What is Intel building in New Albany, Ohio?
Intel is building two chip factories, called fabs, at 11511 Green Chapel Road NW in New Albany, in Jersey Township, Licking County, Ohio. Intel calls the site Ohio One. The two fabs are known as Mod 1 and Mod 2.
Phase 1 is 2.5 million sq ft, with 600,000 sq ft of cleanrooms. Around the fabs are a boiler and chiller plant, an ultra pure water building, a water treatment and reclamation building, an air separation unit, a substation and an office building.
How much is the Intel Ohio chip plant?
Intel plans to invest more than $28 billion in the two fabs. In 2022 the figure was more than $20 billion. The $28 billion is a planned total that includes equipment, not a construction contract.
Intel's report to the state says it spent $3,733,115,863 on the site through 2024, $2,276,015,078 of it in 2024, with $3.2 billion more under contract. It bought $2,016,245,168 from megaproject suppliers in 2024 alone. By the end of 2025, Intel had spent about $5.26 billion, from its letter to the state as reported. Ohio paid Intel a $600 million onshoring grant.
How far along is the Intel Ohio chip plant?
By the end of 2024, crews had built the major underground corridors, poured about 130,000 cubic yards of concrete in Fab 1 and 50,000 in Fab 2, and set 600 precast columns and 320 slabs, per Intel's report. Steel was going up on the support buildings.
On Oct. 21, 2026, crews set the first major structural truss on the first fab. Intel now plans to finish Mod 1 in 2030, with chips from 2030 to 2031, and Mod 2 in 2031, with chips in 2032. The plant was first due to make chips in 2025, so it is at least five years behind schedule.
The delays have frustrated Licking County. A county commissioner put it this way: "Promises made but promises not kept."
Who is building the Intel Ohio chip plant?
Bechtel designs and builds Phase 1, the two fabs, under a deal announced Nov. 28, 2022. Before that, in May 2022, Intel picked an Ohio team led by Gilbane Building Company for the early excavation and site work, with local partners including McDaniel's Construction and Northstar Contracting for staff augmentation and consulting. We found no record of those two firms on the job after 2022.
Which firms are Intel's top Ohio suppliers on the plant?
Each year Intel files a report with the state that lists its top 25 Ohio direct suppliers on the project. The 2024 list includes Bechtel, Gilbane, Lithko Contracting, the MWH-Kokosing Joint Venture, AEP Ohio, Barnhart Plant Services, Siemens Industry, Trane, Linde Engineering, Evoqua, Trionetics and Clean Harbors, plus engineers SSOE, EMH&T, CTL Engineering and Geotechnical Consultants. The 2023 list adds HDR, Brown and Caldwell, Colin Gordon & Associates and Stonhard.
The reports do not say what each firm does on the job or what it was paid. The 2024 report does say underground work for cable pulls from the AEP switchyard to the plant's own substation was in progress. The electrical, mechanical and steel subcontractors under Bechtel are not published. 22 firms in all are on the list below.
Who Intel hired before
On its Arizona fabs Intel has gone back to the same pair again and again: Hoffman Construction to build and Jacobs to design. Ohio broke that pattern, with Bechtel as the builder, so none of these firms is on the Ohio list yet.
- Hoffman Construction: builder (general contractor) on Fab 52 and Fab 62, Intel's Ocotillo campus, Chandler, AZ, started 2021.
- Jacobs: designer (lead design and engineering) on Fab 52, Intel's Ocotillo campus (ENR Southwest Best Projects 2025, Project of the Year), Chandler, AZ, 2021-2025.
- Hoffman Construction: builder on Fab 42, 1.3 million sq ft, Intel's Ocotillo campus, Chandler, AZ, opened 2020.
- Rosendin: electrical on the $7 billion retrofit of Fab 42, Chandler, AZ, before 2021.
These are earlier or other jobs for the same owner. They are not counted in the 22 firms on this job.
How do the ways into the Intel Ohio chip plant compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The firms on the job | A call to the firm's office, asking for the team on Intel's Ohio One chip plant in New Albany | Every supplier, distributor and sales rep | A conversation with a firm already working on the job | Start with the firms whose trade matches what you sell |
Who should go after the Intel Ohio chip plant?
| Electrical and power reps | Siemens Industry and AEP Ohio, both on Intel's top Ohio supplier list, on a site where underground work for cable pulls from the AEP switchyard to the plant's own substation was in progress at the end of 2024. |
|---|
| Concrete, steel and site suppliers | Lithko Contracting and Barnhart Plant Services, on a job that poured about 130,000 cubic yards of concrete into Fab 1 by the end of 2024. |
|---|
| Mechanical and water reps | Trane, Evoqua and Trionetics on Intel's supplier list, and the MWH-Kokosing Joint Venture, on a plant with its own chiller plant and water buildings. |
|---|
What should you do next on the Intel Ohio chip plant?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on Intel's Ohio One chip plant on Green Chapel Road in New Albany.
