Who built California high-speed rail's Hanford Viaduct, on a $3.65 billion contract

California's high-speed rail just finished its mile-long Hanford Viaduct, on a contract that grew from $1.365 billion to $3.65 billion.

By Porter Stanley. Updated .

The California High-Speed Rail Authority finished the Hanford Viaduct, the largest structure on the first 119 miles of the line, with a ribbon cutting in Kings County on Nov. 12, 2026 (California Construction News). It runs 6,333 feet, more than a mile, east of Hanford over the San Joaquin Valley Railroad and State Route 198 (CHSRA). Dragados-Flatiron Joint Venture built it under Construction Package 2-3, a design-build contract for about 65 miles of the line. That contract was signed at $1.365 billion in 2015 and stood at $3.65 billion in October 2025 (CHSRA); no cost for the viaduct alone has been published. 151 firms are named on the viaduct, the contract around it and the track and station work that comes next; the list below has all 151.

$3.65BConstruction Package 2-3 contract, Oct. 2025 (CHSRA)
6,333 ftLength of the Hanford Viaduct (CHSRA)
978Precast concrete girders (CHSRA)
151Firms named on the job

Get all 151 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 151 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 151 firms on the Hanford Viaduct?

We list the 151 firms named on the Hanford Viaduct, one row each, with where each name comes from.

1Latest recordNov 12, 2026

ABSL Construction, Inc.

general engineering contractor (heavy civil) on the Hanford Viaduct

Hanford Viaduct, California high-speed rail Construction Package 2-3, east of Hanford and State Route 43 (Kings County)

Work: general engineering contractor (heavy civil)

Who to call: ABSL Construction, Inc.
ABSL Construction, Inc. office line
(Hayward, CA)
(559) 936-2102

The opportunity: HSR 13-57 DFJV 5/1/2026 ABSL Construction, Inc DBE

2Latest recordNov 12, 2026

Abe Construction Services

heavy / pipeline construction (directory classification) on the Hanford Viaduct

Hanford Viaduct, California high-speed rail Construction Package 2-3, east of Hanford and State Route 43 (Kings County)

Work: heavy / pipeline construction (directory classification)

Who to call: Abe Construction Services
(Livermore
CA (naicslist directory, unconfirmed match))

The opportunity: HSR 13-57 DFJV 5/1/2026 Abe Construction Services MB

3Latest recordNov 12, 2026

BA Construction Inc.

construction (DBE) on the Hanford Viaduct

Hanford Viaduct, California high-speed rail Construction Package 2-3, east of Hanford and State Route 43 (Kings County)

Work: construction (DBE)

Who to call: BA Construction Inc.
(Los Angeles
CA (US DOT DBE decision database, 800 W. 6th St))

The opportunity: HSR 13-81 ARCADIS U.S. Inc. 9/30/2025 BA Construction Inc. DBE

What was built in Hanford?

The Hanford Viaduct carries California's high-speed rail line high above the farmland east of Hanford, in Kings County. It runs 6,333 feet, more than a mile, between Grangeville Boulevard and Hanford-Armona Road, and takes trains over the San Joaquin Valley Railroad and State Route 198 or to the planned Kings/Tulare Regional Station (CHSRA; California Construction News).

It is made of 978 precast concrete girders resting on 286 columns, set on more than 7,000 driven piles, with more than 40,300 cubic yards of concrete placed by May 2025 (CHSRA). The builder cast the girders at its own precast plant beside the structure in Hanford. Girder setting began in August 2022.

The authority held the ribbon cutting on Nov. 12, 2026, and called it the largest structure on the first 119 miles of the line (Railway-News). Interim CEO Joe Stephenshaw cut the ribbon, two weeks after CEO Ian Choudri said on Oct. 29 that he would resign (Newsweek).

How much did it cost?

No one has published a cost for the viaduct by itself. It was built under Construction Package 2-3, a design-build contract for about 65 miles of the line through Fresno, Tulare and Kings counties, with more than 60 road crossings besides the viaduct. The authority signed that contract with Dragados-Flatiron Joint Venture in 2015 for $1.365 billion (CHSRA board resolution).

By October 2025 the contract stood at $3.65 billion, with about $3.08 billion of it paid (CHSRA small business report). On Apr. 29, 2026 the authority's board approved a $537.3 million settlement change order with the builder (CHSRA). Rep. Vince Fong's office called it the largest change order in the project's history and demanded more openness about it.

The whole first phase, San Francisco to Los Angeles and Anaheim, is now put at $126.1 billion, and the Merced to Bakersfield stretch should open in 2033 (Newsweek). Governor-elect Xavier Becerra has said, "I'm going to scrap the current configuration, and I'm going to make sure we finish" (Newsweek).

Which firms are on the job?

Dragados-Flatiron Joint Venture, now FlatironDragados USA, built the viaduct. Jacobs is its lead designer and SENER its project engineer. Arcadis runs project and construction management for the authority on this contract, and The Hanna Group, now part of NV5, was named in 2016 as the site engineer who checks the builder's work. Forefront Deep Foundations drove the viaduct's piles with a hammer from International Construction Equipment (ICE).

Dragados-Flatiron's own precast plant in Hanford cast the viaduct's girders, on forms from Helser Industries and Hamilton Form and a batch plant from Vince Hagan Co. (Concrete Products). IDC Consulting Engineers did the independent design checks for the 6,500-foot viaduct (CHSRA), and Parikh Consultants was the geotechnical independent check engineer on the package.

