What is Disney building at Walt Disney World?
Disney is building four new lands at once at Walt Disney World. At Magic Kingdom, Piston Peak National Park (Cars) is going up where Tom Sawyer Island and the Rivers of America used to be, with Cars Ridge Run Rally and Miss Fritter's Daredevil Spin Along. Villains Land is next to it, with a Maleficent coaster and a Magic Mirror dark ride.
At Animal Kingdom, Tropical Americas brings an Encanto ride (Antonio's Fiesta de Encanto), an Indiana Jones ride in place of DINOSAUR, a carousel and a playground. At Hollywood Studios, Monstropolis (Monsters, Inc.) brings a suspended door coaster, the Glob Theater in the old MuppetVision 3D building and a playground.
How much is Disney spending on Walt Disney World?
On June 5, 2024, Disney and the state-appointed district that now runs the resort's land agreed to a deal under which Disney could invest up to $17 billion in its Florida resort. The deal ended a fight with Gov. Ron DeSantis's appointees. It also says at least half of Disney's construction projects must go to Florida companies.
The $17 billion covers all of Walt Disney World, not these four lands alone. Disney has not published a cost for any of the four lands, and the notices filed for them state no contract values. Worldwide, Disney said in 2023 it would spend about $60 billion on its parks over 10 years.
Who is building Villains Land and Piston Peak at Magic Kingdom?
On Nov. 17, 2026, Walt Disney Imagineering recorded a Notice of Commencement for general construction at 1612 Magic Kingdom Dr, a brand-new address beside the Haunted Mansion. PCL Construction Services is the contractor, the same firm named in September at 1610 Magic Kingdom Dr. The notice is good for one year. Disney has not said whether the buildings are for Villains Land or Piston Peak.
Balfour Beatty is named for general construction near Big Thunder Mountain Railroad (April 2026). NorthStar Contracting Group has the demolition and site prep of Tom Sawyer Island and the Rivers of America (extended July 23, 2026), Phillips has the former Aunt Polly's site (July 2026), and MLC Theming had the old Keel Boat Landing (January 2026). A tower crane went up at Piston Peak in late September 2026, the start of work on the ride buildings.
Who is building Tropical Americas at Animal Kingdom?
Whiting-Turner is the general contractor. On Nov. 12, 2026, Imagineering amended its notice for general construction at 500 DinoLand Dr to run to November 2027, and Disney is still targeting a 2027 opening.
Pro Audio Video is the electrical contractor on nine notices filed in April 2026, covering the Indiana Jones ride, the Encanto ride, the carousel and Restaurantosaurus. Coastal Steel Group (July 1, 2026) and InterAmerica Stage (August 2026) are named at 504 DinoLand Dr, the Encanto ride. Scenario, Adirondack Studios and Mecca Productions are named for sets, and Landscape Structures for the playground.
Who is building Monstropolis at Hollywood Studios?
Icarus Exhibits is named on four notices from April 3, 2026 to install sets in the old PizzeRizzo, MuppetVision 3D, Mama Melrose's and Muppets gift shop buildings. Adirondack Scenic installs sets in the MuppetVision building. At the Glob Theater, Solotech is the audio and video contractor (notice amended Nov. 13, 2026, to November 2027) and Elite A/V Systems has the electrical work.
On Nov. 12, 2026, Imagineering hired Mecca Productions to install sets at 253 S Studio Dr, likely the door coaster building. Nine shipments of Vekoma coaster parts, about 630,000 pounds, reached Imagineering from Oct. 16 to Nov. 9, likely for the same ride. Landscape Structures is building the playground at 361 Cypress Dr.
When do Disney World's new lands open?
Disney is targeting 2027 for Tropical Americas. Monstropolis opens in phases, with most of the land in 2027 and the door coaster later. Disney has not given an opening year for Piston Peak National Park or for Villains Land, which it showed at D23 on Aug. 16, 2026.