Questions people ask about the Intel Ohio chip plant
How much is the Intel Ohio chip plant?
Intel plans to invest more than $28 billion in the two fabs in New Albany. That is a planned total that includes equipment, not a construction contract. Intel told the state it had spent $3,733,115,863 on the site through 2024.
Who is building the Intel plant in Ohio?
Bechtel designs and builds Phase 1, the two fabs. Gilbane led the early excavation and site work team. 22 firms are named on the job, listed above.
When will the Intel Ohio plant open?
Intel plans to finish the first fab in 2030 and make chips there from 2030 to 2031. The second fab is due in 2031, with chips in 2032. The plant was first due to make chips in 2025.
Why is the Intel Ohio plant delayed?
Intel slowed the pace of work in Ohio. In February 2025 it moved the first fab's finish to 2030. Chips were first due in 2025, so the plant is at least five years behind schedule.
Where is the Intel Ohio plant?
It is at 11511 Green Chapel Road NW in New Albany, in Jersey Township, Licking County, Ohio, east of Columbus.
How big is the Intel Ohio plant?
Phase 1 is two fabs with 2.5 million sq ft, including 600,000 sq ft of cleanrooms, plus a chiller plant, water buildings, an air separation unit, a substation and an office building.
How much has Intel spent in Ohio so far?
Intel told the state it spent $3.73 billion on the site through 2024, with $3.2 billion more under contract. By the end of 2025 it had spent about $5.26 billion, from Intel's letter to the state as reported.
How much does Intel pay Ohio suppliers?
Intel bought $2,016,245,168 from megaproject suppliers in 2024, per its report to the state. It does not publish what each firm was paid.
What is the newest news on the Intel Ohio plant?
On Oct. 21, 2026, crews set the first major structural truss on the first fab. We'll update this page when a new firm or record appears.
How we built this list
We read Intel's 2023 and 2024 reports to the Ohio Department of Development, which list the top 25 Ohio direct suppliers on the project, plus Intel's and Bechtel's own releases, Intel's construction timeline and the news. Each firm on the list is named on the job by one of those records. The reports list firms in A to Z order and do not say what each firm does or what it was paid, so a firm's kind comes from its own line of work, not from the record. McDaniel's and Northstar were named by Intel in May 2022 for staff augmentation and consulting on Gilbane's early site work team; we found no later record of either on the job, so their rows say 2022 only. The site address comes from Ohio EPA's public construction stormwater permit for the campus. The $5.26 billion is from Intel's 2025 letter to the state as reported in the news; we did not find the letter itself. Left out: Intel (the owner), the land seller, lawyers, the title company, cost, safety and environmental consultants, freight firms, a printer, a distributor and a union. Phones are each firm's own main or office line from its own site; Bechtel, HDR and Barnhart are head offices, not Ohio. We found no main line on the sites of MWH-Kokosing, Siemens, Trane and Linde, and no site for McDaniel's or Northstar. First published Nov. 21, 2026. We'll update this page when a new record or firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 21, 2026- Intel newsroom: Ohio One Construction Timeline Update (Feb. 28, 2025)
- Intel newsroom: Building America's Capacity to Innovate (Oct. 2026)
- Intel Ohio Onshoring Incentive 2024 Annual Report to the Ohio Department of Development (Feb. 27, 2025)
- Intel 2023 Onshoring Annual Report to the Ohio Department of Development (Mar. 1, 2024)
- Intel newsroom: Intel Announces Next US Site with Landmark Investment in Ohio (Jan. 21, 2022)
- Bechtel: Bechtel to build Intel's semiconductor manufacturing facilities in Ohio (Nov. 28, 2022)
- Intel: Intel Selects Diverse Ohio-Based Team to Lead Early Excavation Work for Ohio Fabs (May 26, 2022)
- ENR: Intel slows speed of construction of $28B in semiconductor plants in Ohio (July 28, 2025)
- CNBC: Intel hits construction milestone at Ohio chip fab (Oct. 21, 2026)
- WHIO: Intel spent $1.53B in Ohio in 2025 (2026)
- Athens Messenger: Intel plant delays frustrate Licking County (Dec. 2, 2025)
- ENR, 'Intel's $20B Arizona Chip Plant Project Poised to Make National Impact', 2024-03-19
- ENR, 'Offsite Assembly, High Velocity Design Help Deliver Arizona Intel Fab Plant', 2026-03-13
- ENR, 'Intel Breaks Ground on Arizona Microchip Plant Expansion', 2021-10-04
- ENR, 'Large Jobs Put Rosendin in a Power Position', 2021-08-31