Who's building Google's data center in Cedar Rapids, Iowa

Cedar Rapids now puts Google's data center campus at more than $3.5 billion, six times Google's first pledge, and Mortenson just filed a $124.8 million cooling-plant addition.

By Porter Stanley. Updated .

Google is building a six-building data center campus at 5800 Edgewood Road SW in the Big Cedar Industrial Center in Cedar Rapids, Linn County, Iowa. The city estimates the total investment at $3.5 billion or more, about six times Google's $576 million minimum commitment. The city's issued building permits add up to about $1.66 billion, the sum, with $696 million more in review. Mortenson is the general contractor. 10 firms are named on the job; the list below has all 10.

$3.5B+City's estimate of Google's total investment
$1.66BIssued city building permits (the sum)
$124.8MCooling-plant addition filed Oct. 26, 2026
10Firms named on the job

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 10 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 10 firms on the Google Cedar Rapids data center?

We list the 10 firms named on Google's Cedar Rapids data center campus, one row each, grouped by kind of firm, with where each name comes from.

1Permit on the recordFeb 28, 2025

Mortenson

General contractor and permit applicant for the whole campus: the shells and data halls of Buildings 1, 2 and 3, Building 4, the water pre-treatment buildings and the new cooling-plant addition on Google's Cedar Rapids data center campus in Cedar Rapids, Linn County, IA

Google's Cedar Rapids data center campus (Paysage), 5800 Edgewood Rd SW, Big Cedar Industrial Center, Cedar Rapids (Linn County), IA

Building permit BLDC-009194-2024, $400 million for the Building 1 shell, issued Feb. 28, 2025, up to BP-008510-2026, a $124.8 million cooling-plant addition filed Oct. 26, 2026 and still in review; the campus's issued building permits add up to about $1.66 billion, the sum

Work: General contractor and permit applicant for the whole campus: the shells and data halls of Buildings 1, 2 and 3, Building 4, the water pre-treatment buildings and the new cooling-plant addition

Who to call: Mortenson
Mortenson Iowa office line
(Coralville, IA)
(319) 338-2180

The opportunity: City permit BLDC-009194-2024: 'CONSTRUCTION OF A NEW 287,547 S.F. COMMERCIAL BUILDING "PAYSAGE DATA CENTER"' Contractor: Mortenson Construction; Property Owner: HEAVISIDE LLC. Permit BP-008510-2026 (applied Oct. 26, 2026, $124,840,789): 'CONSTRUCTION OF A NEW 600,000 S.F. ADDITION TO EXISTING COMMERCIAL BUILDING "EWD2A PAYSAGE" FOR COOLING PLANTS.' Permits list the project office at 3215 64th Ave SW, Suite 200, Cedar Rapids. Minneapolis headquarters: (763) 522-2100.

2Permit on the recordMay 19, 2026

Tri-City Electric Co.

Electrical contractor on the data hall fit-outs of Buildings 1, 2 and 3, plus Building 2 and 3 shell work and the substation control building on Google's Cedar Rapids data center campus in Cedar Rapids, Linn County, IA

Google's Cedar Rapids data center campus (Paysage), 5800 Edgewood Rd SW, Big Cedar Industrial Center, Cedar Rapids (Linn County), IA

Electrical permit EL-003762-2026, $150,024,068 for the Building 3 data hall, issued May 19, 2026; EL-001770-2026, $141,851,802 for the Building 2 data hall, issued Mar. 25, 2026; about $145 million for the Building 1 interior

Work: Electrical contractor on the data hall fit-outs of Buildings 1, 2 and 3, plus Building 2 and 3 shell work and the substation control building

Who to call: Tri-City Electric Co.
Tri-City Electric Co. office line
(Davenport, IA)
(563) 322-7181

The opportunity: City permit EL-003762-2026: '**BLDG 3 DATA HALL**INTERIOR STRUCTURE TO INCLUDE ALL MECHANICAL, ELECTRICAL, PLUMBING, CARPENTY, FINISHES' Electrical Contractor: TRI-CITY ELECTRIC COMPANY, 6225 N Brady St, Davenport, IA. Des Moines office: (515) 288-7181.

