Google is building its Columbus data center campus on the former Hartman farm at 225 Rathmell Rd, on the city's far south side: the city's permits since 2022 state about $1.16 billion of work across 5 data center buildings (CLB1 to CLB5), 2 support buildings, an office hub and substations. By the math on a typical data center split (Dgtl Infra), about $460 million of that is electrical, about $170 million cooling and pipe, about $170 million the building shells and about $230 million fit-out. The permits name 27 firms, led by Saturn Partners on the data center buildings, ESI on the electrical and S. A. Comunale on sprinklers and pipe. Of those, 10 hold a permit open today with new work since December 2025; the list below has those 10 firms buying now, each with a phone.
$1.16BStated on the city's permits since 2022
~$460MPower and wiring, by the math
5Data center buildings (CLB1 to CLB5)
10Firms buying now
Get all 10 firms and who to call
Each one with who's on the record and the date. Free: your email sets up your free account.
We list the 10 firms buying for this job now, one row each: the contractors with a permit open on Nov. 13, 2026 and new work since December 2025 (a City of Columbus permit with status 'Permit Issued' on Nov. 13, 2026, issued since Dec. 1, 2025, or, for Saturn Partners, its open permit for the 5th data hall (ALTC2530787, Oct. 2025) on a building whose trade permits were all issued since Dec. 2025). Every row has a phone.
1Open permit nowOct 9, 2025
Saturn Partners (a Smoot Construction and Turner joint venture)
Building and foundations at Google's Columbus data center campus, 225 Rathmell Rd: 18 city permits
Google's data center campus at 225 Rathmell Rd, Columbus, Ohio
18 City of Columbus permits on the campus, the first 2022-03-11, the newest 2025-10-09
Work: Building and foundations
Who to call: Saturn Partners (a Smoot Construction and Turner joint venture)
Saturn Partners (a Smoot Construction and Turner joint venture) Columbus office line (Smoot Construction)
The opportunity: Named as the licensed contractor on 18 City of Columbus permits at 225 Rathmell Rd since 2022. Work: a joint venture that includes Smoot Construction and Turner; general contractor on the data center buildings (13 permits on CLB1 to CLB5), plus the guard shack, the booster pump station and the crew trailers.
2Open permit nowJun 11, 2026
3C Industries
Building and foundations at Google's Columbus data center campus, 225 Rathmell Rd: 3 city permits
Google's data center campus at 225 Rathmell Rd, Columbus, Ohio
3 City of Columbus permits on the campus, the first 2024-12-11, the newest 2026-06-11
The opportunity: Named as the licensed contractor on 3 City of Columbus permits at 225 Rathmell Rd since 2022. Work: general contractor on the campus office hub, phases 2 and 3, and the new Hub 2 office.
3Open permit nowJul 9, 2026
ESI Electrical Contractors
Electrical at Google's Columbus data center campus, 225 Rathmell Rd: 26 city permits
Google's data center campus at 225 Rathmell Rd, Columbus, Ohio
26 City of Columbus permits on the campus, the first 2022-03-11, the newest 2026-07-09
The opportunity: Named as the licensed contractor on 26 City of Columbus permits at 225 Rathmell Rd since 2022. Work: electrical for every data center building (CLB1 to CLB5), CLB10 and CLB11, the later substations, the booster pump station, the guard shack and the kitchen trailer, plus fire alarms on CLB1.
Where does the money go on Google's Columbus campus?
Google's Columbus data center campus is on the former Hartman farm at 225 Rathmell Rd, on Columbus's far south side. Franklin County lists the 480-acre parcel as a data center, owned by Magellan Enterprises LLC with its tax bill going to Google LLC, and the city's permits name Google on the work. Since 2022 the city has issued 139 permits there: 5 data center buildings (CLB1 to CLB5; 'Project Cyprus is the 5th Data Center on the site'), 2 buildings that support the servers (CLB10 and CLB11), an office hub, substations and a booster pump station.
Counting each building once, at its largest permit value, the permits state $1,155,733,924. No one has published the campus's own split, so we used Dgtl Infra's typical split for a new data center, at the low end of each range: 40 percent electrical, 15 percent cooling and mechanical, 15 percent the building shell and 20 percent fit-out. That is about $460 million, $170 million, $170 million and $230 million. Google says it has invested $20 billion in Ohio since 2019, servers included.
Who gets what?
