What is Google building in Kansas City?
Google confirmed on Feb. 12, 2026 that it is behind the data center campus going up at the northeast corner of I-435 and US 169 in Kansas City's Northland. The Kansas City Star reports five buildings on about 500 acres and calls it a $10 billion complex; that figure is the taxable revenue bonds Port KC approved in July 2025, and Google has not stated its own.
Kansas City has issued 139 permits at 12701 N US 169 Hwy since April 14, 2025. The biggest is a $200 million permit for data center building #1, issued Dec. 19, 2025. The newest, in late October 2026, cover sprinklers for a third data center building and an electrical substation building.
Who gets what?
No one has published the campus's trade split. By the math on Turner & Townsend's data center cost index, about $96 million of the first building's $200 million permit is electrical work and about $66 million is pipes, heat and air. Port KC's bonds allow up to $10 billion across the whole campus.
Which firms are on the job?
JE Dunn holds 12 permits as general contractor, including the $200 million first building, the chiller yard, the electrical yard and the substation building. P1 Group holds 8 mechanical and plumbing permits. Mark One Electric and Staco Electric hold the electrical permits, Staco's for $9.46 million of underground telecom lines; Capital Electric does fire alarm and smoke detection; National Fire Suppression the sprinklers; U.S. Engineering $3.30 million of underground site mechanical; Waldinger the plumbing; Rhys Ivy the water service. Evergy is the utility. 10 firms in all are on the list below.
How do the ways into Google's Kansas City data center compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Google's Kansas City data center | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after Google's Kansas City data center?
| Electrical distributors and gear reps | Mark One, Staco and Capital Electric on the data center, chiller yard and substation building. |
|---|
| Mechanical, chiller and pipe reps | P1 Group's chiller yard (12 mechanical control panels) and U.S. Engineering's site mechanical. |
|---|
| Fire protection suppliers | National Fire Suppression's sprinklers and Capital Electric's fire alarm and smoke detection. |
|---|
What should you do next on Google's Kansas City data center?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Google's Kansas City data center.
Questions people ask about Google's Kansas City data center
How much is Google's Kansas City data center?
The Kansas City Star calls it a $10 billion complex, the amount of revenue bonds Port KC approved. The biggest city permit, for the first building, states $200 million.
Who is building Google's Kansas City data center?
JE Dunn Construction is the general contractor on the city permits. 10 firms are named in all, listed above.
Where is Google's Kansas City data center?
12701 N US 169 Hwy (Arrowhead Trafficway), northeast of I-435 and US 169 in the Northland.
How we built this list
We read all 139 Kansas City permits at 12701 N US 169 Hwy (two city datasets, merged by permit number), The Kansas City Star, KCTV5 and KSHB, and kept each firm a permit or page names on this campus (read Nov. 17, 2026). Two individuals named on permits are left out. The trade split is the math on Turner & Townsend's published data center shares, applied to the first building's permit. Phones are each firm's own office line. First published Nov. 17, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.