What is being built at Homer City, Pennsylvania?
Homer City Generation is building a natural gas power plant on the site of the old Homer City coal plant, at 1750 Power Plant Road in Indiana County. It says the plant is the largest gas power plant under construction in the U.S.
The plant will make up to 4.4 gigawatts. State air permit papers list seven GE Vernova 7HA.02 combined-cycle units with heat recovery steam generators, ten Mitsubishi FT8 turbines, twelve emergency generators, a fire water pump, auxiliary boilers, fuel gas heaters and seven cooling towers. The whole campus is 3,200 acres.
How much is the Homer City gas plant?
The developer projects more than $10 billion for the campus. It said on April 1, 2026 that more than $1 billion had been funded into construction so far. That is the company's own figure, and no contract value has been made public.
Amazon's data center campus next door has no published cost.
How far along is the Homer City gas plant?
The first steel went up in April 2026. Demolition and digging finished early, in June 2026, after about 3 million cubic yards were moved. Heavy hauls of the big steam generator modules began Sept. 16, 2026.
On Nov. 17, 2026, the developer said the first two of seven GE Vernova turbines had been delivered and set, and the first half of the steam generators installed. The developer says they were set in late September. The other five turbines come by rail later in 2026 and through 2027. The developer says first power is on track for early 2028, with more than 2,000 workers on site.
On Nov. 12, the developer announced a long-term deal for Kyuden Energy Partners to run and maintain the plant. Plant hiring is expected to start in January, followed by about 18 months of training. On Nov. 20, Aquatech was named to treat all of the site's water.
Who is fighting the Homer City gas plant?
Clean Air Council, PennFuture and the Sierra Club appealed the plant's state air permit, plan approval 32-00457A, on Dec. 18, 2025. A group of young Pennsylvanians filed a separate appeal. A hearing is set for Dec. 8-9, 2026 in Pittsburgh.
Work has not stopped. In September, more than 1,800 workers from nine union trades were on site, and a boilermakers local said it once went years without taking an apprentice because the work was not there.
What is Amazon planning next to the Homer City plant?
Amazon Data Services has filed a plan for a data center campus on about 2,200 acres across six sites near the plant. Its August project narrative describes 39 two-story data centers of 225,000 sq ft each; news reports of the plan count 36 buildings.
Indiana County's planners tabled the plan in September, then accepted it for review on Oct. 14, 2026. Acceptance is not approval, and the county has until Jan. 12, 2027 to decide. Amazon aims to start building in December 2026.
Who is building the Homer City gas plant?
Kiewit Power Constructors is the engineering, procurement and construction contractor and has been on site since October 2025. Its engineering arm, Kiewit Engineering Group, is the consultant on the power block's stormwater permit.
Independence Excavating led the demolition and digging, with Kovalchick, Winter Environmental and Frontier Industrial on the old plant's teardown. R & L Development, The Beaver Excavating Company and Wampum Hardware hold state permits for grading and blasting. Edwards Moving & Rigging hauls the big parts in.
The state air permit file names the equipment makers: GE Vernova, Mitsubishi Power, Cummins, MIRATECH, Clarke, EvapTech, CIB Unigas and Aether DBS. Aquatech treats the water, Kyuden will run the plant, and AECOM, Michael Baker International and Civil & Environmental Consultants did engineering and permit work. 23 firms in all are on the list below.
Who Amazon hired before
Homer City Generation is a single-project company with no earlier builds, so this shows the data center owner: Amazon keeps returning to a short list of big general contractors for its AWS campuses. None is named at Homer City yet.
- Ryan Companies: builder on Project Rise, the $7 billion AWS data center campus in Wheatfield, Wheatfield, IN, 2026.
- Skanska: builder on Buildings E and F ($300 million each) at Amazon's Quail Ridge data center campus, Aldie, VA, 2025.
- Gray Construction: builder on AWS data center campuses in Hilliard ($300 million first phase) and Plain City (three expansion buildings), Hilliard and Plain City, OH, 2024.
- Gray Construction: builder on Amazon data centers in Boardman, Oregon, and Jerome, Ohio, Boardman, OR and Jerome, OH, 2024.
These are earlier or other jobs for the same owner. They are not counted in the 23 firms on this job.
How do the ways into the Homer City gas plant compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the Homer City Energy Campus gas plant | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| Amazon's data center campus next door | A place with the builders once Amazon names them for its data centers | Builders, electrical and mechanical contractors and their suppliers | Work on a campus of 36 to 39 data centers | No builder named yet, and the county has until Jan. 12, 2027 to decide on the plan |
Who should go after the Homer City gas plant?
| Mechanical, water and HVAC suppliers | Aquatech on all site water and wastewater treatment, EvapTech's seven cooling towers, and CIB Unigas and Aether DBS on boiler burners and gas heaters. |
|---|
| Site, concrete and heavy haul suppliers | Independence Excavating, R & L Development, Beaver Excavating and Wampum Hardware on digging, grading and blasting, and Edwards Moving & Rigging on the big hauls. |
|---|
| Power and electrical reps | Kiewit's team building the plant around GE Vernova's seven turbines, Mitsubishi's ten FT8 units and Cummins' twelve emergency generators, and Kyuden, which will run the plant. |
|---|
What should you do next on the Homer City gas plant?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the Homer City Energy Campus gas plant at 1750 Power Plant Road in Indiana County.
- Watch for Indiana County's decision on Amazon's data center plan, due by Jan. 12, 2027, and the air permit hearing on Dec. 8-9, 2026.