3Permit on the recordNov 16, 2026

Baker Group

Mechanical, plumbing and low-voltage contractor across the campus: above-ground mechanical for Building 1 and EWD2A, plumbing for EWD2A and EWD3A, low-voltage systems, the water meter and water pre-treatment buildings on Google's Cedar Rapids data center campus in Cedar Rapids, Linn County, IA

Google's Cedar Rapids data center campus (Paysage), 5800 Edgewood Rd SW, Big Cedar Industrial Center, Cedar Rapids (Linn County), IA

Mechanical permit ME-009008-2026, $1,404,200 for the water pre-treatment building, issued Nov. 16, 2026, one of the three newest issued permits on the campus; ME-006209-2025, $8,925,907 for Building 1 mechanical, issued Sept. 18, 2025

Work: Mechanical, plumbing and low-voltage contractor across the campus: above-ground mechanical for Building 1 and EWD2A, plumbing for EWD2A and EWD3A, low-voltage systems, the water meter and water pre-treatment buildings

Who to call: Baker Group
Baker Group main line
(Ankeny, IA)
(855) 262-4000

The opportunity: City permit ME-009008-2026: 'EWD2A - Above-Ground Mechanical Work for WPT (Water Pre-Treatment) Building Construction' Mechanical Contractor: BAKER GROUP, 1600 SE Corporate Woods Dr, Ankeny, IA. Also ME-009007-2026 ($1,178,344) and plumbing permit PL-009010-2026 ($175,000), issued the same day. Permits also list a Cedar Rapids office at 1025 Kirkwood Pkwy SW.

What is Google building in Cedar Rapids, Iowa?

Google is building a data center campus at 5800 Edgewood Road SW, in the Big Cedar Industrial Center on the southwest side of Cedar Rapids. City permits call it Paysage. Heaviside LLC is the owner on every campus permit that names one. The city's 2024 development agreement for Google's project is with Heaviside LLC.

The plans call for six buildings. Building 1 is a 287,547 sq ft building. Buildings 2 and 3 have shells of about 165,561 sq ft each, and Building 4 was filed in April 2026. Permits also cover water pre-treatment buildings, a fire pump building, a substation control building, a warehouse and an office building called The Hub.

How much is the Google Cedar Rapids data center?

Cedar Rapids estimates the total investment at $3.5 billion or more. That is the city's estimate, not a Google figure. Google's minimum commitment, set in 2024, was $576 million, so the city's estimate is about six times that.

The city's issued building permits for the campus add up to about $1.66 billion, the sum. The biggest is $400 million for the Building 1 shell. The data halls in Buildings 2 and 3 carry $324 million permits each. Filings still in review add $696 million more, including the Building 4 shell and data hall. Each permit value is what was declared to the city for that work, not Google's total spend.

How far along is the Google Cedar Rapids data center?

Building 1 got a temporary occupancy permit in June 2026, through an indemnification agreement approved by the airport commission and the city council. The data halls in Buildings 2 and 3 were permitted in January and April 2026, with electrical fit-outs of about $142 million and $150 million. Building 4 is filed and still in review.

Building 1 got that permit even though the impacts of Buildings 1 through 6 "have not been fully identified," including possible water vapor plumes from its cooling, near the Eastern Iowa Airport. At the same council meeting, a council member floated a moratorium on future data centers.

The newest filing came on Oct. 26, 2026: Mortenson applied for a 600,000 sq ft cooling-plant addition worth $124.8 million. The newest issued permits went to Baker Group on Nov. 16, 2026: two for mechanical work on the water pre-treatment buildings and one for plumbing in Building 2.

Who is building the Google Cedar Rapids data center?

Mortenson is the general contractor and the applicant on the campus building permits, from the Building 1 shell in 2025 to the cooling-plant addition filed last month. Permits list its project office on 64th Avenue SW in Cedar Rapids.

Olsson was the civil engineer on the 2024 erosion control permit for "Project Paysage Phase 1." DLR Group filed for the campus warehouse, and Cushing Terrell filed for The Hub.

Which trade firms are on the Google Cedar Rapids data center?

Tri-City Electric holds the electrical permits for the data hall fit-outs in Buildings 1, 2 and 3; the Building 3 permit alone is about $150 million. Nelson Electric of Cedar Rapids has the site entrance, security, lighting and service work.

Baker Group has the mechanical, plumbing and low-voltage work across the campus. F.E. Moran Fire Protection has the fire pump building, and Dave Schmitt Construction holds the campus sewer permit. Alliant Energy developed the industrial park and serves the campus with power. 10 firms in all are on the list below.

How do the ways into the Google Cedar Rapids data center compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Google's Cedar Rapids data centerEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Google Cedar Rapids data center?

