What is TxDOT building on I-35 in Austin?
I-35 Capital Express Central rebuilds about 8 miles of I-35 through central Austin, from US 290 East to SH 71/Ben White Blvd. The Texas Department of Transportation (TxDOT) owns the job. The main lanes downtown will be lowered, and there will be two non-tolled HOV lanes each way and more than 19 miles of shared-use paths.
The bridge over Lady Bird Lake grows from 13 lanes to 18. Under the highway, a drainage tunnel 22 feet wide runs 6.5 miles in all, about 3 miles under I-35 and about 3.5 miles under Cesar Chavez St, 70 to 200 feet deep, with nine shafts and a pump station near US 183.
How much does the I-35 rebuild in Austin cost?
At the groundbreaking on Oct. 31, 2024, TxDOT called it the $5.6 billion Capital Express Central project. Many news reports use a $4.5 billion budget for the same job. It is a budget, not money spent. TxDOT says the whole corridor should be done in 2033, weather permitting.
Three contracts with a stated price have been awarded so far: $746.4 million for the Lady Bird Lake segment, $698.1 million for the drainage tunnel and $34.4 million for the MLK Jr. Blvd bridge. Together that is about $1.48 billion, the sum of TxDOT's bid results.
Who is digging the I-35 drainage tunnel?
SAK Construction and J.F. Shea Construction bid the drainage tunnel together at $698.1 million, the lowest of 3 bids, on Dec. 4, 2024 (CSJ 0015-13-433). News reports put the whole tunnel job at about $748 million. Webber is building the pump station near US 183 and Cesar Chavez St.
The two tunnel boring machines were made by Herrenknecht in Germany and put together on site. As of Nov. 20, 2026, crews were still digging drop shafts, and TxDOT expects both machines running by the end of the year, starting near Airport Blvd. BGE is the tunnel and pump station design engineer, and AECOM inspects the tunnel work for TxDOT.
What is happening at the Lady Bird Lake bridge?
Balfour Beatty won the Lady Bird Lake segment, from Holly St to US 290 West/SH 71, with a low bid of $746.4 million of 4 on Sept. 6, 2024 (CSJ 0015-13-428). By July 2026, crews had torn down part of the old bridge and set columns and caps for the new bridges on shore.
The work has drawn a fight on the water. Boaters are held to a passage about 75 feet wide under the work, and rowers worry it is too narrow for two-way traffic. TxDOT says it is not looking to make a change. The northbound frontage road at Riverside Drive is closed through 2029 for a new pedestrian bridge over the lake.
Did a lawsuit stop the I-35 rebuild?
No. The group Rethink35 sued over TxDOT's environmental review of the project. In March 2026 a court upheld that review, and work has gone on.
Which I-35 contracts did TxDOT just bid?
On Nov. 3, 2026, TxDOT took bids on two more pieces as one contract: the University segment, from US 290 East to MLK Jr. Blvd (CSJ 0015-13-432), and the Capital Plaza segment, from US 290 East to 51st St (CSJ 0015-13-441). Austin Bridge & Road Services was the apparent low bidder at $412.2 million of 6 bids. TxDOT's estimates for the pieces of that contract add up to about $409.8 million, the sum, including $294.2 million for the University segment and $111.3 million for Capital Plaza. The award is not yet confirmed, so Austin Bridge & Road is not on our list.
The downtown segment, with the lowered lanes from MLK Jr. Blvd to Holly St, starts in early 2027.
Which engineering firms are on the I-35 rebuild?
HNTB is TxDOT's general engineering consultant, giving engineering services and oversight of design and construction. WSP designed the Lady Bird Lake segment, with RS&H as engineer. HDR is the design firm of record for the drainage tunnels and the MLK bridge. Volkert designed the University segment, and Huitt-Zollars the power line job that feeds the pump station.
On the tunnel, Schnabel Engineering is a core member of the tunnel design team, with tunnel and shaft design, and Balcones Geotechnical is a geotechnical consultant. 17 firms in all are on the list below.
Who TxDOT hired before
TxDOT keeps handing its biggest Texas highway rebuilds to the same handful of heavy civil firms; Balfour Beatty won both Austin's Lady Bird Lake segment and Dallas's I-30 Canyon within five months.
- Balfour Beatty Infrastructure: builder on I-30 Canyon, IH 35E to IH 45, downtown Dallas ($888.7M), Dallas, TX, 2025. Also on this job.
