What is being built on I-405 between Renton and Bellevue?
WSDOT is widening about 12 miles of I-405 between SR 167 in Renton and NE 6th Street in Bellevue. The job adds a lane each way and a two-lane express toll lane system, part of a toll lane network of about 40 miles. WSDOT calls the stretch one of the state's worst commutes.
The work rebuilds interchanges at NE Park Drive and NE 44th Street in Renton and at 112th Avenue SE and Coal Creek Parkway in Bellevue. It also builds 4 fish passage crossings, 47,656 sq ft of noise wall and 2.5 miles of paved Eastrail, the regional walking and biking trail.
How much do the I-405 Renton to Bellevue toll lanes cost?
The job was budgeted at $813 million. On Nov. 23, 2026, a news investigation put it at about $883 million, including an added funding need of about $45 million in the next legislative session.
The design-build contract itself is $704,975,000. WSDOT awarded it to Flatiron-Lane, a joint venture of Flatiron West, Inc. and The Lane Construction Corporation, on Oct. 1, 2019.
Why is WSDOT suing the I-405 builder?
The toll lanes were due by the end of 2025. In July 2025 a WSDOT program administrator wrote, "We know that the end of 2025 is not feasible." On Nov. 24, 2025, WSDOT told the public the lanes would open in summer 2027 and said it was taking the contractor to court.
WSDOT sued the joint venture in 2023 over construction delays. The contract sets late-completion damages of up to $60,000 a day, and WSDOT's lawyers wrote in July 2025 that the damages owed are projected to be more than $75 million. Court papers cite missed milestones, including "toll infrastructure completion" and "toll commencement." The joint venture filed counterclaims accusing WSDOT of "active interference" and "obstruction." The trial is expected to begin in September 2027.
When will the I-405 Renton to Bellevue toll lanes open?
WSDOT expects the express toll lanes to open in summer 2027. A WSDOT internal report dated Aug. 6, 2026 projects tolling to begin in July 2027, with construction on site not finished until February 2028.
Crews set the toll gantries over northbound and southbound I-405 during weekend closures in September 2026.
Who is building the I-405 Renton to Bellevue toll lanes?
Flatiron-Lane is the design-builder. State prevailing wage filings on the contract name 220 firms besides the joint venture. The biggest subcontract is KLB Construction's, at $249,133,443, filed July 23, 2020. Rainier Welding's steel work is $85.0 million and Valley Electric's electrical work is $61.4 million.
On design, Wood (now part of WSP) filed $50.1 million, Parsons $21.7 million and David Evans and Associates $7.0 million. Each amount is what the firm stated on its filing; a firm hired by another sub is counted inside that sub's work too, so the amounts do not add up to the contract. 34 firms in all are on the list below.
Who WSDOT hired before
WSDOT keeps going back to the same I-405 team: Flatiron built the earlier Bellevue to Lynnwood toll lanes, and the joint venture re-hired that job's subcontractors and consultants for Renton to Bellevue.
- Flatiron: builder on I-405 Bellevue to Lynnwood widening and express toll lanes (Flatiron's first I-405 job), Bellevue to Lynnwood, WA, 2015. Also on this job.
- Valley Electric: electrical on SR 520 Eastside HOV project, Bellevue/Kirkland, WA, 2014. Also on this job.
- Kleinfelder: quality testing on I-405 Bellevue to Lynnwood (BTL) design-build, Bellevue to Lynnwood, WA, 2015.
- Hart Crowser, Exeltech and EnviroIssues: geotech, design and outreach on I-405 Bellevue to Lynnwood (BTL) design-build, Bellevue to Lynnwood, WA, 2015.
These are earlier or other jobs for the same owner. They are not counted in the 34 firms on this job.
How do the ways into the I-405 Renton to Bellevue job compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the I-405 Renton to Bellevue toll lanes | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose work matches what you sell |
Who should go after the I-405 Renton to Bellevue job?
| Concrete, steel, rebar and paving suppliers | KLB Construction's $249.1 million subcontract, Rainier Welding's $85.0 million steel work, and the rebar, precast and paving firms on the list. |
|---|
| Electrical and traffic systems distributors | Valley Electric's $61.4 million electrical work, with Transcon, Saber Technologies and Trenchless Construction Services under it. |
|---|
| Equipment, traffic control and site service firms | A job with a new sub filing as late as October 2026, and traffic control, striping, crane, landscaping and trucking firms already on it. |
|---|
What should you do next on the I-405 Renton to Bellevue job?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the I-405 Renton to Bellevue widening and express toll lanes (WSDOT contract 9242).
