What's due Dec. 1 on the Harborview garage?
Mortenson and Perkins&Will published a notice on Nov. 3, 2026 asking firms for lump-sum construction proposals on the Ninth & Alder Building parking garage. Proposals are due Dec. 1, 2026 at 2:00 p.m. Pacific. It's on the bid board of Washington's Office of Minority and Women's Business Enterprises.
The notice lists 18 scopes. Steel is one line: structural steel, vehicle-rated barrier cable guardrail, stairs and misc. steel. It states no estimate for any scope, and it says more solicitations will be advertised separately.
A virtual pre-bid meeting ran Nov. 9, and a pre-bid site walk is set for Nov. 11 at the corner of 9th and Alder Street. Firms send their company name, primary contact and scope to Mortenson's solicitation contacts, and the team sends the bid requirements and documents.
What are the 18 trade scopes on the Harborview garage?
Mortenson's notice groups nothing, so here are its 18 lines sorted by trade family. The words in quotes are the notice's own.
- Site: "Water Management / Treatment", "Utilities/Grading", "Concrete Paving / Curbs".
- Steel: "Structural Steel, Vehicle Rated Barrier Cable Guardrail, Stairs & Misc. Steel" and "Fireproofing".
- Envelope: "Masonry", "Metal Panels", "Roofing", "Glass and Glazing".
- Openings: "Doors/Frames/Hardware" and "Coil Doors".
- Finishes: "Drywall", "Painting", "Traffic Coating", "Pavement Markings".
- Garage systems: "Unit Pavers, Plantings, Irrigations", "Parking Control Equipment", "Garage Signage".
The list has no structural concrete, electrical, mechanical, plumbing, fire sprinkler or elevator line. The notice doesn't say which trades come in the later round.
How big is the Harborview garage, and what does it cost?
Seattle's land-use record 3044234-LU, filed Oct. 16, 2026, covers a 7-story medical services building, the Harborview 9th & Alder Building, and proposes parking for 645 vehicles. Its estimated project cost is $121 million. King County's own post ties that record to the below-grade garage and a future medical office building.
County officials put the garage at $189 million, The Urbanist reported Oct. 29, 2026. MyNorthwest reported 640 spaces and The Urbanist 700 to 730, so we use the city filing's number.
The garage is not the $1.74 billion bond. MyNorthwest reported it's paid for by the county hospital property tax and a $5 million state Commerce grant. The bond program it supports was approved by voters in 2020 at $1.74 billion, and The Urbanist reported costs going "from $1.74 billion when it was approved six years ago to more than $3 billion today."
Who is already working around Harborview's garage site?
Seattle issued Gary Merlino Construction Company a street use permit revision on Nov. 2, 2026 to pothole about 25 underground utilities in the right of way and at Harborview, to support design for the bond construction project. The county wrote that utility drilling around Ninth and Alder could begin as soon as Nov. 2.
Mortenson's public plan room shows a first make-ready package for the tower, a temporary haul road connecting Yesler and James streets, with bids that were due Oct. 23, 2026. We found no winner posted.
At 925 Terrace Street, site work began Oct. 19 for a three-story modular office building, and Security Solutions NW holds its fire alarm permit, issued Oct. 2.
How do the ways into the Harborview garage compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| Mortenson's Dec. 1 proposal round | Send Mortenson's solicitation contacts your company name, primary contact and scope, as its public notice asks | Subcontractors in one of the 18 listed scopes | The bid requirements and project documents from the project team | Proposals are due Dec. 1, 2026 at 2 p.m. Pacific, and the notice states no estimates |
| Selling to the subs who bid it | A call to steel, glazing, panel and coating subs pricing the garage now | Suppliers and manufacturers' reps | Your product in a sub's number before Dec. 1 | The notice names no bidders, so you find them yourself |
| The architect's specification | A call to Perkins&Will's Seattle studio about a product in one of the 18 scopes | Manufacturers of doors, glazing, panels, coatings and parking equipment | A shot at the spec while design is midway | Design review was accepted Sept. 23, so the spec may be far along |
| The later rounds | Mortenson's next solicitations for the garage and the Harborview program's contractor page | Concrete, electrical, mechanical, plumbing and elevator firms | A place on the next round | The notice gives no date and no trade list for them |
Who should go after the Harborview garage, and who shouldn't?
| Steel fabricators, erectors and barrier cable suppliers | Structural steel, vehicle-rated barrier cable guardrail, stairs and misc. steel is one scope, with proposals due Dec. 1, 2026. |
|---|
| Envelope and finish subs: glazing, metal panels, masonry, roofing, drywall, paint | Each has its own scope line in the same Dec. 1 round. |
|---|
| Parking equipment, coil door, traffic coating and signage suppliers | Parking control equipment, coil doors, traffic coating, pavement markings and garage signage are all listed. |
|---|
| Concrete, electrical and mechanical firms looking for a scope today | This isn't your round: the notice lists none of those, and says more solicitations will be advertised separately. |
|---|
What should you do next on the Harborview garage?
