Who is building Reagan National's North Airfield Package 2?
MWAA's new contract awards page lists Lagan Construction, LLC on North Airfield Improvements, Package 2, awarded July 14, 2026 at not to exceed $146,756,960.15. We found no press on the award.
Virginia's environmental agency received Lagan's construction stormwater permit filing for the job on Oct. 19, 2026. It describes improved airfield drainage, taxiways, hold bays and electrical on 58.59 acres, with work estimated from Oct. 30, 2026 to Dec. 31, 2028.
That filing is stormwater permit coverage, not a building permit. It names the operator, so it's the plainest public record of who is working on Reagan's north airfield now.
Aldridge Electric held the state filing for an earlier North Airfield package at Reagan, with work estimated to end Aug. 1, 2026.
What is MWAA buying at Dulles, and when are bids due?
The biggest dated bid is the rebuild of Dulles Runway 1R-19L and its taxiways. MWAA issued the request on Sept. 22, 2026, and proposals are due Nov. 18, 2026. The scope includes LED airfield lighting and signs, electrical vault changes, and underground drainage and utilities.
MWAA hasn't stated a contract value. Its fourth-quarter 2026 forecast puts the runway in its over $200 million band, and a December 2024 MWAA presentation estimated construction at $150 million to $200 million, starting in 2027.
- Stormwater. MWAA's page gives a Nov. 9, 2026 due date for Dulles airfield stormwater work meant to stop water coming in from Route 28.
- Fire training. A design-build upgrade of the Dulles live fire training grounds is due Nov. 18, 2026.
- Terminal 1. The construction manager request for Reagan's Terminal 1 and South Area work shows a Nov. 23, 2026 due date, with 2 amendments issued.
- Forecast. MWAA's planned procurements include a new Dulles concourse and Reagan's roadway master plan, each over $200 million, with no dates.
Every due date here is MWAA's own and can move by amendment, so confirm it with MWAA before you count on it.
Who else holds work at Reagan and Dulles right now?
Virginia's stormwater records name Turner Construction on site work for the center Tier 2 concourse at Dulles, filed May 5, 2026 for 74.63 acres, and Atlantic Contracting & Materials on Dulles taxilane work filed March 24, 2026.
MWAA's awards page lists 2026 contracts to firms including RMS Electrical Services for Dulles audio paging at $9,998,259, Hughes Network Systems for a private wireless network at $1,241,394, and DAA International Virginia for a remote VIP services facility at Dulles at $125,000,000.
How do the ways into Reagan and Dulles work compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Lagan Construction | The firm on MWAA's Package 2 award and the state filing | Drainage pipe, structures, conduit, cable and light base sellers | A conversation with the builder on Reagan's airfield now | We found no public list of what it has already bought |
| MWAA's current solicitations | Bids and proposals with due dates on mwaa.com | Primes and firms that bid public work | A bid with a stated due date | Most are prime contracts, so a supplier needs a bidder to sell through |
| MWAA's awards page | Contract winners with amounts and award dates | Subs and suppliers looking for a buyer | A named firm already under contract | It shows only the contract's title, not its scope |
| MWAA's forecast | Planned procurements for October to December 2026, with value bands | Firms planning their pipeline | Early warning on big work, like a new Dulles concourse | Its dates are estimates, and it gives no issue dates |
| General contractor registration | A form linked from MWAA's contracting pages | General contractors new to MWAA | Your firm on file with the airport authority | The pages we read don't say what registering gives you |
Who should go after Reagan and Dulles work, and who shouldn't?
| Drainage pipe and structure suppliers | Lagan's state filing lists airfield drainage across 58.59 acres, with work set to start Oct. 30, 2026. |
|---|
| Airfield electrical and lighting sellers | Package 2 lists electrical, and the Dulles runway bid due Nov. 18, 2026 includes LED lighting and signs. |
|---|
| Heavy civil and paving primes | The Dulles runway rebuild and the Dulles stormwater rehabilitation both carry stated due dates. |
|---|
| Firms that need a contract value first | This isn't the job for you yet: the Dulles runway has only a forecast band, and Package 2's figure is a ceiling. |
|---|
What should you do next on Reagan and Dulles work?
