Who's building Google's reported $29 billion data center near Amarillo

Google's reported $29 billion data center in Claude, Texas is the first test of a new Texas law: in a grid emergency, it must cut power within 30 minutes.

By Porter Stanley. Updated .

Crusoe is building Google's Goodnight data center campus in Claude, Texas, in Armstrong County outside Amarillo: six single-story buildings, about 4.2 million square feet, on more than 1,100 acres (Crusoe; Texas TDLR; Hoffman Construction). The campus is reported at about $29 billion (Construction Review Online), a figure neither Crusoe nor Google has stated. The hard number is $4.08 billion of construction estimates on nine Texas state building registrations at the site. Ground broke in June 2025, and more than 5,500 workers are on site each day (Crusoe). 18 firms are named on the job; the list below has all 18.

$4.08BTexas building registrations at the site (TDLR)
5,500+Workers on site a day (Crusoe)
6Data center buildings
18Firms named on the job

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 18 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 18 firms on Google's Goodnight campus?

We list the 18 firms named on Google's Goodnight campus, one row each, with where each name comes from.

1Named in the newsNov 17, 2026

DPR Construction

Builder, in a joint venture with Hoffman Construction (the Llano site sign), and a prime in Crusoe's multi-prime team with Rosendin and Southland on Google's Goodnight campus

Google's Goodnight data center campus (Project Llano), developed by Crusoe, 10001 Lima Road, Claude, Armstrong County, Texas

Work: Builder, in a joint venture with Hoffman Construction (the Llano site sign), and a prime in Crusoe's multi-prime team with Rosendin and Southland

Who to call: DPR Construction
DPR Construction office line
(Redwood City
CA (Texas Contractor lists Santa Clara, CA))
(214) 979-9900

The opportunity: Owner Crusoe Energy has assembled a team that includes DPR Construction, Southland Industries, and Rosendin to develop two data centers in Abilene and Amarillo/Claude, Texas.

2Latest recordNov 17, 2026

Hoffman Construction Company

Builder, in a joint venture with DPR Construction (the Llano site sign) on Google's Goodnight campus

Google's Goodnight data center campus (Project Llano), developed by Crusoe, 10001 Lima Road, Claude, Armstrong County, Texas

Work: Builder, in a joint venture with DPR Construction (the Llano site sign)

Who to call: Hoffman Construction Company
Hoffman Construction Company office line
(Lake Oswego, OR)
(503) 221-8811

The opportunity: Located in Claude, Texas, this expansive next-generation data center will support the increasing demand for digital connectivity and the future of AI.

3Latest recordNov 17, 2026

Cache Valley Electric (CVE)

Full-scope mission critical electrical construction, commissioning and QA/QC on the hyperscale campus in Claude, TX (18-36 month duration) on Google's Goodnight campus

Google's Goodnight data center campus (Project Llano), developed by Crusoe, 10001 Lima Road, Claude, Armstrong County, Texas

Work: Full-scope mission critical electrical construction, commissioning and QA/QC on the hyperscale campus in Claude, TX (18-36 month duration)

Who to call: Cache Valley Electric (CVE)
Cache Valley Electric (CVE) office line
(Logan, UT)
(469) 844-5760

The opportunity: Located in Claude, Texas, this next-generation data center is part of the critical digital infrastructure powering cloud computing, AI, and the connected future. CVE is delivering full-scope mission critical electrical construction on one of the most significant projects in the country right now.

What is Crusoe building for Google near Amarillo?

Crusoe, based in Denver, said on Sept. 28, 2026 that it is the developer of Google's data center campus under construction in Armstrong County, outside Amarillo (Crusoe). The site is 10001 Lima Road in Claude. Texas building registrations call it Project Llano and list six single-story data center buildings: two of about 485,000 square feet and four of 805,380 square feet each (Texas TDLR). Hoffman Construction's own page calls it a site of more than 1,100 acres and more than 1 gigawatt.

Ground broke in June 2025, and more than 5,500 skilled workers are on site each day (Crusoe). KFDA NewsChannel 10 reports that Google gets the first buildings in early 2027 and that construction is done by the end of 2027.

The campus is wired straight to Serena's Goodnight 1 wind farm next door, 265.5 MW and running (Crusoe). Crusoe Energy Systems also filed in January 2026 for a 933 MW gas power plant for the data center buildings, and that permit is still pending at TCEQ (TCEQ).

How much is the Goodnight campus?

The campus is reported at about $29 billion (Construction Review Online). That number is an outside estimate, not a cost Crusoe or Google has stated.

The hard number is on the state's records. Nine Texas TDLR building registrations at 10001 Lima Road add up to $4.08 billion of estimated construction: $292 million each for the shells of Buildings 1 and 2, and $500 million each for the inside work on Buildings 1 and 2 and for Buildings 3, 4, 5 and 6, plus one more $500 million filing for Building 3 (Texas TDLR). Those are builders' estimates for the work, not the total cost of the campus.

