Who's building Intel's chip plant in New Albany, Ohio

Intel's $28 billion chip plant in New Albany, Ohio just set its first major truss, and it is at least five years late.

By Porter Stanley. Updated .

Intel is building two chip factories, called Ohio One, at 11511 Green Chapel Road NW in New Albany, Licking County, Ohio. Intel plans to invest more than $28 billion in the two fabs. On Oct. 21, 2026, crews set the first major structural truss on the first fab. The plant was first due to make chips in 2025; Intel now plans to finish the first fab in 2030, at least five years late. Bechtel designs and builds Phase 1. 22 firms are named on the job; the list below has all 22.

$28BIntel's planned investment, two fabs
$3.73BSpent on the site through 2024
2030First fab's new finish; chips were due in 2025
22Firms named on the job

Get all 22 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Get all 22 firms and who to call

Each one with what it does on the job and its main office line. Free: your email sets up your free account.

We send the list to this address, so use one you check. We never share it.

Who are the 22 firms on the Intel Ohio chip plant?

We list the 22 firms named on Intel's Ohio One chip plant in New Albany, one row each, grouped by kind of firm, with where each name comes from.

1Latest recordFeb 27, 2025

Bechtel

Designs and builds Phase 1 of the plant: two fabs, 2.5 million sq ft with 600,000 sq ft of cleanrooms on Intel's Ohio One chip plant in New Albany, Licking County, OH

Intel Ohio One chip fabs, 11511 Green Chapel Rd NW, New Albany (Licking County), OH

Phase 1 design and build, announced Nov. 28, 2022; also on Intel's 2024 top 25 Ohio supplier list. No contract value is published

Work: Designs and builds Phase 1 of the plant: two fabs, 2.5 million sq ft with 600,000 sq ft of cleanrooms

Who to call: Bechtel
Bechtel office line
(Reston, VA)
(571) 392-6300

The opportunity: Bechtel, Nov. 28, 2022: 'Bechtel will design and build Phase 1 of the Intel Ohio project, a total of 2.5 million square feet of facility.' Intel's 2024 report lists '3. Bechtel'; its 2023 report lists '2. Bechtel Manufacturing & Technology, Inc.' The report lists its top 25 in A to Z order, so the number is not a rank. The phone is the Reston, VA headquarters line.

2Latest recordFeb 27, 2025

Gilbane Building Company

Led the early excavation and site work team for the two fabs from 2022; still on Intel's top 25 Ohio supplier list in 2023 and 2024 on Intel's Ohio One chip plant in New Albany, Licking County, OH

Intel Ohio One chip fabs, 11511 Green Chapel Rd NW, New Albany (Licking County), OH

Early excavation team named May 26, 2022; Intel's 2024 report to the state, dated Feb. 27, 2025; no amount per firm is published. Intel bought $2,016,245,168 from all its megaproject suppliers in 2024

Work: Led the early excavation and site work team for the two fabs from 2022; still on Intel's top 25 Ohio supplier list in 2023 and 2024

Who to call: Gilbane Building Company
Gilbane Building Company office line
(800) 445-2263

The opportunity: Intel, May 26, 2022: Intel picked an Ohio team led by Gilbane for the early excavation work. Intel's 2024 report lists '14. Gilbane'. The report lists its top 25 in A to Z order, so the number is not a rank. The phone is 1-800-GILBANE.

3Latest recordFeb 27, 2025

Lithko Contracting

Listed in Intel's 2023 and 2024 reports to the state as a top 25 Ohio direct supplier to the project; also named in July 2025 trade press coverage of the job on Intel's Ohio One chip plant in New Albany, Licking County, OH

Intel Ohio One chip fabs, 11511 Green Chapel Rd NW, New Albany (Licking County), OH

Intel's 2024 report to the state, dated Feb. 27, 2025; no amount per firm is published. Intel bought $2,016,245,168 from all its megaproject suppliers in 2024

Work: Listed in Intel's 2023 and 2024 reports to the state as a top 25 Ohio direct supplier to the project; also named in July 2025 trade press coverage of the job

Who to call: Lithko Contracting
Lithko Contracting office line
(West Chester, OH)
(513) 564-2000

The opportunity: Intel's 2024 report lists '16. Lithko Contracting, LLC'. The report lists its top 25 in A to Z order, so the number is not a rank. The report does not say what each firm does; the kind comes from the firm's line of work, concrete.

What is Intel building in New Albany, Ohio?

Intel is building two chip factories, called fabs, at 11511 Green Chapel Road NW in New Albany, in Jersey Township, Licking County, Ohio. Intel calls the site Ohio One. The two fabs are known as Mod 1 and Mod 2.

Phase 1 is 2.5 million sq ft, with 600,000 sq ft of cleanrooms. Around the fabs are a boiler and chiller plant, an ultra pure water building, a water treatment and reclamation building, an air separation unit, a substation and an office building.

How much is the Intel Ohio chip plant?