Who Disney hired before
Disney keeps going back to the same firms: six on these four lands also show up on its other jobs, from Test Track to the Galactic Starcruiser.
- Balfour Beatty: contractor named on a permit on Star Wars: Galactic Starcruiser building, Walt Disney World, FL, 2026. Also on this job.
- Solotech: audio/visual contractor on Test Track reimagining (EPCOT) and Zootopia: Better Zoogether (Animal Kingdom), Walt Disney World, FL, 2025. Also on this job.
- Mecca Productions: set installation on Reimagined Carousel of Progress (Magic Kingdom), Walt Disney World, FL, 2026. Also on this job.
- Pro Audio Video, Inc.: electrical / A/V on Test Track 3.0 and the Beak and Barrel, Walt Disney World, FL, 2025. Also on this job.
- PCL Construction: renovation contractor on Disney Technology Solutions & Services (DTSS) Orlando Data Center, Orlando, FL, date not stated. Also on this job.
- Landscape Structures: play equipment on EPCOT play area (2016), Walt Disney World, FL, 2016. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 17 firms on this job.
How do the ways into Disney World's new lands compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Walt Disney World job | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The work still coming | New notices at new addresses, like 1610 and 1612 Magic Kingdom Dr this fall | Builders and trade subcontractors | An early look at buildings before they rise | Disney publishes no contract values, and Villains Land has no opening date |
Who should go after Disney World's new lands?
| Electrical, A/V and lighting suppliers | Pro Audio Video's nine Tropical Americas notices, Elite A/V Systems at the Glob Theater and Solotech's audio and video work in Monstropolis. |
|---|
| Steel, concrete and site suppliers | PCL's two new buildings beside the Haunted Mansion, Balfour Beatty at Piston Peak, Coastal Steel Group at the Encanto ride and NorthStar's demolition and utility work. |
|---|
| Theming, set and fabrication shops | Mecca Productions, Icarus Exhibits, Adirondack, Scenario, InterAmerica Stage and MLC Theming all hold set or theming notices on the four lands. |
|---|
What should you do next on Disney World's new lands?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Walt Disney World job named on the notice: Villains Land, Piston Peak, Tropical Americas or Monstropolis.
- Watch for new notices near the Haunted Mansion and at the Monstropolis door coaster.
Questions people ask about Disney World's new lands
What new lands is Disney building at Walt Disney World?
Four: Piston Peak National Park (Cars) and Villains Land at Magic Kingdom, Tropical Americas at Animal Kingdom, and Monstropolis (Monsters, Inc.) at Hollywood Studios. All four are under construction.
How much will Disney World's new lands cost?
Disney has not published a cost for the four lands. They are part of the up-to-$17 billion Florida build-out Disney agreed to on June 5, 2024. That figure covers the whole resort, not these four lands alone.
Who is building Villains Land?
PCL Construction Services is named on two new buildings beside the Haunted Mansion, at 1612 Magic Kingdom Dr (notice recorded Nov. 17, 2026) and 1610 Magic Kingdom Dr (September 2026). Disney has not said whether they are for Villains Land or Piston Peak.
Who is building Piston Peak National Park?
Balfour Beatty is named for general construction near Big Thunder Mountain Railroad, NorthStar Contracting Group for demolition and site prep of Tom Sawyer Island and the Rivers of America, and Phillips for the former Aunt Polly's site.
Who is building Tropical Americas at Animal Kingdom?
Whiting-Turner is the general contractor, with its notice extended to November 2027 on Nov. 12, 2026. Pro Audio Video has the electrical work on nine notices, and Coastal Steel Group and InterAmerica Stage are named at the Encanto ride.
Who is building Monstropolis at Hollywood Studios?
Icarus Exhibits, Adirondack Scenic and Mecca Productions are named for sets, Solotech and Elite A/V Systems for audio, video and electrical work at the Glob Theater, and Landscape Structures for the playground. Vekoma coaster parts are likely for the door coaster.
When will Disney World's new lands open?