Power and wiring, about $460 million by the math: 5 electrical firms. ESI is on 26 permits: every data center building, CLB10 and CLB11, the later substations and the pump station; Gibson Electrical, Denier Electric and Universe Electric wired the office hubs, and Michels Power the first substation.
Cooling and pipe, about $170 million: 9 plumbing, HVAC and refrigeration firms, led by S. A. Comunale (22 permits, with sprinklers), Barnett Mechanical (13) and Upland Mechanical (10).
The shells, about $170 million: 6 builders. Saturn Partners, a joint venture that includes Smoot Construction and Turner, holds 13 building permits on CLB1 to CLB5 and 5 more on the guard shack, trailers and pump station; Turner Construction built CLB10 and CLB11; 3C Contracting and TW Constructors the office hub; Keeley and George J. Igel the substation foundations. Fire alarms and sprinklers: 5 more firms, led by TD4 Electric on 11 fire alarm permits.
Which firms are on the permits?
We read every City of Columbus permit at 225 Rathmell Rd since 2022 (139) and each record's page, which names the licensed contractor. They name 27 firms: 6 builders, 5 electrical, 9 plumbing and HVAC, 5 fire alarm and sprinkler firms, a demolition firm and a tent rental. The list below holds the 10 of them buying now.
The open permits in 2026 are for CLB5 (the 5th data hall) and the Hub 2 office; CLB10 and CLB11 are finished. The firms on CLB5 and Hub 2 are on site now.
How do the ways into Google's Columbus campus compare?
Way in
What it is
Best for
What you get
The limit
The firms on the permits
A call to the firm's office, asking for the Google Columbus team
Every supplier, distributor and sales rep
A conversation with a firm already working on the campus
Start with the firms on CLB5 and the Hub 2 office
Who should go after this campus?
Electrical distributors and gear reps
About $460 million of power and wiring by the math, with 5 electrical firms on the permits.
HVAC, plumbing and cooling reps
About $170 million of cooling and pipe, with 9 firms on the permits.
Building material, fire and safety reps
6 builders on the shells and 5 fire alarm and sprinkler firms.
What should you do next on Google's Columbus campus?
Pick the firms whose permits match what you sell, and call them this week.
Ask for the team on Google's Rathmell Rd campus in Columbus.
Questions people ask about Google's Columbus data center
Where is Google's Columbus data center?
At 225 Rathmell Rd on Columbus's far south side, on the former Hartman farm. Franklin County lists the 480-acre parcel as a data center, owned by Magellan Enterprises LLC with its tax bill going to Google LLC.
How much is Google spending in Columbus?
The city's permits since 2022 state about $1.16 billion of construction on the campus. Google says it has invested $20 billion in Ohio since 2019, across its New Albany, Columbus and Lancaster campuses, servers included.
Who is building Google's Columbus data center?
Saturn Partners (a joint venture that includes Smoot Construction and Turner) holds the building permits on the 5 data center buildings and Turner Construction on CLB10 and CLB11; ESI does the electrical. In all, the permits name 27 firms. The full list is above.
How we built this list
We read every City of Columbus building permit at 225 Rathmell Rd from March 2022 to Nov. 13, 2026 (139, from the city's permit layer) and each record's page on the city portal, which names the licensed contractor. Firms are the licensed contractors on those records; a firm's name variants are counted once, and Upland Mechanical and Poole & Kent, sister EMCOR firms on one city license, are listed separately. Permits at other Rathmell Rd addresses (homes and a church) are left out. The campus value counts each building once, at its largest stated permit value, because a building's foundation, shell and fit-out permits restate its value: CLB1 (phases 1 and 2) $250.00M; CLB2 $250.00M; CLB3 $110.00M; CLB4 $110.00M; CLB5 $200.00M; CLB10 $100.00M; CLB11 $100.00M; Office hub phase 1 $7.68M; Office hub phase 2 $0.00M; Office hub phase 3 $5.00M; Hub 2 office $13.00M; CLB1A substation $1.50M; CLB2A substation $1.70M; Booster pump station $5.00M; Guard shack $0.50M; Construction trailers $0.50M; Office trailers $0.50M; Kitchen trailer $0.35M. The dollar split is the math on that total and Dgtl Infra's typical data center split, at the low end of each range. The owner is from the Franklin County Auditor. Phones come from each firm's own website where we found one; otherwise the row gives the phone on the city's license record and says so. First published Nov. 13, 2026. We'll update this page as Columbus issues new permits on the campus.
Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.