- Pulice Construction: builder on I-35 Capital Express North, widening from SH 45N ($606.9M), Travis County, TX, 2022.
- Webber, LLC: builder on I-10 reconstruction from Heights Blvd, Houston ($407.8M), Houston, TX, 2024. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 17 firms on this job.
How do the ways into the I-35 rebuild compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on I-35 Capital Express Central in Austin | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
| The segments still being let | A place on the team that wins the University and Capital Plaza contract (CSJ 0015-13-432 and 0015-13-441) or the downtown segment | Builders, concrete, steel and site subcontractors | A share of a contract bid at $412.2 million, and the downtown segment after it | The University and Capital Plaza award is not yet confirmed, and the downtown segment is not yet bid |
Who should go after the I-35 rebuild in Austin?
| Tunnel, concrete and steel suppliers | SAK and J.F. Shea on the $698.1 million drainage tunnel, Webber on the pump station, and Balfour Beatty on the $746.4 million Lady Bird Lake segment. |
|---|
| Engineering, survey and testing firms | HNTB, TxDOT's general engineering consultant, the segment designers (WSP, RS&H, HDR, Volkert, Huitt-Zollars), the tunnel design team (BGE, Schnabel, Balcones Geotechnical) and AECOM on tunnel inspection. |
|---|
| Builders and big subcontractors | The University and Capital Plaza segments were bid on Nov. 3, 2026, and the downtown segment starts in early 2027. |
|---|
What should you do next on the I-35 rebuild?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on I-35 Capital Express Central in Austin.
- Watch for TxDOT's award on the University and Capital Plaza contract, bid Nov. 3, 2026, and for the tunnel machines to start by the end of 2026.
Questions people ask about the I-35 rebuild in Austin
How much does I-35 Capital Express Central cost?
TxDOT called it a $5.6 billion project at the Oct. 31, 2024 groundbreaking. Many news reports use a $4.5 billion budget. It is a budget, not money spent. The three awarded contracts with a stated price add up to about $1.48 billion, the sum.
Who is building the I-35 rebuild in Austin?
TxDOT owns the job. Balfour Beatty builds the Lady Bird Lake segment ($746.4 million), SAK and J.F. Shea dig the drainage tunnel ($698.1 million), Webber builds the pump station, and Harper Brothers built the MLK Jr. Blvd bridge ($34.4 million). 17 firms are named on the job, listed above.
When will the I-35 rebuild in Austin be done?
TxDOT says the whole corridor should be done in 2033, weather permitting. The MLK Jr. Blvd bridge has been fully open since Aug. 9, 2026, and the downtown segment starts in early 2027.
How big is the I-35 drainage tunnel?
The tunnels run 6.5 miles in all, 22 feet wide and 70 to 200 feet deep: about 3 miles under I-35 and about 3.5 miles under Cesar Chavez St, with nine shafts and a pump station near US 183.
When do the I-35 tunnel boring machines start?
As of Nov. 20, 2026, TxDOT expects both tunnel boring machines to be running by the end of 2026, starting near Airport Blvd. The two machines were made by Herrenknecht in Germany.
Who won the Lady Bird Lake bridge contract?
Balfour Beatty, with a low bid of $746.4 million of 4 on Sept. 6, 2024. The bridge over Lady Bird Lake grows from 13 lanes to 18.
Who bid the I-35 University segment?
On Nov. 3, 2026, TxDOT bid the University and Capital Plaza segments as one contract. Austin Bridge & Road Services was the apparent low bidder at $412.2 million of 6 bids, against TxDOT's estimates of about $409.8 million for the whole contract, the sum. The award is not yet confirmed.
Did a lawsuit stop the I-35 rebuild in Austin?
No. Rethink35 sued over TxDOT's environmental review, and in March 2026 a court upheld the review. Work has gone on.
Which engineering firms work on the I-35 rebuild?
HNTB is TxDOT's general engineering consultant. WSP, RS&H, HDR, Volkert and Huitt-Zollars design segments, BGE, Schnabel and Balcones Geotechnical work on the tunnel design, and AECOM inspects the tunnel work.
How can subcontractors and suppliers get on the I-35 rebuild?
Call the firms already on the job, starting with Balfour Beatty, SAK, J.F. Shea and Webber. For the segments still being bid, the way in is the firm that wins them.