Electrical distributors and gear repsTri-City Electric on the data hall fit-outs, where the Building 3 electrical permit alone is about $150 million, and Nelson Electric on site power and lighting.
Mechanical, HVAC, plumbing and fire repsBaker Group on the mechanical, plumbing and low-voltage work, F.E. Moran on the fire pump building, with a $124.8 million cooling-plant addition just filed.
Concrete, site and building material suppliersMortenson on every building, Dave Schmitt Construction on the site sewer, and Olsson, DLR Group and Cushing Terrell on design.

What should you do next on the Google Cedar Rapids data center?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Google's Paysage data center on Edgewood Road SW in Cedar Rapids.

Questions people ask about the Google Cedar Rapids data center

How much is the Google Cedar Rapids data center?

Cedar Rapids estimates Google's total investment on the campus at $3.5 billion or more. That is the city's estimate, not a Google figure. Google's minimum commitment was $576 million. The city's issued building permits add up to about $1.66 billion, the sum, with $696 million more still in review.

Who is building the Google data center in Cedar Rapids?

Mortenson is the general contractor and applicant on the campus building permits. Tri-City Electric has the data hall electrical work, and Baker Group has the mechanical and plumbing. 10 firms are named on the job, listed above.

Who owns the Google Cedar Rapids data center?

The owner on every campus permit that names one is Heaviside LLC. In 2024 the city announced Google as the company behind the project and signed its development agreement with Heaviside LLC.

Where is the Google Cedar Rapids data center?

It is at 5800 Edgewood Road SW, in the Big Cedar Industrial Center on the southwest side of Cedar Rapids, Linn County, Iowa.

How big is the Google Cedar Rapids data center?

City plans call for six buildings. Building 1 is a 287,547 sq ft building. Buildings 2 and 3 have shells of about 165,561 sq ft each, and a 600,000 sq ft cooling-plant addition was filed in October 2026.

Is Google's Cedar Rapids data center open?

Building 1 got a temporary occupancy permit in June 2026. Buildings 2 and 3 have $324 million data hall permits each, and Building 4 is filed and still in review.

Why is there a fight over the Google Cedar Rapids data center?

Building 1 got its temporary occupancy even though the impacts of Buildings 1 through 6 "have not been fully identified," including possible water vapor plumes from its cooling, near the Eastern Iowa Airport. At the same council meeting, a council member floated a moratorium on future data centers.

What is the newest permit on the Google Cedar Rapids campus?

Mortenson filed a $124.8 million permit on Oct. 26, 2026 for a 600,000 sq ft cooling-plant addition. The newest issued permits went to Baker Group on Nov. 16, 2026: two mechanical permits for the water pre-treatment buildings and a plumbing permit.

How many jobs will the Google Cedar Rapids data center create?

More than 1,200 construction workers and about 100 operations staff once it opens, according to 2025 reporting. The city's deal requires at least 31 full-time jobs.

Is this the same as QTS Cedar Rapids or Google's Palo site?

No. QTS is building its own data center campus in Cedar Rapids with different firms, and Google's proposed Palo site is a separate project. This page covers only Google's Big Cedar campus.

What happens next on the Google Cedar Rapids data center?

The Building 4 shell and data hall, the cooling-plant addition, The Hub and a warehouse are still in city review. We'll update this page when a new permit or firm appears.

How we built this list

We searched the City of Cedar Rapids public EnerGov permit portal on Nov. 20, 2026 for the 65 records at 5800 Edgewood Rd SW and opened each case by number. We also read the city's 2024 release and its July 2026 data center one-sheet, Alliant Energy's release and the news, and kept each firm a city permit or the firm's own release names on this campus. Trades come from each permit's own contractor field, except Dave Schmitt Construction's (its line of work) and Alliant Energy's (its own release). Record dates are the issue date, or the filing date for permits still in review. The $1.66 billion and $696 million are our sums of the city's declared permit values for building permits, not Google's spend; trade permits are left out of the sum because they may overlap the building scopes. Left out: three firms that worked only on the remodel of the project's field office on 64th Avenue SW, a permitting consultant on a floodplain filing whose role we could not confirm, the owner (Heaviside LLC), the land seller's landlord, an equipment rental firm, government bodies, individuals, and every firm on the separate QTS Cedar Rapids campus. Phones are each firm's own main or office line from its own site; Dave Schmitt's comes from the city permit because its site, under construction, shows none. Mortenson's line is its Iowa office in Coralville, Baker Group's is its main line, F.E. Moran's is its Champaign, Illinois fire protection office named on the permit, and DLR Group's is its Omaha office. First published Nov. 20, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 10 firms, free

All 10 firms on the Google Cedar Rapids data center

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.