Who's building Hudson's Detroit, the $1.4 billion project GM now calls home

GM moved its HQ into Detroit's $1.4 billion Hudson's project in January, even though the 45-story tower is still a massive active job site.

By Porter Stanley. Updated .

Bedrock is building Hudson's Detroit on the site of the old J.L. Hudson's department store on Woodward Avenue: a $1.4 billion, 1.5 million-square-foot project with a 12-story office building, where General Motors opened its new world headquarters on Jan. 12, 2026, and a 45-story tower holding The Detroit EDITION hotel and 96 condos, set to open in 2027. Barton Malow is the builder. The City of Detroit has issued 146 permits at the site since December 2024; the trade permits name the firms doing the wiring, pipes, heat and air, elevators and parking. 25 firms are on the job; the list below has all 25.

$1.4BHudson's Detroit (Detroit Free Press)
45Stories in the EDITION tower
146City of Detroit permits since Dec. 2024
25Firms named on the job

Get all 25 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 25 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 25 firms on Hudson's Detroit?

We list the 25 firms named on Hudson's Detroit, one row each, with where each name comes from.

1Named in the newsJan 13, 2026

Barton Malow

Builder (general contractor) on Hudson's Detroit

Hudson's Detroit, 1208 Woodward Ave, Detroit (Wayne County)

Work: Builder (general contractor)

Who to call: Barton Malow
Barton Malow office line
(Southfield, MI)
(248) 436-5000

The opportunity: ConstructConnect (Jan. 13, 2026): Barton Malow built GM's new headquarters at Hudson's Detroit.

2Permit on the recordJun 9, 2026

Superior Electric Great Lakes Company

Electrical and fire alarm on Hudson's Detroit

Hudson's Detroit, 1208 Woodward Ave, Detroit (Wayne County)

16 City of Detroit permits, 2025-02-27 to 2026-06-09

Work: Electrical and fire alarm

Who to call: Superior Electric Great Lakes Company
Superior Electric Great Lakes Company office line
(Troy, MI)
(248) 585-3400

The opportunity: Permit: Installation of Electrical on Level G GM Hudson

3Permit on the recordSep 30, 2026

Motor City Electric Co.

Electrical, fire alarm and generator on Hudson's Detroit

Hudson's Detroit, 1208 Woodward Ave, Detroit (Wayne County)

11 City of Detroit permits, 2024-12-04 to 2026-09-30

Work: Electrical, fire alarm and generator

Who to call: Motor City Electric Co.
Motor City Electric Co. office line
(Detroit, MI)
(313) 921-5300

The opportunity: Permit: Hudsons Bulletin 138

What is Bedrock building at Hudson's?

Bedrock, Dan Gilbert's real estate firm, is building Hudson's Detroit where the J.L. Hudson's department store stood on Woodward Avenue: 1.5 million square feet in two buildings, at a cost the Detroit Free Press put at $1.4 billion (Building Design+Construction says $1.5 billion).

The 12-story office building is done. General Motors opened its new world headquarters there on Jan. 12, 2026, on about 200,000 square feet over four floors. The 45-story tower beside it, about 685 feet tall, holds The Detroit EDITION hotel and 96 condos that went on sale March 31, 2026 from the $600,000s; it opens in 2027. Crews hung the last of the tower's 4,677 glass panels, each up to 2,200 pounds, in March 2025.

Who gets what?

No one has published Bedrock's trade split. By the math on RSMeans' typical split for office buildings, about $141 million of Hudson's $1.4 billion is electrical work and about $167 million is pipes, heat and air. The rest is the frame, the glass and the finishes.

The City of Detroit has issued 146 permits at 1208 Woodward Ave since December 2024. The biggest, BLD2024-01604, states $82.9 million to build out 97 homes on floors 26 to 45; it names no contractor, and the city's trade permits carry no dollar figure.

Which firms are on the permits?

Barton Malow is the builder. Detroit's trade permits name the rest: Superior Electric Great Lakes Company (16 electrical and fire alarm permits, including the wiring on GM's floors), Motor City Electric (11) and LaBelle Electrical Contractors on the wiring; Limbach (7) and Western Mechanical Contractors (5) on the pipes, heat and air; Schindler on the elevators; and SilMan Industries on the automated parking. 25 firms in all are on the list below.

How do the ways into Hudson's Detroit compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Hudson's DetroitEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after Hudson's Detroit?

Electrical distributors and gear repsSuperior Electric Great Lakes, Motor City Electric, LaBelle and six more electrical firms.
HVAC, plumbing and pipe repsLimbach, Western Mechanical and a dozen more mechanical firms on the tower.
Elevator, parking and building suppliersSchindler's elevators and SilMan's automated parking.

What should you do next on Hudson's Detroit?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Hudson's Detroit.

Questions people ask about Hudson's Detroit

How much does Hudson's Detroit cost?

$1.4 billion, as the Detroit Free Press reported in March 2025; Building Design+Construction put it at $1.5 billion in October 2025.

Who is building Hudson's Detroit?

Barton Malow is the builder for Bedrock. The City of Detroit's trade permits name 25 firms in all, listed above.

When does the Hudson's tower open?

The 45-story tower with The Detroit EDITION hotel and 96 condos is set to open in 2027. GM's headquarters in the office building opened Jan. 12, 2026.

How we built this list

We read every City of Detroit building and trade permit at 1208 Woodward Ave issued from Dec. 4, 2024 to Nov. 4, 2026 (146 permits, read Nov. 16, 2026) and kept each firm a permit names; a permit filed under a person's name with no firm found is left out. Barton Malow is from the news. The project's cost is the Detroit Free Press figure; the trade split is the math on RSMeans' typical shares. Phones are each firm's own office line. First published Nov. 17, 2026. We'll update this page when a new permit, filing or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 25 firms, free

All 25 firms on Hudson's Detroit

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.