What is Hyundai Steel building near Donaldsonville, Louisiana?
HYUNDAI-POSCO Louisiana Steel (HPLS) is building a steel mill on about 1,822 acres in the RiverPlex MegaPark, by the Mississippi River at Modeste, north of Donaldsonville in Ascension Parish. It is Hyundai Motor Group's first steelmaking plant in North America. Hyundai Steel owns half. POSCO owns 20%, and Hyundai Motor and Kia own 15% each.
The mill will make 2.7 million metric tons of steel a year, much of it for cars. An iron plant will make 2.5 million tonnes a year of direct reduced iron. Two electric arc furnaces melt it into steel, two slab casters shape it, and a hot strip mill, a cold mill and coil finishing lines roll and finish it.
How much does the Hyundai Steel mill in Louisiana cost?
HPLS calls the mill a $5.8 billion investment. The state incentive filing, received July 15, 2026, lists $3,662,639,000 of investment and 5,294 jobs. That is likely the part in that one application.
Other money around the mill: the State Bond Commission approved about $1.3 billion of tax-free bonds in September 2026, $900 million through a state finance authority plus the Port of South Louisiana's up to $400 million in revenue bonds for the dock. The state offers a $100 million grant for roads, rail, power and pipelines. POSCO is putting $582 million into its 20% stake.
Who is building the Hyundai Steel mill?
Hyundai Engineering & Construction is the builder. Korean business press reports it won about 5.38 trillion won of construction work in June 2026 through Hyundai America, its U.S. arm. That is about $3.9 billion at about 1,380 won to the dollar, our conversion. The figure comes from Korean press, not a company filing.
Site work began in early 2026: clearing, wick drains, test piles and a detention pond. Federal stormwater records from May 22, 2026 name Forgen on the mill site and Five-S Group on the laydown yards. The owner's photo log shows a Keller rig on site in April 2026. The equipment comes from Danieli, Tenova, SMS group and Fives.
What did the air permit and the court ruling change?
Louisiana's environmental agency issued the mill's air permit on Oct. 23, 2026, after a public hearing on Sept. 1. The permit runs to Oct. 23, 2031. The company held a groundbreaking on Sept. 4 but could not begin full building until the permit came through.
The dock fight came next. Rural Roots Louisiana, the Louisiana Bucket Brigade and a third plaintiff sued over the Port's up to $400 million in revenue bonds for the dock. On Nov. 17, 2026, a judge in St. John the Baptist Parish dismissed the suit and lifted a temporary order that had blocked the Port's hearing on the bonds. HPLS's lease is what pays the bonds back. The Port still has to hold a hearing and vote on the financing.
What is the Port building for the mill?
The Port of South Louisiana plans the Ascension RiverPlex Megadoc, a deep-water dock near mile 185 of the Mississippi. The plan dredges to 50 feet deep, about 630,000 cubic yards, and fills 25.76 acres of water. It adds a conveyor trestle, a marine offloading spot and a heavy haul bridge.
T. Baker Smith filed the dock's Corps of Engineers application for the Port on May 15, 2026, and WSP is the engineer. The Port advertised a heavy haul road and construction bridge job on July 22, 2026, and put its award to the lowest bidder on its Sept. 22 agenda. We found no record naming the winner yet.
When will the Hyundai Steel mill open?
Trial runs are set for late 2028 and commercial production for early 2029. About 4,800 workers are expected at the peak of building, by the company's projection. The mill plans 1,300 permanent jobs and about 4,100 more jobs around it.
On Nov. 18, 2026, HPLS won Deal of the Year at the Louisiana Energy Awards. On Nov. 20, Korean trade press reported a drone station now flies over the site with Hyundai E&C.
Who Hyundai hired before
Hyundai Steel went back to SMS group for rolling mills, as it did at its Dangjin works in Korea in 2011. Hyundai Motor Group's Georgia car plant was built by Hyundai Engineering of America, an affiliate of Hyundai E&C, with Hanterin US.
