Who's building the I-405 toll lanes from Renton to Bellevue

Bellevue's $883 million I-405 toll lanes are headed to trial, with the state suing its own builder over the delays.

By Porter Stanley. Updated .

Washington State is widening about 12 miles of I-405 between SR 167 in Renton and NE 6th Street in Bellevue and adding a two-lane express toll lane system. The job was budgeted at $813 million and is now estimated at about $883 million, a news investigation reported on Nov. 23, 2026. The $704,975,000 design-build contract went to Flatiron-Lane, a joint venture of Flatiron West and The Lane Construction Corporation, in 2019. WSDOT sued the joint venture in 2023 over construction delays, and the joint venture filed counterclaims accusing WSDOT of "active interference" and "obstruction." The contract sets late-completion damages of up to $60,000 a day; in July 2025 WSDOT's lawyers wrote that the damages owed are projected to be more than $75 million. The toll lanes are now due to open in summer 2027. 34 firms are named on the job; the list below has all 34.

$883MEstimated cost, up from an $813M budget
$75M+Late damages owed, as projected by WSDOT's lawyers
$705MDesign-build contract to Flatiron-Lane (2019)
34Firms named on the job

Get all 34 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 34 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 34 firms on the I-405 Renton to Bellevue toll lanes?

We list the 34 firms named on the I-405 Renton to Bellevue toll lanes, one row each, builders and biggest subs first, with what each one does on the job and where its name comes from.

1Latest recordNov 5, 2019

Flatiron West, Inc. (Flatiron-Lane joint venture)

Design-builder: lead partner of Flatiron-Lane, the joint venture that holds the whole contract on the I-405 Renton to Bellevue toll lanes in King County, WA

I-405 Renton to Bellevue widening and express toll lanes (WSDOT contract 9242), King County, WA

Design-build contract 9242, $704,975,000, awarded Oct. 1, 2019, for the whole joint venture; its state prevailing wage filing 1019888, filed Nov. 5, 2019

Work: Design-builder: lead partner of Flatiron-Lane, the joint venture that holds the whole contract

Who to call: Flatiron West, Inc. (Flatiron-Lane joint venture)
Flatiron-Lane joint venture office line (the number on its state filing)
(Renton, WA)
(425) 420-9900

The opportunity: WSDOT awarded the $704,975,000 design-build contract to Flatiron West, Inc.-The Lane Construction Corporation, A Joint Venture on Oct. 1, 2019. WSDOT sued the joint venture in 2023 over construction delays, and the joint venture filed counterclaims accusing WSDOT of "active interference" and "obstruction." The trial is expected in September 2027. Flatiron also built WSDOT's earlier Bellevue to Lynnwood toll lanes.

2Latest recordOct 1, 2019

The Lane Construction Corporation

Design-builder: partner in Flatiron-Lane, the joint venture that holds the whole contract on the I-405 Renton to Bellevue toll lanes in King County, WA

I-405 Renton to Bellevue widening and express toll lanes (WSDOT contract 9242), King County, WA

Design-build contract 9242, $704,975,000, awarded Oct. 1, 2019, for the whole joint venture, not Lane's share

Work: Design-builder: partner in Flatiron-Lane, the joint venture that holds the whole contract

Who to call: The Lane Construction Corporation
The Lane Construction Corporation corporate office line (from its own site)
(704) 553-6500

The opportunity: WSDOT's award names Flatiron West, Inc.-The Lane Construction Corporation, A Joint Venture. Lane's own project page says the project is a joint venture with Flatiron Construction. The contract value is for the whole joint venture, not Lane's share.

3Latest recordJul 23, 2020

KLB Construction, Inc.

Heavy civil subcontractor with the biggest subcontract on the job on the I-405 Renton to Bellevue toll lanes in King County, WA

I-405 Renton to Bellevue widening and express toll lanes (WSDOT contract 9242), King County, WA

State prevailing wage filing 1074539, $249.1 million stated, filed July 23, 2020, hired by Flatiron-Lane

Work: Heavy civil subcontractor with the biggest subcontract on the job

Who to call: KLB Construction, Inc.
KLB Construction, Inc. office line (from its own site)
(425) 355-7335

The opportunity: Hired by Flatiron-Lane on WSDOT contract 9242. The largest subcontract filed on the job. KLB in turn hired Grady Excavating for excavation.