Disney is targeting 2027 for Tropical Americas and for most of Monstropolis; the door coaster opens later. Disney has not given a year for Piston Peak National Park or Villains Land.
How big is Villains Land?
Disney says Villains Land is comparable in size and scale to Star Wars: Galaxy's Edge at Hollywood Studios. It will have a Maleficent coaster and a Magic Mirror dark ride.
Does Disney have to hire Florida companies?
Yes, in part. Its June 2024 deal says at least half of Disney's construction projects must go to Florida companies.
How can subcontractors get on Disney World's new lands?
Call the firms already on the job, starting with the builders: PCL Construction Services, Whiting-Turner and Balfour Beatty. Ask for the team on the Walt Disney World job named on the notice.
What happens next on Disney World's new lands?
Watch for more notices at new addresses near the Haunted Mansion and for the door coaster's track work. We'll update this page when a new notice or firm appears.
How we built this list
We read news reports of the Notices of Commencement Walt Disney Imagineering recorded with Orange County for the four lands, from two Disney news sites that read the county's records, and Disney's own announcements, on Nov. 22, 2026. We did not open the recorded notices ourselves. We kept each firm a notice names on one of the four lands; Vekoma is a likely tie from import records, not a notice. No notice states a contract value. Left out: Disney itself (the owner), the state-appointed district and the water district (government), and a chiller contractor on a nearby energy plant that no record ties to the four lands. Phones are each firm's own line from its own site; Phillips is a main line, Landscape Structures is in Minnesota, and we found no line for NorthStar, Solotech or Vekoma and no website we could confirm for NorthStar, Pro Audio Video or Elite A/V Systems. First published Nov. 22, 2026. We'll update this page when a new notice, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 22, 2026- PBS NewsHour (AP): Disney set to invest up to $17 billion in Florida parks (June 5, 2024)
- BlogMickey: new Imagineering permit could signal Villains Land work (Nov. 17, 2026)
- WDW News Today: Imagineering files construction permit that may be for Villains Land (Nov. 17, 2026)
- BlogMickey: Imagineering files permit for new building in Piston Peak site (Sept. 23, 2026)
- BlogMickey: Piston Peak shifts into new gear (Sept. 27, 2026)
- FOX 35 Orlando: everything announced for Walt Disney World at D23 (Aug. 16, 2026)
- BlogMickey: Imagineering extends Tropical Americas permit to November 2027 (Nov. 2026)
- BlogMickey: Glob Theater permit extended into November 2027 (Nov. 13, 2026)
- WDW News Today: permit to install set elements for the Monsters, Inc. door coaster (Nov. 12, 2026)
- BlogMickey: is Project La Brea the codename for the Monsters, Inc. coaster? (Nov. 12, 2026)
- The Walt Disney Company: plans to expand investment in parks (Sept. 19, 2023)
- Notice of Commencement report: Balfour Beatty (2026-04-09)
- Notice of Commencement report: Pro Audio Video, Inc. (2026-04-16)
- Notice of Commencement report: Elite A/V Systems, Inc. (2026-07-09)
- Notice of Commencement report: Coastal Steel Group (Coastal Steel) (2026-07-01)
- Notice of Commencement report: NorthStar Contracting Group, Inc. (NorthStar Group Services) (2026-07-23)
- Notice of Commencement report: Phillips (formerly Phillips & Jordan) (2026-07-01)
- Notice of Commencement report: InterAmerica Stage (2026-08-27)
- Notice of Commencement report: Adirondack Scenic (Adirondack Studios) (2026-03-05)
- Notice of Commencement report: Icarus Exhibits, Inc. (2026-04-03)
- Notice of Commencement report: Scenario (Scenario Global) (2026-03-03)
- Notice of Commencement report: MLC Theming (2026-01-19)
- Notice of Commencement report: Landscape Structures, Inc. (2026-10-13)
- WDW News Today: first permit filed for Monsters, Inc. land at MuppetVision 3D (July 2025)