- Hyundai Engineering of America: builder on Hyundai Motor Group Metaplant America, the $7.6 billion EV plant, Ellabell, GA, 2024.
- Hanterin US: builder on Hyundai Motor Group Metaplant America, Ellabell, GA, 2024.
- SMS group (SMS Siemag): steel mill equipment on Second heavy-plate mill at Hyundai Steel's Dangjin works, Dangjin, South Korea, 2011. Also on this job.
- Paul Wurth: engineer on Hyundai Steel's Dangjin integrated steel mill, No. 1 blast furnace, Dangjin, South Korea, 2010.
These are earlier or other jobs for the same owner. They are not counted in the 14 firms on this job.
How do the ways into the Hyundai Steel mill compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Hyundai Steel's Louisiana mill | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The Port's dock work | A place on a team working the Port of South Louisiana's dock, haul road and bridge | Marine, dredging and site contractors | A share of the dock work the Port plans to fund with up to $400 million in bonds | The Port still has to vote on the financing, and no heavy haul road winner is public yet |
Who should go after the Hyundai Steel mill in Louisiana?
| Concrete, steel and site suppliers | Forgen on the mill's site work, Five-S Group on the laydown yards and Keller on ground improvement, on the 1,822-acre site. |
|---|
| Electrical, mechanical and industrial gear reps | Hyundai E&C as builder, with Danieli, Tenova, SMS group and Fives supplying the furnaces, iron plant and mills, and Air Liquide piping in gases. |
|---|
| Marine, dredging and engineering firms | The Port's deep-water dock, engineered by WSP, with a 50-foot dredge, a conveyor trestle and a heavy haul bridge. |
|---|
What should you do next on the Hyundai Steel mill?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Hyundai Steel's mill in the RiverPlex MegaPark near Donaldsonville.
- Watch for the Port of South Louisiana's vote on the dock bonds.
Questions people ask about the Hyundai Steel mill in Louisiana
How much does the Hyundai Steel mill in Louisiana cost?
HPLS calls it a $5.8 billion investment. The state incentive filing lists $3,662,639,000 of investment and 5,294 jobs, likely the part in that one application.
Where is the Hyundai Steel mill in Louisiana?
In the RiverPlex MegaPark at Modeste, on the west bank of the Mississippi River north of Donaldsonville, in Ascension Parish. The site is about 1,822 acres.
Who is building the Hyundai Steel mill?
Hyundai Engineering & Construction, through its U.S. arm Hyundai America. Korean press reports it won about 5.38 trillion won of work in June 2026; that is a press report, not a filing. 14 firms are named on the job, listed above.
Who owns the Louisiana steel mill?
HYUNDAI-POSCO Louisiana Steel LLC. Hyundai Steel owns 50%, POSCO 20%, Hyundai Motor 15% and Kia 15%.
Did the Hyundai Steel mill get its air permit?
Yes. Louisiana issued the air permit on Oct. 23, 2026, after a public hearing on Sept. 1. It runs to Oct. 23, 2031, and lets full building begin.
What happened with the lawsuit over the Port dock?
On Nov. 17, 2026, a judge dismissed the suit against the Port of South Louisiana's up to $400 million in revenue bonds for the dock. HPLS's lease pays the bonds back. The Port still has to vote on the financing.
When will the Hyundai Steel mill open?
Trial runs are set for late 2028 and commercial production for early 2029.
How many workers will build the Hyundai Steel mill?
About 4,800 at the peak of building, by the company's projection. The mill plans 1,300 permanent jobs.
Who supplies the steelmaking equipment?
Danieli supplies two electric arc furnaces, two slab casters and two reheating furnaces. Tenova and Danieli supply the iron plant, SMS group all the rolling mills and Fives the coil finishing lines.
How can subcontractors get on the Hyundai Steel mill?