The authority's small business reports name about 120 more subcontractors on this contract, each with the firm one tier up. Papich Construction paved, A-C Electric and West Pacific Electric did electrical work, Keller and Forefront worked on the piles, and Deer Creek Rock and Asphalt, Moore Twining, Central Valley Reinforcing and dozens of trucking, survey, fencing, biology and erosion firms fill out the list; Arcadis's own team adds 23 subconsultants.

The next money on this stretch goes to the firms that come after the concrete. Kiewit, Stacy and Witbeck and Herzog won the $3.5 billion track and systems contract for the 119 miles, which run over the viaduct (GV Wire), and Foster + Partners and Arup are designing the Kings/Tulare Regional Station the viaduct leads to. 151 firms in all are on the list below.

How do the ways into the Hanford Viaduct compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the Hanford ViaductEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Hanford Viaduct?

Rail, track and electrical suppliersKiewit, Stacy and Witbeck and Herzog on $3.5 billion of track, overhead power and train control over the 119 miles.
Concrete, rebar, pile and site suppliersDragados-Flatiron, Forefront Deep Foundations and the haulers on Construction Package 2-3.
Engineering and building-product repsJacobs, SENER, Arcadis and the Foster + Partners and Arup team designing the Kings/Tulare Regional Station.

What should you do next on the Hanford Viaduct?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the Hanford Viaduct.

Questions people ask about the Hanford Viaduct

How much did the Hanford Viaduct cost?

No cost for the viaduct alone has been published. It was built under Construction Package 2-3, a contract for about 65 miles of the line that was signed at $1.365 billion in 2015 and stood at $3.65 billion in October 2025 (CHSRA).

Who built the Hanford Viaduct?

Dragados-Flatiron Joint Venture, the design-build contractor for Construction Package 2-3, with Jacobs as lead designer. 151 firms are named on the viaduct, its contract and the work that comes next, listed above.

When was the Hanford Viaduct finished?

The California High-Speed Rail Authority marked its completion with a ribbon cutting in Kings County on Nov. 12, 2026.

How long is the Hanford Viaduct?

6,333 feet, more than a mile, built from 978 precast concrete girders on 286 columns (CHSRA).

What comes next on the Hanford stretch?

Track. A $3.5 billion contract approved June 1, 2026 gives Kiewit, Stacy and Witbeck and Herzog the job of laying track, power and train control on the 119 miles (GV Wire; Railway-News). The Kings/Tulare Regional Station is in design.

How we built this list

We read the California High-Speed Rail Authority's board resolutions, its small business report and its BuildHSR page for the viaduct, the Dragados-Flatiron Joint Venture's own site, a 2021 federal court opinion, company releases and the news, and kept each firm a page names on the viaduct, on Construction Package 2-3 or on the track and station work tied to it (read Nov. 17, 2026). The authority's small business under utilization reports (Dec. 2023 and Sept. 2024) list each small business subcontract on this contract by name, with the firm one tier up, so most of the list is contract-wide, not tied to the viaduct alone; its small business newsletters, a precast trade story and firms' own pages add the rest. Its Nov. 12 release was read in a browser. About 50 of the small subcontractors publish no website of their own, so their rows carry no phone; a phone matched by name only was left off. No cost for the viaduct alone is public, so we give no money-by-trade split. Phones are each firm's own office line where one is published. First published Nov. 18, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

Sources, checked Nov. 18, 2026
  1. California Construction News: high-speed rail completes largest structure in Central Valley (Nov. 15, 2026)
  2. Railway-News: California high-speed rail completes largest Central Valley structure (Nov. 13, 2026)
  3. Newsweek: new images show California high-speed rail progress (Nov. 12, 2026)
  4. CHSRA BuildHSR: Hanford Viaduct project page
  5. CHSRA Small Business Under Utilization Report (Sept. 2024)
  6. CHSRA Small Business Under Utilization Report (Dec. 2023)
  7. CHSRA Small Business Newsletter, Spring 2023 (IDC Consulting Engineers on the Hanford Viaduct)
  8. Concrete Products, 'Central Casting', on Dragados-Flatiron's Hanford precast plant (republished by Vince Hagan, Jan. 20, 2021)
  9. CHSRA small business utilization summary, data through October 2025 (January 2026)
  10. CHSRA board resolution, CP 2-3 Change Order 427 (Apr. 29, 2026)
  11. Rep. Vince Fong: demands transparency on $537 million change order (Feb. 10, 2026)
  12. GV Wire: $3.5B high-speed rail contract means Valley tracks to be laid soon (June 1, 2026)
  13. Railway-News: track and systems contract awarded (June 2, 2026)
  14. Railway-News: design contract for Central Valley stations (October 2022)
  15. Dragados-Flatiron Joint Venture CP 2-3 site
  16. ICE: Hanford Viaduct pile driving (July 23, 2024)
  17. METRO Magazine: Jacobs wins California high-speed rail contract (July 22, 2015)
  18. SENER: Construction Package 2-3
  19. CHSRA 'Faces of High-Speed Rail' profile (2016, hosted by NV5)
  20. Herzog: joins Kiewit and Stacy Witbeck (July 13, 2026)
  21. W. Pac. Elec. Co. v. Dragados/Flatiron (E.D. Cal. 2021)

More project reports

All project reports
Get all 151 firms, free

All 151 firms on the Hanford Viaduct

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.