- Watch for the start of tolling, projected for July 2027.
Questions people ask about the I-405 Renton to Bellevue toll lanes
How much do the I-405 Renton to Bellevue toll lanes cost?
The job was budgeted at $813 million and is now estimated at about $883 million, reported Nov. 23, 2026, including an added funding need of about $45 million in the next legislative session. The design-build contract is $704,975,000.
Who is building the I-405 Renton to Bellevue toll lanes?
Flatiron-Lane, a joint venture of Flatiron West, Inc. and The Lane Construction Corporation, holds the $704,975,000 design-build contract, awarded Oct. 1, 2019. 34 firms are named on the job, listed above.
Why is WSDOT suing Flatiron-Lane?
WSDOT sued the joint venture in 2023 over construction delays. The contract sets late-completion damages of up to $60,000 a day, and WSDOT's lawyers project the damages owed at more than $75 million. The joint venture filed counterclaims accusing WSDOT of "active interference" and "obstruction." The trial is expected in September 2027.
When will the I-405 express toll lanes between Renton and Bellevue open?
WSDOT expects summer 2027. The deadline was the end of 2025. A WSDOT internal report projects tolling in July 2027 and construction done in February 2028.
Where are the new I-405 toll lanes?
On I-405 from SR 167 in Renton to NE 6th Street in Bellevue, in King County, Washington, about 12 miles.
What is the biggest subcontract on the I-405 Renton to Bellevue job?
KLB Construction's, at $249,133,443, filed July 23, 2020. Rainier Welding ($85.0 million) and Valley Electric ($61.4 million) are next among the firms we list.
How many firms work on the I-405 Renton to Bellevue job?
220 firms besides the joint venture filed state prevailing wage forms on the contract. We list 34 of the biggest and best-tied, each with what it does and its office line.
Who is the electrical contractor on the I-405 Renton to Bellevue toll lanes?
Valley Electric Co. of Mt. Vernon, at $61.4 million. It hired Transcon, Saber Technologies and Trenchless Construction Services under it.
How can subcontractors and suppliers get on the I-405 Renton to Bellevue job?
Call the firms already on it, starting with Flatiron-Lane and its biggest subs: KLB Construction, Rainier Welding and Valley Electric. The newest sub filing on the contract is from Oct. 2, 2026.
What happens next on the I-405 Renton to Bellevue toll lanes?
Tolling is projected for July 2027 and the trial in WSDOT's lawsuit for September 2027. We'll update this page when a new filing or firm appears.
How we built this list
We read WSDOT's contract 9242 page and project page, WSDOT's Nov. 24, 2025 blog update, WSDOT's September 2026 photos, Lane's project page, a 2023 state outreach flyer, the joint venture's 2018 statement of qualifications, a Nov. 23, 2026 news investigation, and all 311 Washington L&I prevailing wage filings on contract 009242, on Nov. 24, 2026. Those filings name 220 firms besides the joint venture; we list the 34 that are the builders, the biggest subs and the firms with a clear trade, each from its own filing, plus Lane (named in WSDOT's award and in the joint venture's filing name). Each amount is what the firm stated on its filing, not money paid; a firm hired by another sub sits inside that sub's amount too, so the amounts overlap. The contract value is for the whole joint venture. The $883 million is the news investigation's figure, not a WSDOT release. We do not name the court; we did not confirm it. Left out: WSDOT (the owner), Sound Transit and King County (public partners), the losing 2019 proposers, WSDOT's toll vendor, the lawyers, firms named only in the 2018 proposal or only on their own websites, and about 190 smaller filers. Phones: most are the number the firm gave on its state filing; KLB, Valley Electric, Saber, Rainier Welding, Transcon, C & R Tractor, Camblin, Salinas, Holmberg, Concrete Technology and Lane are the main line on each firm's own site. First published Nov. 24, 2026. We'll update this page when a new filing, ruling or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.