Call the firms already on the job, starting with Hyundai E&C and the site firms, Forgen and Five-S Group. For the dock, the Port's engineer is WSP.
What happens next on the Hyundai Steel mill?
Full building can now start under the air permit, and the Port has to vote on the dock bonds. We'll update this page when a new contract, filing or firm appears.
How we built this list
We read the owner's site and photo log, the suppliers' own releases (Danieli, Tenova, Air Liquide, Entergy), trade press on SMS group and Fives, federal stormwater construction records, the Port of South Louisiana's bid papers and dock permit application, Korean business and trade press, and local news on the air permit and the court ruling, all on Nov. 23, 2026. We kept each firm a public record names on the mill or its dock. Hyundai E&C's 5.38 trillion won figure is from Korean press, not a company filing, and the dollar figure is our conversion. Left out: the owners (Hyundai Steel, POSCO, Hyundai Motor, Kia), the Port and state agencies, AMOVA (part of the SMS order), and the firms on the separate workforce training center (Arkel Constructors, Domain Architecture and DLR Group, CSRS) and a small grounds crew. Ascension Parish has no building permit feed we read. Phones are each firm's own line from its own site; SMS group's is its U.S. office in Pittsburgh, Wooyang HC's and Meissa's are in South Korea, and the other firms show no main line on their sites. First published Nov. 23, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 23, 2026- HYUNDAI-POSCO Louisiana Steel: project site and construction photo log (read Nov. 23, 2026)
- WBRZ: judge dismisses lawsuit, clearing path for Port of South Louisiana megadock project (Nov. 18, 2026)
- SteelOrbis: court ruling clears way for $400 million port project (Nov. 23, 2026)
- 10/12 Industry Report: Hyundai-POSCO secures air permit (Oct. 28, 2026)
- Business Report: Hyundai's air permit is approved (Nov. 3, 2026)
- 10/12 Industry Report: Louisiana Energy Awards (Nov. 19, 2026)
- Hyundai Steel via PR Newswire: Louisiana EAF steel mill project launch (Sept. 4, 2026)
- WBRZ: Hyundai meets with Donaldsonville residents
- InsightKorea: Hyundai E&C overseas orders (Nov. 19, 2026)
- Korea Sprint: Meissa drone station at the HPLS site (Nov. 20, 2026)
- Danieli: HPLS selects Danieli (May 4, 2026)
- Tenova: Hyundai Steel selects ENERGIRON (May 4, 2026)
- Steel Market Update: Hyundai-POSCO chooses Danieli (May 8, 2026)
- Steel Times International: HPLS chooses SMS group mills (May 12, 2026)
- Steel Market Update: Hyundai and Fives deal for coil finishing lines (April 15, 2026)
- Dealsite: Wooyang HC DRI equipment contract (Aug. 31, 2026)
- Entergy: electric service agreement for the steel mill (April 30, 2026)
- Air Liquide: over $350 million to support the steel industry in Louisiana (April 22, 2026, archived)
- EPA ECHO: stormwater construction record LAR10Q774
- EPA ECHO: stormwater construction record LAR10Q800
- Port of South Louisiana: heavy haul road and construction bridge, addendum 01 (July 27, 2026)
- Port of South Louisiana: Megadoc Corps of Engineers permit application (May 15, 2026)
- WWNO: State Bond Commission approves $1.3B in bonds (Sept. 18, 2026)
- Louisiana Economic Development FastLane: incentive filing 20250339-QJ (July 15, 2026)
- Manufacturing Dive: POSCO's $582M investment in the Louisiana mill
- Good Jobs First: Hyundai Steel subsidy record
- Construction Review Online: Hyundai EV plant in Georgia (updated 2026-08-10)
- AIST: Hyundai Steel Orders Second Heavy-Plate Mill from SMS Siemag (2011-06-30)
- Industrial Info Resources, 2010-01-13