What is being built to replace Harrisburg's South Bridge?
The South Bridge carries I-83 over the Susquehanna River between Lemoyne Borough in Cumberland County and the City of Harrisburg in Dauphin County. More than 125,000 vehicles cross it every day, the most of any bridge in the Harrisburg area. It opened in 1960 and cost $6,350,261 to build.
PennDOT will replace it with a new river bridge. The job also reconfigures the Lemoyne interchange, replaces the South Third Street bridge in Lemoyne, and rebuilds the viaduct from the river to Route 230 (Cameron Street), including the Front Street and 2nd Street interchange. The contract is S.R. 0083 Section 094.
There will be no bike or walking path on the new river bridge. PennDOT says bikes and walkers get a longer, wider South Third Street bridge instead.
How much is the I-83 South Bridge contract?
PennDOT opened two bids on Nov. 13, 2026. The apparent low bid is $1,289,055,555.55. The other, from a joint venture of Wagman Heavy Civil, J.D. Eckman and Brayman Construction, is $1,586,266,706.63. That is about $297 million apart, the math.
In March 2026, PennDOT showed engineers a $1.13 billion construction estimate and $1,275,300,000 for the whole job: $11.7 million for early engineering, $26.3 million for final design, $20.3 million for railroad work, $40 million for utilities and $79 million for land. The low bid is about $159 million over the construction estimate, the math.
In 2024 the project won a $500 million federal Bridge Investment Program grant, which PennDOT calls the largest federal transportation-project grant in state history.
Who is the apparent low bidder on the South Bridge?
PennDOT says the apparent low bidder is a joint venture of Joseph B. Fay Company and New Enterprise Stone & Lime Company, Inc. Fay is the Pittsburgh-based U.S. construction arm of Israel's Shikun & Binui, which reported an 80% share. New Enterprise, from New Enterprise, PA, holds the other 20%.
It is a bid, not an award. PennDOT says the contract will be awarded and a notice to proceed issued within six to eight weeks if the bid is in order. Shikun & Binui's CEO says the bridge will be built in stages to keep traffic moving, and the company says the contract covers construction, not design, so it does not carry the design risk.
PennDOT chose to bid the job as one single construction contract, and every bidder had to attend a pre-bid meeting in Harrisburg on Aug. 19, 2026. The winner must take on 10 trainees from PennDOT's On-the-Job Training Program.
When will work on the South Bridge start?
PennDOT expects construction to begin in 2027 and last through 2039. In November 2026, right before the bids opened, PennDOT sent crane crews to inspect the old bridge two weeks running: northbound Nov. 4 to 6 and southbound Nov. 9 to 13.
The fight so far has been over the railroads. In 2025 Norfolk Southern objected that the planned Amtrak overhead wire towers on the east-shore viaduct would get in the way of its future operations. It took the case to the state utility commission with an AECOM engineer as its witness, then withdrew the objection on May 13, 2026. PennDOT filed the final Section 094 construction drawings with the commission on Oct. 9, 2026.
Earlier, in 2022, Cumberland County and several towns sued over PennDOT's plan to toll up to nine major bridges, the South Bridge among them, and a judge halted the plan.
Who else is on the South Bridge job?
HNTB Corporation, from its Harrisburg office, is PennDOT's design engineer, and Navarro & Wright wrote the final design noise study for HNTB. HDR led the federal Environmental Assessment, with KCI on highway design and traffic, NTM Engineering on river hydraulics, Gannett Fleming on wetlands, JMT, ASC Group on archaeology and Markosky on historic properties.
Seventeen utilities and railroads are named on PennDOT's filings: PPL Electric, UGI, Amtrak, Norfolk Southern, Capital Region Water, Pennsylvania American Water and 11 phone, cable and fiber carriers. They are not hired builders. They are who to call about moving lines, gas mains and overhead wires, the work PennDOT budgets $40 million for.
No subcontractor list is public yet. It comes after the award, so the time to reach the low bidders is now.
Who PennDOT hired before
PennDOT District 8 already has New Enterprise rebuilding the I-83 Capital Beltway in Harrisburg, and Fay won PennDOT's Layton Bridge over the Youghiogheny River in January 2026.
- New Enterprise Stone & Lime: contractor on I-83 East Shore Section 3, first contract, Harrisburg, PA, 2025. Also on this job.
- J.D. Eckman: contractor on I-83 East Shore Section 3, second contract, Harrisburg, PA, 2025.
- Fay, S&B USA Construction: contractor on Layton Bridge replacement over the Youghiogheny River, Fayette County, PA, 2026. Also on this job.
- HNTB: engineer on I-83 South Bridge inspection and rehabilitation, Harrisburg, PA, 2006. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 29 firms on this job.
How do the ways into the I-83 South Bridge job compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on the I-83 South Bridge | Every supplier, distributor and sales rep | A conversation with a firm already on the job | Start with the firms whose work matches what you sell |
| The low bidders before the award | A call to Joseph B. Fay Company or New Enterprise Stone & Lime about subcontracts and supply | Subcontractors, suppliers and equipment dealers | A place on a $1.289 billion job that runs 2027 through 2039 | Not awarded yet; PennDOT expects the award within six to eight weeks of Nov. 13, 2026 |
Who should go after the I-83 South Bridge job?
| Steel, concrete, aggregate and marine suppliers | A $1.289 billion bridge, interchange and viaduct job over 12 years, with Fay and New Enterprise as the apparent low bidders. |
|---|
| Engineering, survey, testing and inspection firms | HNTB's design team and the Environmental Assessment firms, plus the inspection and testing work that comes with a job this size. |
|---|
| Utility and railroad contractors | 17 utilities and railroads, with $40 million set aside for utility work and $20.3 million for railroad work in PennDOT's estimate. |
|---|
What should you do next on the I-83 South Bridge?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the I-83 South Bridge replacement in Harrisburg.