Questions people ask about the Homer City gas plant
How much is the Homer City gas plant?
The developer projects more than $10 billion for the campus. It says more than $1 billion had been funded into construction by April 1, 2026. No contract value has been made public.
Who is building the Homer City gas plant?
Kiewit Power Constructors is the engineering, procurement and construction contractor, on site since October 2025. 23 firms are named on the job, listed above.
Where is the Homer City Energy Campus?
At 1750 Power Plant Road in Homer City, in Center and Black Lick Townships, Indiana County, Pennsylvania, on the site of the old Homer City coal plant.
How big is the Homer City gas plant?
Up to 4.4 gigawatts from seven GE Vernova 7HA.02 gas turbines, plus ten Mitsubishi FT8 turbines, on a 3,200-acre campus. The developer calls it the largest gas power plant under construction in the U.S.
When will the Homer City gas plant open?
The developer says first power is on track for early 2028. The first two of seven turbines were set in late September 2026, announced Nov. 17, and the rest arrive later in 2026 and through 2027.
How many people work on the Homer City gas plant?
More than 2,000 tradespeople and contractors as of Nov. 17, 2026. In September, more than 1,800 workers from nine union trades were on site.
Is the Homer City air permit being challenged?
Yes. Clean Air Council, PennFuture and the Sierra Club appealed the state air permit, plan approval 32-00457A, on Dec. 18, 2025, and young Pennsylvanians filed a separate appeal. A hearing is set for Dec. 8-9, 2026.
Is Amazon building data centers at Homer City?
Amazon has filed a plan for a data center campus next to the plant, 39 buildings in its August filing (news reports count 36). Indiana County accepted it for review on Oct. 14, 2026 and has until Jan. 12, 2027 to decide.
Who will run the Homer City plant?
Kyuden Energy Partners, formerly IHI Power Services, has a long-term operations and maintenance deal, announced Nov. 12, 2026. Plant hiring is expected to start in January.
How we built this list
We read the developer's news posts, Pennsylvania's air permit review and its other permit files for the site (stormwater, blasting, general permits, the pipeline permit and the silo dust plan), Amazon's filed project narrative, and news reports, all on Nov. 22, 2026. We kept each firm a public record names on this project. Eight equipment makers are named in the air permit file as the vendors whose units or guarantees the permit relies on. Contract values are not public for any firm. Left out: the owner and its financial sponsor, Amazon (the data center owner), a power company named only as Amazon's seller, the gas supplier (an agreement in principle only), a wetland credit bank, a trailer maker, the county's own review engineers, unions, well plugging firms, a 2021 survey firm, and a demolition firm we could read only from a scanned file name. Phones are each firm's own line from its own site, except Wampum Hardware, whose line comes from its state blasting permit; AECOM's is its headquarters and GE Vernova's is its U.S. toll-free line. Kiewit Power Constructors, Kiewit Engineering Group, Michael Baker International, EvapTech, Clarke, CIB Unigas, Aether DBS, Mitsubishi Power and Cummins show no main line we could read, so we give their websites only. First published Nov. 22, 2026. We'll update this page when a new permit, contract or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 22, 2026- Homer City Generation: first two GE Vernova turbines delivered (Nov. 17, 2026)
- Homer City Generation: Aquatech to deliver water technology (Nov. 20, 2026)
- Homer City Generation: Kyuden operations and maintenance agreement (Nov. 12, 2026)
- Homer City Generation: Kiewit's one year on site (Oct. 20, 2026)
- Homer City Generation: heavy equipment transport begins (Sept. 16, 2026)
- Homer City Generation: early completion of demolition and excavation (June 2, 2026)
- Homer City Redevelopment: first steel (April 1, 2026)
- Homer City Redevelopment: $10 billion+ redevelopment moves forward (Sept. 25, 2025)
- PA DEP technical review memo, plan approval 32-00457A (Nov. 18, 2025)
- PA DEP PSD analysis summary (Aug. 11, 2025)
- PA DEP Homer City Generation site redevelopment page and permits
- PA DEP stormwater filing PAC320068, power block
- PA DEP stormwater plan PAC320065 (Michael Baker International)
- PA DEP permit PAD320011, HCPP Pipeline (June 18, 2026)
- PA DEP general permit GP3-32-00460A, R & L Development (Dec. 2, 2025)
- PA DEP blasting permit 32254102
- Dust plan for the coal silo implosion (June 12, 2025)
- Amazon Data Services PIT100 project narrative (Aug. 27, 2026)
- WDAD: county accepts Amazon data center plan for review (Oct. 15, 2026)
- WCCS: Amazon data center plan (Oct. 15, 2026)
- Lehigh Daily: Homer City workers and the permit appeal (Sept. 7, 2026)
- Energy News Beat: Kyuden to run Homer City (Nov. 12, 2026)
- WJAC: first two turbines at Homer City (Nov. 17, 2026)
- Power Engineering: first turbine delivery (Nov. 18, 2026)
- Construction Review Online: $7bn Project Rise, Amazon breaks ground on Indiana data center campus in Wheatfield (2026-11-16)
- Industrial Info Resources: Tech industry, transport needs fuel Skanska's work across U.S. (2025-07-22)
- Industrial Info Resources: Amazon furthers investment in Ohio data centers (2024-12-18)
- Industrial Info Resources: Gray Construction has hand in $11 billion worth of projects (2024-02-15)