Who gets what?

No one has published the campus's trade split. By the math on Turner & Townsend's data center cost index, about $2 billion of the $4.08 billion in Texas building registrations is electrical work and about $1.3 billion is pipes, heat and air. That math uses only the $4.08 billion on the state registrations, so the real work is likely bigger.

Rosendin says 60% of the electrical gear for Crusoe's West Texas campuses was built off-site by Modular Power Solutions, its company in McKinney (Texas Contractor). That is work a supplier can chase in Texas, not only on the site.

Which firms are on the job?

The project sign at the site names a joint venture of DPR Construction and Hoffman Construction as the builder, with Rosendin and Southland Industries, the design-build electrical and mechanical contractors Texas Contractor reports for Crusoe's campuses (KVII; Texas Contractor). HKS and AO are the design firms on the state building registrations, and the sign adds AlfaTech, Kimley-Horn, BW Design Group, Fire & Risk Alliance and dlb associates. Cache Valley Electric is hiring for the campus on its own page.

State stormwater filings name Overland Contracting, a Black & Veatch company, on the Goodnight power plant beside the campus, and PACK Power on the Goodnight wind substation expansions (TCEQ, via EPA).

On the power side, the Public Utility Commission of Texas names Oncor as the transmission provider and Greenbelt Electric Cooperative as the distribution provider for the campus load wired to the wind farm, and Serena owns the wind farm (Crusoe). The commission made the campus the first test of Texas's new Senate Bill 6 rules for big loads wired to a power plant: in a grid emergency, it must cut its power within 30 minutes (Latitude Media). 18 firms in all are on the list below.

How do the ways into Google's Goodnight campus compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Google's Goodnight campusEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after Google's Goodnight campus?

Electrical distributors and gear repsRosendin, Cache Valley Electric and Modular Power Solutions on more than 1 gigawatt of buildings.
Mechanical, cooling and pipe repsSouthland Industries, the design-build mechanical contractor, on six buildings.
Building material and site suppliersDPR Construction and Hoffman Construction on about 4.2 million square feet over 1,100+ acres.

What should you do next on Google's Goodnight campus?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Google's Goodnight campus.

Questions people ask about Google's Goodnight campus

How much is Google's Goodnight data center?

It is reported at about $29 billion (Construction Review Online), an outside estimate; Crusoe and Google have not stated a cost. Nine Texas state building registrations at the site add up to $4.08 billion of estimated construction.

Who is building Google's data center near Amarillo?

Crusoe is the developer. DPR Construction, Rosendin and Southland Industries are its builders for the Amarillo/Claude campus (Texas Contractor), and Hoffman Construction is hiring for it. 18 firms are named in all, listed above.

Where is the Goodnight data center?

10001 Lima Road in Claude, Armstrong County, Texas, outside Amarillo (Texas TDLR).

When will the Goodnight campus be done?

KFDA NewsChannel 10 reports Google gets the first buildings in early 2027 and construction is done by the end of 2027.

How many people work on the Goodnight site?

More than 5,500 skilled workers are on site each day (Crusoe, Sept. 28, 2026).

Where does the campus get its power?

It is wired straight to Serena's Goodnight 1 wind farm, 265.5 MW (Crusoe). A 933 MW gas plant for the data center buildings is pending at TCEQ.

How we built this list

We read Crusoe's Sept. 28, 2026 release, KFDA NewsChannel 10, Construction Review Online, Texas Contractor, KVII's photo of the project sign at the site (Nov. 24, 2025), TCEQ stormwater authorizations, the nine Texas TDLR building registrations at 10001 Lima Road, the Public Utility Commission of Texas order in Docket 58881, TCEQ's air permit notice and the contractors' own pages, and kept each firm a record or page names on this campus (read Nov. 17, 2026). The project sign at the site names the DPR Construction and Hoffman Construction joint venture, Rosendin, AlfaTech, Southland, HKS, AO, Kimley-Horn, BW Design Group, Fire & Risk and dlb; three more logos on it could not be read, so they are not listed. Texas Contractor also names Modular Power Solutions for Crusoe's West Texas campuses, and Cache Valley Electric's page names Claude, Texas but not the owner. Firms seen only on job boards are left out, and so are the individuals on the state filings. No county or city building permits were found. The $29 billion is an outside estimate; the trade split is the math on Turner & Townsend's published data center shares, applied to the $4.08 billion on the state registrations, where shell and inside-work filings cover the same two buildings and one filing may repeat Building 3; a tenth registration (Llano Building 4, July 2026, $500 million) looks like a re-filing and is not counted. Phones are each firm's main office line; Serena's was not found. First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 18 firms, free

All 18 firms on Google's Goodnight campus

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.