What is being built on I-405 between Renton and Bellevue?

WSDOT is widening about 12 miles of I-405 between SR 167 in Renton and NE 6th Street in Bellevue. The job adds a lane each way and a two-lane express toll lane system, part of a toll lane network of about 40 miles. WSDOT calls the stretch one of the state's worst commutes.

The work rebuilds interchanges at NE Park Drive and NE 44th Street in Renton and at 112th Avenue SE and Coal Creek Parkway in Bellevue. It also builds 4 fish passage crossings, 47,656 sq ft of noise wall and 2.5 miles of paved Eastrail, the regional walking and biking trail.

How much do the I-405 Renton to Bellevue toll lanes cost?

The job was budgeted at $813 million. On Nov. 23, 2026, a news investigation put it at about $883 million, including an added funding need of about $45 million in the next legislative session.

The design-build contract itself is $704,975,000. WSDOT awarded it to Flatiron-Lane, a joint venture of Flatiron West, Inc. and The Lane Construction Corporation, on Oct. 1, 2019.

Why is WSDOT suing the I-405 builder?

The toll lanes were due by the end of 2025. In July 2025 a WSDOT program administrator wrote, "We know that the end of 2025 is not feasible." On Nov. 24, 2025, WSDOT told the public the lanes would open in summer 2027 and said it was taking the contractor to court.

WSDOT sued the joint venture in 2023 over construction delays. The contract sets late-completion damages of up to $60,000 a day, and WSDOT's lawyers wrote in July 2025 that the damages owed are projected to be more than $75 million. Court papers cite missed milestones, including "toll infrastructure completion" and "toll commencement." The joint venture filed counterclaims accusing WSDOT of "active interference" and "obstruction." The trial is expected to begin in September 2027.

When will the I-405 Renton to Bellevue toll lanes open?

WSDOT expects the express toll lanes to open in summer 2027. A WSDOT internal report dated Aug. 6, 2026 projects tolling to begin in July 2027, with construction on site not finished until February 2028.

Crews set the toll gantries over northbound and southbound I-405 during weekend closures in September 2026.

Who is building the I-405 Renton to Bellevue toll lanes?

Flatiron-Lane is the design-builder. State prevailing wage filings on the contract name 220 firms besides the joint venture. The biggest subcontract is KLB Construction's, at $249,133,443, filed July 23, 2020. Rainier Welding's steel work is $85.0 million and Valley Electric's electrical work is $61.4 million.

On design, Wood (now part of WSP) filed $50.1 million, Parsons $21.7 million and David Evans and Associates $7.0 million. Each amount is what the firm stated on its filing; a firm hired by another sub is counted inside that sub's work too, so the amounts do not add up to the contract. 34 firms in all are on the list below.

Who WSDOT hired before

WSDOT keeps going back to the same I-405 team: Flatiron built the earlier Bellevue to Lynnwood toll lanes, and the joint venture re-hired that job's subcontractors and consultants for Renton to Bellevue.

  • Flatiron: builder on I-405 Bellevue to Lynnwood widening and express toll lanes (Flatiron's first I-405 job), Bellevue to Lynnwood, WA, 2015. Also on this job.
  • Valley Electric: electrical on SR 520 Eastside HOV project, Bellevue/Kirkland, WA, 2014. Also on this job.
  • Kleinfelder: quality testing on I-405 Bellevue to Lynnwood (BTL) design-build, Bellevue to Lynnwood, WA, 2015.
  • Hart Crowser, Exeltech and EnviroIssues: geotech, design and outreach on I-405 Bellevue to Lynnwood (BTL) design-build, Bellevue to Lynnwood, WA, 2015.

These are earlier or other jobs for the same owner. They are not counted in the 34 firms on this job.

How do the ways into the I-405 Renton to Bellevue job compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on the I-405 Renton to Bellevue toll lanesEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose work matches what you sell

Who should go after the I-405 Renton to Bellevue job?

Concrete, steel, rebar and paving suppliersKLB Construction's $249.1 million subcontract, Rainier Welding's $85.0 million steel work, and the rebar, precast and paving firms on the list.
Electrical and traffic systems distributorsValley Electric's $61.4 million electrical work, with Transcon, Saber Technologies and Trenchless Construction Services under it.
Equipment, traffic control and site service firmsA job with a new sub filing as late as October 2026, and traffic control, striping, crane, landscaping and trucking firms already on it.

