What is Fermi building near Amarillo?
Fermi is building Project Matador, a campus with its own power plants and AI data centers, planned for about 8,400 acres beside the Pantex Plant, northeast of Amarillo in Carson County, Texas. The land is leased from the Texas Tech University System. Fermi Inc. trades on the NASDAQ, and it was co-founded by Rick Perry, the former Texas governor and U.S. Energy Secretary.
So far the work is power and site work. As of Oct. 31, 2026, Fermi says about 300 acres are prepared, with 4.6 miles of gas line, 7.2 miles of water line and 11.3 miles of fence. Five gas turbines are on site: three GE 6B units with their foundations poured and two Siemens F-class units. No data center building is up yet.
How much is Project Matador?
Fermi has not given a total cost. On Nov. 12, 2026, it said it has nearly $1.7 billion invested in the buildout so far. Its balance sheet shows $1.66 billion of construction in progress on Sept. 30, 2026. That is money already spent, on engineering, site preparation and equipment such as turbines, not a budget or a contract.
Fermi and the customer are also finalizing a $90 million sale of Fermi's structural steel and building materials to the customer. Siemens Energy still had about $126.2 million of turbine orders open with Fermi on Sept. 30.
Who is the customer at Project Matador?
TensorWave signed a lease in August 2026 to be the first tenant. On Nov. 12, 2026, Fermi said that lease was terminated.
The same day, Fermi said an investment-grade hyperscaler had signed a non-binding letter of intent for 600 MW starting in 2027, with a $200 million prepayment agreement and a $15 million early construction and site development deal. Fermi has not named the customer. The Financial Times reported it is Amazon.
Who is building Project Matador?
Fermi names two EPC partners. Fermi picked Primoris to engineer and build the balance of plant around the first six Siemens SGT-800 turbines: underground lines, equipment foundations and tie-ins. Primoris had already dug out the six turbine power islands. TSK, a Spanish firm, has the early works for three Siemens F-class turbines: permits, moving onto the site and engineering.
Siemens Energy makes the turbines. Energy Transfer has committed up to 220,000 MMBtu of gas a day, and Southwestern Public Service, part of Xcel Energy, connects up to about 200 MW of grid power. NAES will run the gas power plants, and CBRE will run data center building one once it is built.
What about the nuclear plan and the water fight?
Fermi plans four Westinghouse AP1000 reactors, with the first planned for 2034. Hyundai E&C did front-end design work for them, and Doosan Enerbility agreed to start forging long-lead reactor parts. Federal regulators put out a draft environmental review on Oct. 9, 2026; comments close Nov. 23.
On Nov. 19, 2026, the Panhandle Groundwater Conservation District approved comments asking regulators for more detail on water demand, current wells, effects on groundwater and how it will be monitored. Fermi's own filing also lists a lawsuit from its former CEO and a pending securities class action. 10 firms in all are on the list below.
How do the ways into Project Matador compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Fermi's Project Matador near Amarillo | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose work matches what you sell |
| The data center buildings still to come | A place with the builders once the data halls start | Builders, electrical, mechanical and steel subcontractors | A share of a campus with nearly $1.7 billion already invested | No data center builder named yet, and vertical work waits on lease conditions |
Who should go after Project Matador?
| Power, gas and electrical suppliers | Primoris on the balance of plant for six SGT-800 turbines, TSK on three F-class turbines, and NAES running the gas plants. |
|---|
| Site, concrete and pipe suppliers | Primoris's underground lines and equipment foundations, on a site with 4.6 miles of gas line and 7.2 miles of water line already in. |
|---|
| Data center and building systems reps | CBRE will run data center building one (cooling, fire protection, building systems), and Fermi is finalizing a $90 million sale of steel and building materials to the customer. |
|---|
What should you do next on Project Matador?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Fermi's Project Matador campus near Amarillo, in Carson County.
- Watch for the data center builder, the long-term lease with the hyperscaler and its 600 MW start in 2027.
Questions people ask about Fermi's Project Matador
How much is Fermi's Project Matador?
Fermi has not given a total cost. It says it has nearly $1.7 billion invested in the buildout so far. Its Sept. 30, 2026 balance sheet shows $1.66 billion of construction in progress. That is money spent, not a budget.
Where is Project Matador?
It is planned for about 8,400 acres beside the Pantex Plant, northeast of Amarillo, in Carson County, Texas. The core site is leased from the Texas Tech University System. No street address is published.
Who is building Project Matador?