What happens next on the I-35 rebuild in Austin?
TxDOT expects both tunnel machines running by the end of 2026, an award on the University and Capital Plaza contract, and the downtown segment in early 2027. We'll update this page when a new contract or firm appears.
How we built this list
We read TxDOT's groundbreaking release and its construction information sheets for the MLK and Lady Bird Lake segments; TxDOT's bid results for the Lady Bird Lake, tunnel, MLK, Power to Pump, University and Capital Plaza contracts; Texas building plan registrations for the tunnel, Lady Bird Lake, University and Power to Pump jobs; the firms' own releases and project pages; and news and trade reports, all on Nov. 23, 2026. We kept each firm a public record names on this project. Contract values for the SAK and Shea team are for the whole team, not one firm's share. We used TxDOT's $5.6 billion for Capital Express Central, not an older figure for the whole I-35 Capital Express program across several counties. Left out: TxDOT and its funding partners (the owner), the losing bidders, Austin Bridge & Road (the apparent low bidder on the University segment, award not yet confirmed), the apparent low bidder on the Power to Pump job (award not confirmed), and a firm named only among the corridor's designers. We did not find a public list of subcontractors below the main contractors. Phones are each firm's own line from its own site where it shows one; WSP's is its Austin office as shown on a state filing; BGE, Schnabel, RS&H, HDR, Volkert and AECOM are headquarters lines; Balfour Beatty, Webber and Herrenknecht show no main line on their sites, and we found no website for Harper Brothers. First published Nov. 23, 2026. We'll update this page when a new contract, filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 23, 2026- TxDOT: TxDOT breaks ground on I-35 Capital Express Central (Oct. 31, 2024)
- Community Impact: Central Austin transportation projects to watch as 2026 wraps up (Nov. 20, 2026)
- Community Impact: TxDOT spends $748M to burrow tunnels under central Austin (Oct. 29, 2025)
- Community Impact: Where central Austin's road, bridge and trail projects stand in October (Oct. 20, 2026)
- Community Impact: Long-term closure on I-35 frontage road near Riverside Drive (Feb. 2026)
- KUT: I-35 bridge over Lady Bird Lake and the 75-foot passageway (May 19, 2026)
- KUT: I-35 drainage tunnel under Cesar Chavez (Sept. 29, 2025)
- MySA via Yahoo: Austin's $5.65B in I-35 projects (July 27, 2026)
- Bloomberg Government: Texas highway expansion environmental review upheld by court (March 2026)
- TBM: Tunnel Business Magazine: Tunneling for an improved Austin (Oct. 16, 2023)
- TBM: Tunnel Business Magazine: AECOM to deliver TxDOT I-35 drainage tunnels (May 2024)
- Construction Equipment Guide: Capital Express Central project ramps up (Dec. 23, 2024)
- Construction Equipment Guide: I-35 Capital Express Central flood prevention project under way (Aug. 19, 2025)
- Texas Contractor: TxDOT rebuilding Lady Bird Lake bridge (Oct. 2026)
- TxDOT: MLK Jr. Blvd segment construction information sheet (Sept. 2024)
- TxDOT: Lady Bird Lake segment construction information sheet
- TxDOT bid results: CSJ 0015-13-428, Lady Bird Lake segment
- TxDOT bid results: CSJ 0015-13-433, drainage tunnel
- TxDOT bid results: CSJ 0015-13-432, University segment (Nov. 3, 2026)
- TxDOT bid results: CSJ 0015-13-441, Capital Plaza segment (Nov. 3, 2026)
- TDLR: TABS2025001141, IH 35 drainage tunnels
- TDLR: TABS2024015937, IH 35 Lady Bird Lake segment
- TDLR: TABS2027002239, IH 35 University segment
- TDLR: TABS2026018842, Kingsbery duct bank (Power to Pump)
- BGE: named design engineer for TxDOT drainage tunnels and pump station (Oct. 31, 2023)
- Schnabel Engineering: I-35 CapEx drainage tunnel project page
- HNTB: I-35 Capital Express Central project page
- FODS: SAK tunnel project case study
- TxDOT bid tabulation CSJ 0009-11-254, let 2025-02-07
- TxDOT bid tab archive CSJ 0015-10-062, let 2022-08-03
- TxDOT bid tab archive CSJ 0271-07-326, let 2024-08-01