- Watch for PennDOT's award and notice to proceed, expected within six to eight weeks of the Nov. 13, 2026 bid opening.
Questions people ask about the I-83 South Bridge
How much will the new I-83 South Bridge cost?
The apparent low bid to build it is $1,289,055,555.55, opened by PennDOT on Nov. 13, 2026. It is a bid, not yet an award. In March 2026 PennDOT put construction at $1.13 billion and the whole job, with design, land, railroad and utility work, at $1,275,300,000.
Who won the I-83 South Bridge contract?
No one yet. The apparent low bidder is a joint venture of Joseph B. Fay Company and New Enterprise Stone & Lime Company, Inc. PennDOT says the contract will be awarded and a notice to proceed issued within six to eight weeks of the Nov. 13, 2026 bid opening if the bid is in order.
How many bids did PennDOT get for the South Bridge?
Two. Fay and New Enterprise bid $1,289,055,555.55. A joint venture of Wagman Heavy Civil, J.D. Eckman and Brayman Construction bid $1,586,266,706.63, about $297 million more.
When will the I-83 South Bridge be built?
PennDOT expects construction to begin in 2027 and last through 2039. The bridge will be built in stages so traffic keeps moving.
What does the South Bridge project include?
A new bridge over the Susquehanna River, a reconfigured Lemoyne interchange, a new South Third Street bridge in Lemoyne, and a rebuilt viaduct from the river to Route 230 (Cameron Street), including the Front Street and 2nd Street interchange.
Who designed the new South Bridge?
HNTB Corporation is PennDOT's design engineer for the job, S.R. 0083 Section 094. HDR led the Environmental Assessment, with KCI, NTM Engineering, Gannett Fleming, JMT, ASC Group and Markosky on the study team.
Who is paying for the South Bridge replacement?
PennDOT owns the job. In 2024 it won a $500 million federal Bridge Investment Program grant for the bridge, which PennDOT calls the largest federal transportation-project grant in state history.
How can subcontractors and suppliers get on the South Bridge job?
Call the low bidders, Joseph B. Fay Company and New Enterprise Stone & Lime, now, before the award. No subcontractor list is public until after the award. The utilities and railroads on the list move their own lines and wires, so they are calls to make about that work.
Will the new South Bridge have a bike lane?
No. PennDOT says there will not be a bicycle and pedestrian path on the new river bridge. Bikes and walkers get a longer, wider South Third Street bridge in Lemoyne instead.
How we built this list
We read PennDOT's Nov. 13, 2026 bid release, its project FAQ and bid preparation pages, its March 2026 project overview, the December 2025 final design noise report, the October 2023 Environmental Assessment, PennDOT's and Norfolk Southern's filings at the Pennsylvania Public Utility Commission (including the final Section 094 construction drawings of Oct. 9, 2026), PennDOT's inspection notices, and news reports, on Nov. 23, 2026. We kept each firm a public record names on this project. The bid is the joint venture's, not one firm's share; the 80/20 split is Shikun & Binui's report. The Environmental Assessment firms worked on the study, not the build. AECOM works for Norfolk Southern, not PennDOT. The 17 utilities and railroads are named on PennDOT's filings as owners of lines in the work area, not as hired builders. Left out: PennDOT, the federal funder, the losing bidders, law firms, local governments, government-owned utilities, firms on older South Bridge work, and two contractors whose staff appear only as contacts for a utility. Phones are each firm's own line from its own site; Fay's is S&B USA's Pittsburgh headquarters and Markosky's is its headquarters, and we found no main line for HDR, Gannett Fleming, AECOM or most utilities. First published Nov. 23, 2026. We'll update this page when PennDOT awards the contract or a new filing or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 23, 2026- PennDOT: apparent low bidder for the I-83 bridge replacement (Nov. 13, 2026)
- PennDOT: I-83 South Bridge frequently asked questions
- PennDOT: I-83 South Bridge construction bid preparation resources
- PennDOT: I-83 South Bridge project overview for ACEC (March 2026)
- PennDOT: final design highway traffic noise report, S.R. 0083 Section 094 (Dec. 19, 2025)
- FHWA and PennDOT: I-83 South Bridge Environmental Assessment (October 2023)
- PA PUC: PennDOT filing on the I-83 South Bridge early Amtrak work (July 8, 2025)
- PA PUC: Norfolk Southern prehearing memorandum, viaduct crossing (March 4, 2026)
- PA PUC: Norfolk Southern withdrawal (May 13, 2026)
- PA PUC: final drawings for construction, S.R. 0083 Section 094 (Oct. 9, 2026)
- PennDOT: southbound South Bridge inspection (Nov. 9-13, 2026)
- Ynet: Shikun & Binui's share of the South Bridge bid (Nov. 16, 2026)
- Construction Review Online: Shikun & Binui on the South Bridge (Nov. 17, 2026)
- WHTM abc27: I-83 bridge project draws low bid (Nov. 13, 2026)
- WHYY: judge halts bridge tolling plans (May 2022)
- American Infrastructure: PennDOT advances the I-83 South Bridge replacement (Nov. 16, 2026)
- PennDOT District 8 release 'Second Contract Awarded for East Shore Section 3 of the I-83 Capital Beltway Project', 2025
- S&B USA: Fay awarded PennDOT contract for the Layton Bridge Replacement Project (2026-01-14)
- Roads & Bridges: PENNDOT selects HNTB for I-83 South Bridge project (2006-09-15)