Fermi names Primoris and TSK as its EPC partners. Primoris is building the balance of plant for the first six Siemens SGT-800 turbines, and TSK has the early works for three Siemens F-class turbines. 10 firms are named on the job, listed above.
Who is the customer at Project Matador?
Fermi says an investment-grade hyperscaler signed a $200 million prepayment agreement for 600 MW starting in 2027, under a non-binding letter of intent, and a $15 million early construction deal. Fermi has not named it. The Financial Times reported it is Amazon.
What happened to TensorWave at Project Matador?
TensorWave signed a lease in August 2026 to be the first tenant. Fermi said on Nov. 12, 2026 that the lease was terminated.
What is built at Project Matador so far?
As of Oct. 31, 2026: about 300 acres prepared, 4.6 miles of gas line, 7.2 miles of water line, 11.3 miles of fence, and five gas turbines on site. No data center building is up yet.
Will Project Matador have nuclear power?
Fermi plans four Westinghouse AP1000 reactors. Federal regulators put out a draft environmental review on Oct. 9, 2026, with comments due Nov. 23. Fermi plans the first reactor for 2034.
Why is the Panhandle groundwater district asking about Fermi?
On Nov. 19, 2026, the Panhandle Groundwater Conservation District approved comments asking federal regulators for more detail on water demand, current wells, effects on groundwater and how it will be monitored under Fermi's four-reactor plan.
Who supplies power and gas to Project Matador?
Energy Transfer has committed up to 220,000 MMBtu of natural gas a day. Southwestern Public Service, part of Xcel Energy, connects up to about 200 MW of grid power. NAES will run the gas power plants.
Who is Fermi?
Fermi Inc. is a public company (NASDAQ: FRMI) co-founded by Rick Perry, the former Texas governor and U.S. Energy Secretary. It is building Project Matador as a private power grid and AI data center campus.
What happens next on Project Matador?
Fermi and the customer are finalizing a $90 million sale of Fermi's structural steel and building materials to the customer and a long-term lease. The data center buildings wait on Texas Tech lease conditions that come before vertical construction. We'll update this page when a new contract or firm appears.
How we built this list
We read Fermi's Q3 2026 earnings release, 10-Q, prepared remarks and investor presentation (all Nov. 12, 2026), Fermi's own releases naming each firm, trade press and local news, on Nov. 21, 2026. We kept each firm a Fermi release, Fermi's SEC filing or trade press names on this campus. Some firms are suppliers or operators rather than site trades, and each row says which. The $1.7 billion is Fermi's own figure for money spent so far, not a budget or a contract. Left out: Fermi and its subsidiaries (the owner), the reported customer and the former tenant, the landowner, lenders, law firms, the seller of used turbines, the city water supplier, Hillcore (a framework deal to finance and own a power plant on the campus, not yet final), GE Vernova (it made the three 6B turbines, but Fermi bought them used, so we cannot say it was paid) and a heavy-haul firm seen only in photos. Contract values are not published for most firms. Phones are each firm's own main line from its own site; we found lines for Energy Transfer and Westinghouse only, so the rest carry their websites. First published Nov. 21, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 21, 2026- Fermi Q3 2026 earnings release (Nov. 12, 2026)
- Fermi Inc. Form 10-Q for Q3 2026 (filed Nov. 12, 2026)
- Fermi Q3 2026 prepared remarks (Nov. 12, 2026)
- Fermi Q3 2026 investor presentation (site stats as of Oct. 31, 2026)
- Fermi release: Primoris to build balance of plant (June 30, 2026)
- Pipeline & Gas Journal: Primoris wins EPC contract for Fermi (June 30, 2026)
- Fermi release: TSK early works engineering (June 25, 2026)
- Fermi release: CBRE to operate its first data center (Sept. 24, 2026)
- Fermi: NAES to operate the natural gas fleet (Sept. 28, 2026)
- Fermi: second Siemens F-class turbine arrives (Oct. 2026)
- Fermi release: firm gas supply from Energy Transfer (Oct. 2025)
- Fermi release: Hyundai E&C partnership (Feb. 11, 2026)
- World Nuclear News: Fermi enlists Korean firms (Oct. 28, 2025)
- Amarillo Tribune: groundwater district asks Fermi for more detail (Nov. 20, 2026)
- Crypto Briefing, citing the Financial Times: Amazon and Fermi's 600 MW deal (Nov. 14, 2026)
- Bisnow: Fermi, Rick Perry's energy REIT, files for IPO
- Blackridge Research: Project Matador profile (TensorWave lease)