TCEQ, construction stormwater authorization TXR1538ZS, Point East Industrial
- EPA ECHO, TXR1519ZQ
- CBG Building Company, Dallas office
- Brasfield & Gorrie, Dallas
- CRE Daily, AT&T Plano headquarters, Oct. 16, 2026
- Community Impact, Carrier, Oct. 27, 2026
- Community Impact, Colovore, Sept. 29, 2026
- Baxtel, PowerHouse Circle T, Aug. 7, 2026
- Mesquite ISD, bond
- WGI, when a project needs TDLR registration