What should you do next on the I-405 Renton to Bellevue job?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on the I-405 Renton to Bellevue widening and express toll lanes (WSDOT contract 9242).
  3. Watch for the start of tolling, projected for July 2027.

Questions people ask about the I-405 Renton to Bellevue toll lanes

How much do the I-405 Renton to Bellevue toll lanes cost?

The job was budgeted at $813 million and is now estimated at about $883 million, reported Nov. 23, 2026, including an added funding need of about $45 million in the next legislative session. The design-build contract is $704,975,000.

Who is building the I-405 Renton to Bellevue toll lanes?

Flatiron-Lane, a joint venture of Flatiron West, Inc. and The Lane Construction Corporation, holds the $704,975,000 design-build contract, awarded Oct. 1, 2019. 34 firms are named on the job, listed above.

Why is WSDOT suing Flatiron-Lane?

WSDOT sued the joint venture in 2023 over construction delays. The contract sets late-completion damages of up to $60,000 a day, and WSDOT's lawyers project the damages owed at more than $75 million. The joint venture filed counterclaims accusing WSDOT of "active interference" and "obstruction." The trial is expected in September 2027.

When will the I-405 express toll lanes between Renton and Bellevue open?

WSDOT expects summer 2027. The deadline was the end of 2025. A WSDOT internal report projects tolling in July 2027 and construction done in February 2028.

Where are the new I-405 toll lanes?

On I-405 from SR 167 in Renton to NE 6th Street in Bellevue, in King County, Washington, about 12 miles.

What is the biggest subcontract on the I-405 Renton to Bellevue job?

KLB Construction's, at $249,133,443, filed July 23, 2020. Rainier Welding ($85.0 million) and Valley Electric ($61.4 million) are next among the firms we list.

How many firms work on the I-405 Renton to Bellevue job?

220 firms besides the joint venture filed state prevailing wage forms on the contract. We list 34 of the biggest and best-tied, each with what it does and its office line.

Who is the electrical contractor on the I-405 Renton to Bellevue toll lanes?

Valley Electric Co. of Mt. Vernon, at $61.4 million. It hired Transcon, Saber Technologies and Trenchless Construction Services under it.

How can subcontractors and suppliers get on the I-405 Renton to Bellevue job?

Call the firms already on it, starting with Flatiron-Lane and its biggest subs: KLB Construction, Rainier Welding and Valley Electric. The newest sub filing on the contract is from Oct. 2, 2026.

What happens next on the I-405 Renton to Bellevue toll lanes?

Tolling is projected for July 2027 and the trial in WSDOT's lawsuit for September 2027. We'll update this page when a new filing or firm appears.

How we built this list

We read WSDOT's contract 9242 page and project page, WSDOT's Nov. 24, 2025 blog update, WSDOT's September 2026 photos, Lane's project page, a 2023 state outreach flyer, the joint venture's 2018 statement of qualifications, a Nov. 23, 2026 news investigation, and all 311 Washington L&I prevailing wage filings on contract 009242, on Nov. 24, 2026. Those filings name 220 firms besides the joint venture; we list the 34 that are the builders, the biggest subs and the firms with a clear trade, each from its own filing, plus Lane (named in WSDOT's award and in the joint venture's filing name). Each amount is what the firm stated on its filing, not money paid; a firm hired by another sub sits inside that sub's amount too, so the amounts overlap. The contract value is for the whole joint venture. The $883 million is the news investigation's figure, not a WSDOT release. We do not name the court; we did not confirm it. Left out: WSDOT (the owner), Sound Transit and King County (public partners), the losing 2019 proposers, WSDOT's toll vendor, the lawyers, firms named only in the 2018 proposal or only on their own websites, and about 190 smaller filers. Phones: most are the number the firm gave on its state filing; KLB, Valley Electric, Saber, Rainier Welding, Transcon, C & R Tractor, Camblin, Salinas, Holmberg, Concrete Technology and Lane are the main line on each firm's own site. First published Nov. 24, 2026. We'll update this page when a new filing, ruling or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 34 firms, free

All 34 firms on the I-405 Renton to Bellevue toll lanes

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.