- Call Lagan Construction if you sell drainage pipe, structures, conduit, cable or light bases.
- Read MWAA's Dulles runway notice before the Nov. 18, 2026 due date if you sell airfield lighting or paving.
- Watch MWAA's awards page for the winners of the bids that closed this year.
- Open the full list and call the firm named for your trade.
Questions people ask about Reagan and Dulles construction
Who is building Reagan National's North Airfield Package 2?
Lagan Construction, LLC, of Sterling, Virginia. MWAA's new contract awards page lists the firm on the contract, awarded July 14, 2026, and Lagan is the operator on the job's Virginia construction stormwater permit filing, received Oct. 19, 2026.
How much is the North Airfield Package 2 contract worth?
MWAA lists it at not to exceed $146,756,960.15. That's a ceiling on the contract, not a final cost.
When does work start on Reagan's North Airfield Package 2?
Lagan's state filing gives an estimated start of Oct. 30, 2026 and an estimated end of Dec. 31, 2028. Those are estimates on the filing, not confirmed dates.
What does the North Airfield Package 2 at Reagan cover?
The state filing describes improved airfield drainage, taxiways, hold bays and electrical, with 58.59 acres disturbed. No public list of materials or subcontracts has been posted.
Is the Virginia filing a building permit?
No. It's coverage under Virginia's construction stormwater permit, which a site operator needs before it disturbs land. It names the operator, the site, the acreage and the estimated dates.
When are bids due on Dulles Runway 1R-19L?
MWAA's current opportunities page gives a Nov. 18, 2026 due date for proposals to rebuild Runway 1R-19L and its taxiways. MWAA issued the request on Sept. 22, 2026 and has issued 4 amendments.
How big is the Dulles Runway 1R-19L job?
There's no contract value yet. MWAA's fourth-quarter 2026 forecast puts it in its over $200 million band, and a December 2024 MWAA presentation estimated construction at $150 million to $200 million.
Who is building the Dulles runway?
No one yet. MWAA hasn't chosen a prime, and we found no public record naming the firms proposing on it.
How do subcontractors and suppliers get on Reagan and Dulles work?
Call the prime named on an award, like Lagan on North Airfield Package 2, or bid MWAA's own solicitations on its current opportunities page. MWAA also links a general contractor registration form. None of these guarantees work.
What else is bidding at Reagan and Dulles?
Besides the runway, MWAA's page lists due dates from Nov. 9 to Dec. 3, 2026 for stormwater work, a building demolition, a fire training facility, a terminal construction manager and smaller jobs. Each due date is MWAA's and can move with an amendment.
What are the risks of chasing this work?
Much of Package 2 may already be bought, the start date is an estimate, and MWAA's dates can change by amendment. The forecast items have no issue dates, and some bids closed months ago with no winner posted.
What happens next at Reagan and Dulles?
Proposals on the Dulles runway are due Nov. 18, 2026, and MWAA should post winners for the bids that closed this year on its awards page. Its forecast lists more work, including a new Dulles concourse and Reagan's roadway plan, with no dates yet.
How we built this list
We read MWAA's public contracting pages on mwaa.com (current opportunities, contract awards, upcoming awards and its fourth-quarter 2026 forecast), Virginia DEQ's public construction stormwater records at both airports, and press coverage. A row is on the list only if one of those records ties it to Reagan National, Dulles or the Dulles Toll Road. We don't add contract values together, a forecast band is never a contract value, and a row is marked as a bid only when MWAA states a future due date. First published Nov. 8, 2026. We'll update this page when MWAA posts a new award, a due date moves, or a new state filing appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- MWAA, current contracting opportunities
- MWAA, new contract awards
- MWAA, upcoming awards
- MWAA, upcoming contracting opportunities
- MWAA, solicitation forecast, Q4 2026
- Virginia DEQ, construction stormwater record VAR10X866
- Virginia DEQ, construction stormwater record VAR10X117
- Virginia DEQ, construction stormwater record VAR10W904
- MWAA presentation to SAME, Dec. 2024
- FFXnow, March 20, 2025
- Lagan Construction, contact
- Aldridge, contact