What is Fluidstack building near Harlingen, Texas?
Fluidstack is building an AI data center campus at 27751 FM 106 in unincorporated Cameron County, Texas. The site is east of Valley International Airport and outside Harlingen city limits. Fluidstack says the campus covers more than 1,100 acres.
Fluidstack announced on Sept. 10, 2026 that it had started work on the first phase, a $4 billion job (KRGV). That is the company's figure. Every Cameron County permit on the site shows $0, and we found no Texas Department of Licensing and Regulation (TDLR) registration for the project. Fluidstack says phase one will conclude by mid-2028.
Which permits has Cameron County issued for the Fluidstack data center?
HDR filed two permits for new non-residential buildings on the Fluidstack campus, on Sept. 28 and Oct. 5, 2026. Both are still in review on the county's permit portal. Fluidstack is the owner on both.
Cameron County issued two concrete slab on grade permits on Oct. 13, 2026, with Alston Construction and Melden & Hunt as agents. Alston filed four permits for temporary structures on Oct. 12, 2026, and those are still in review too.
How much power and water will the Fluidstack campus use?
Fluidstack has "reserved" 1.5 GW of power from AEP Texas for the $4 billion first phase, per the Valley Morning Star (Sept. 25, 2026). The paper says the company has considered an expansion that "could include an 'incremental 5.85GW' between 2029 to 2033," and a second project near Rio Hondo.
Fluidstack says it will buy its power from AEP Texas. East Rio Hondo Water Supply Corporation will supply the water for the campus's closed-loop cooling (KRGV).
What did Harlingen decide about the Fluidstack data center?
Harlingen city commissioners tabled Fluidstack's drainage request on Sept. 2, 2026 (KRGV). The deal pitched to the city included a $20 million community benefits agreement plus $7 million in donated drainage improvements near Valley International Airport, per the RGV Business Journal.
The RGV Business Journal reported on Nov. 4, 2026 that the deal fell through in recent weeks, and that it could be revived if a community benefits agreement and interlocal contract are approved. The campus is outside the city, so the county issues its permits.
Which firms are on the Fluidstack Harlingen data center?
Cameron County's permits name Alston Construction as general contractor, HDR as the applicant on the building permits, and Melden & Hunt as an agent. They name Coonrod Electric Company as the electrical contractor and RK Mechanical as the mechanical contractor.
RMCI's tie is jobsite signage only: its name is on the signs with Alston's, and no permit we read names it. A Cardinal Strategies stormwater (SWPPP) notice is posted on the jobsite sign. AEP Texas supplies the power and East Rio Hondo Water Supply Corporation the water. 9 firms in all are on the list below.
How do the ways into the Fluidstack Harlingen data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Fluidstack data center near Harlingen | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Fluidstack Harlingen data center?
| Electrical distributors and gear reps | Coonrod Electric Company, the electrical contractor on both building permits, and AEP Texas on power. |
|---|
| Mechanical, HVAC and plumbing reps | RK Mechanical, the mechanical contractor on both building permits. |
|---|
| Concrete, site and stormwater suppliers | Alston Construction on the slab and site work, and Cardinal Strategies on stormwater. |
|---|
What should you do next on the Fluidstack Harlingen data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Fluidstack data center at 27751 FM 106 in Cameron County.
Questions people ask about the Fluidstack Harlingen data center
How much is the Fluidstack data center near Harlingen?
Fluidstack says the first phase is a $4 billion job. That is the company's figure, not a contract. Every Cameron County permit on the site shows $0, and we found no TDLR registration. Fluidstack has not given a cost for the whole campus.
Who is building the Fluidstack data center in Cameron County?
Alston Construction is the general contractor on the county's temporary structure permits and an agent on the slab permits. RMCI's name is on the jobsite signs with Alston's. 9 firms are named on the job, listed above.
Where is the Fluidstack data center?
It is at 27751 FM 106, with a Harlingen mailing address, in unincorporated Cameron County, Texas. It sits east of Valley International Airport, outside Harlingen city limits, between Harlingen and Rio Hondo.
Does the Fluidstack data center have a building permit?
Not yet. HDR filed two building permits on Sept. 28 and Oct. 5, 2026, and both are in review. The county issued two concrete slab permits on Oct. 13, 2026.
How much power will the Fluidstack campus use?
Fluidstack has 1.5 GW reserved from AEP Texas for the first phase, per the Valley Morning Star, and says it "could use less." The paper says an expansion could add an "incremental 5.85GW" from 2029 to 2033.
Where will the Fluidstack data center get its water?
East Rio Hondo Water Supply Corporation will supply the water for its closed-loop cooling (KRGV). Fluidstack says the tanks are filled once and reuse the same water.
How many jobs will the Fluidstack data center create?
Fluidstack says more than 2,500 construction jobs and several hundred permanent jobs.
Did Harlingen approve the Fluidstack data center?
No. The campus is outside the city. Harlingen tabled Fluidstack's drainage request on Sept. 2, 2026 (KRGV), and the RGV Business Journal reported on Nov. 4, 2026 that the deal with the city had fallen through.
Does Fluidstack get a tax break in Cameron County?
No. KRGV reported the project comes with no local property tax breaks, and Fluidstack says it did not ask for any.
When will the Fluidstack data center be finished?
Fluidstack says phase one will conclude by mid-2028. The building permits are still in review.
How we built this list
We read all 10 Cameron County permit cases at 27751 FM 106 on the county's public EnerGov portal on Nov. 19, 2026, searched the TDLR project registry (no match), and read Fluidstack's project site, KRGV, the Valley Morning Star and the RGV Business Journal. We kept each firm a permit, the jobsite signs or the company names on this campus. RMCI and Cardinal Strategies come from jobsite signs in KRGV's video stills, not permits. Left out: the owner, a land entity on two permits, land sellers, public agencies, trucks seen near the site with no stated work, and individuals on the permits. Phones are each firm's own main line from its own site; HDR's is its national line. Alston, Coonrod Electric and RK Mechanical list no main line we could confirm, so we give their websites only. First published Nov. 19, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 19, 2026- Cameron County Citizen Self Service permit records (EnerGov), 27751 FM 106, read Nov. 19, 2026
- KRGV: Fluidstack breaks ground on $4 billion data center campus in Cameron County (Sept. 10, 2026)
- Valley Morning Star via Yahoo: Fluidstack 'reserving' 1.5GW for data center (Sept. 25, 2026)
- KRGV: Harlingen tables Fluidstack data center drainage request (Sept. 3, 2026)
- Fluidstack: Cameron County project site (read Nov. 19, 2026)
- RGV Business Journal: Fluidstack drainage agreement (Nov. 4, 2026)
- KRGV: Concerns arise over data center's water and power usage in Cameron County (Sept. 12, 2026)