- Read Mortenson's notice on Washington's OMWBE bid board and pick your scope.
- Send Mortenson's team your company name, primary contact and scope well before Dec. 1, 2026 at 2 p.m. Pacific.
- If you supply a product, call the subs pricing your scope and Perkins&Will's Seattle studio about the spec.
- Open the full list for the firms already on the record around the hospital.
Questions people ask about the Harborview garage
Who is building the Harborview garage?
Mortenson and Perkins&Will, the design-build team King County and UW Medicine picked for Harborview's expansion in July 2025. Their Nov. 3, 2026 notice asks firms for lump-sum proposals on the Ninth & Alder Building parking garage.
Who owns the Ninth and Alder garage?
King County, which owns Harborview Medical Center and bought the vacant 1.6-acre Ninth and Alder parcel in 2024. Its Harborview Construction and Infrastructure Division runs the project.
How much does the Harborview garage cost?
County officials put it at $189 million, The Urbanist reported Oct. 29, 2026. The city land-use application estimates $121 million for the building. MyNorthwest reported the garage is paid for by the county hospital property tax and a $5 million state grant, not the 2020 bond.
When are bids due on the Harborview garage?
Mortenson's notice says proposals are due Dec. 1, 2026 at 2:00 p.m. Pacific. A virtual pre-bid meeting was held Nov. 9, and a pre-bid site walk is set for Nov. 11 at the corner of 9th and Alder Street.
What trades are in the Harborview garage package?
18 scopes: water management and treatment, utilities and grading, concrete paving and curbs, structural steel with barrier cable guardrail and stairs, fireproofing, masonry, metal panels, roofing, glass and glazing, doors and hardware, coil doors, drywall, painting, traffic coating, pavement markings, pavers and planting, parking control equipment and garage signage.
How does a subcontractor get on the Harborview garage?
The notice asks interested firms to contact Mortenson's solicitation contacts with their company name, primary contact and the scope they want. The project team then sends the bid requirements and documents.
Is the garage part of the $1.74 billion Harborview bond?
Mortenson's notice files it under the Harborview Bond Program, which voters approved at $1.74 billion in 2020. MyNorthwest reported the garage itself is funded by the county hospital property tax and a state grant, not the bond. The Urbanist reported the program's costs going "from $1.74 billion when it was approved six years ago to more than $3 billion today."
How many parking spaces will the Harborview garage have?
The city land-use filing proposes parking for 645 vehicles. MyNorthwest reported 640 spaces, and The Urbanist reported 700 to 730 stalls.
When does construction start on the Harborview garage?
King County wrote on Oct. 27, 2026 that it intends to break ground in January 2027. The Urbanist reported the garage isn't expected to be complete until late 2028.
Why is Harborview building a garage first?
The new inpatient tower goes on the site of the View Park garages, which close in 2028. The county wants the Ninth and Alder garage open first so parking doesn't drop during construction.
What comes after the garage?
A medical office building above it, which has no funding yet, and the new inpatient tower, whose schematic design began in August 2026. Neither has posted trade packages.
How we built this list
We read Mortenson's notice on the Washington State Office of Minority and Women's Business Enterprises bid board (both copies), Mortenson's public plan room, King County's Harborview program posts, Seattle's land-use and street-use records for 755 Alder St, 325 9th Ave and 925 Terrace St, McKinstry's announcement, and coverage in The Urbanist, MyNorthwest and New England Construction News. A row is on the list only if a record ties it to the garage or the Harborview program around it. We left every person's name, phone and email off the list. The garage's stall count differs by source: the city filing says 645, MyNorthwest 640, and The Urbanist 700 to 730. First published Nov. 9, 2026. We'll update this page when Mortenson posts the next garage round, an award or a new permit at Ninth and Alder.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 9, 2026- Mortenson and Perkins&Will, Ninth & Alder Building parking garage notice, Nov. 3, 2026 (OMWBE)
- Mortenson, public plan room
- Mortenson, Critical Make Ready Package #1A
- Harborview program, Ninth and Alder parking structure moving through permitting, Oct. 27, 2026
- Harborview program, Construction is starting at Harborview, Oct. 27, 2026
- Harborview program, public meeting on 9th and Alder, July 16, 2026
- Harborview program, design-build team announced, July 31, 2025
- Harborview program, schematic design begins on new inpatient tower, Aug. 12, 2026
- Harborview program, contractors
- The Urbanist, New Harborview Garage Advances, Oct. 29, 2026
- MyNorthwest, Harborview parking garage, Sept. 14, 2026
- McKinstry, H&M Harborview JV selected
- City of Seattle, land use record 3044234-LU
- City of Seattle, street use record SUUTIL0032895-A001
- Mortenson, Seattle office