Intel plans to invest more than $28 billion in the two fabs. In 2022 the figure was more than $20 billion. The $28 billion is a planned total that includes equipment, not a construction contract.

Intel's report to the state says it spent $3,733,115,863 on the site through 2024, $2,276,015,078 of it in 2024, with $3.2 billion more under contract. It bought $2,016,245,168 from megaproject suppliers in 2024 alone. By the end of 2025, Intel had spent about $5.26 billion, from its letter to the state as reported. Ohio paid Intel a $600 million onshoring grant.

How far along is the Intel Ohio chip plant?

By the end of 2024, crews had built the major underground corridors, poured about 130,000 cubic yards of concrete in Fab 1 and 50,000 in Fab 2, and set 600 precast columns and 320 slabs, per Intel's report. Steel was going up on the support buildings.

On Oct. 21, 2026, crews set the first major structural truss on the first fab. Intel now plans to finish Mod 1 in 2030, with chips from 2030 to 2031, and Mod 2 in 2031, with chips in 2032. The plant was first due to make chips in 2025, so it is at least five years behind schedule.

The delays have frustrated Licking County. A county commissioner put it this way: "Promises made but promises not kept."

Who is building the Intel Ohio chip plant?

Bechtel designs and builds Phase 1, the two fabs, under a deal announced Nov. 28, 2022. Before that, in May 2022, Intel picked an Ohio team led by Gilbane Building Company for the early excavation and site work, with local partners including McDaniel's Construction and Northstar Contracting for staff augmentation and consulting. We found no record of those two firms on the job after 2022.

Which firms are Intel's top Ohio suppliers on the plant?

Each year Intel files a report with the state that lists its top 25 Ohio direct suppliers on the project. The 2024 list includes Bechtel, Gilbane, Lithko Contracting, the MWH-Kokosing Joint Venture, AEP Ohio, Barnhart Plant Services, Siemens Industry, Trane, Linde Engineering, Evoqua, Trionetics and Clean Harbors, plus engineers SSOE, EMH&T, CTL Engineering and Geotechnical Consultants. The 2023 list adds HDR, Brown and Caldwell, Colin Gordon & Associates and Stonhard.

The reports do not say what each firm does on the job or what it was paid. The 2024 report does say underground work for cable pulls from the AEP switchyard to the plant's own substation was in progress. The electrical, mechanical and steel subcontractors under Bechtel are not published. 22 firms in all are on the list below.

Who Intel hired before

On its Arizona fabs Intel has gone back to the same pair again and again: Hoffman Construction to build and Jacobs to design. Ohio broke that pattern, with Bechtel as the builder, so none of these firms is on the Ohio list yet.

  • Hoffman Construction: builder (general contractor) on Fab 52 and Fab 62, Intel's Ocotillo campus, Chandler, AZ, started 2021.
  • Jacobs: designer (lead design and engineering) on Fab 52, Intel's Ocotillo campus (ENR Southwest Best Projects 2025, Project of the Year), Chandler, AZ, 2021-2025.
  • Hoffman Construction: builder on Fab 42, 1.3 million sq ft, Intel's Ocotillo campus, Chandler, AZ, opened 2020.
  • Rosendin: electrical on the $7 billion retrofit of Fab 42, Chandler, AZ, before 2021.

These are earlier or other jobs for the same owner. They are not counted in the 22 firms on this job.

How do the ways into the Intel Ohio chip plant compare?

Way inWhat it isBest forWhat you getThe limit
The firms on the jobA call to the firm's office, asking for the team on Intel's Ohio One chip plant in New AlbanyEvery supplier, distributor and sales repA conversation with a firm already working on the jobStart with the firms whose trade matches what you sell

Who should go after the Intel Ohio chip plant?

Electrical and power repsSiemens Industry and AEP Ohio, both on Intel's top Ohio supplier list, on a site where underground work for cable pulls from the AEP switchyard to the plant's own substation was in progress at the end of 2024.
Concrete, steel and site suppliersLithko Contracting and Barnhart Plant Services, on a job that poured about 130,000 cubic yards of concrete into Fab 1 by the end of 2024.
Mechanical and water repsTrane, Evoqua and Trionetics on Intel's supplier list, and the MWH-Kokosing Joint Venture, on a plant with its own chiller plant and water buildings.

What should you do next on the Intel Ohio chip plant?

  1. Pick the firms whose work matches what you sell, and call them this week.
  2. Ask for the team on Intel's Ohio One chip plant on Green Chapel Road in New Albany.

Questions people ask about the Intel Ohio chip plant

How much is the Intel Ohio chip plant?

Intel plans to invest more than $28 billion in the two fabs in New Albany. That is a planned total that includes equipment, not a construction contract. Intel told the state it had spent $3,733,115,863 on the site through 2024.

Who is building the Intel plant in Ohio?

Bechtel designs and builds Phase 1, the two fabs. Gilbane led the early excavation and site work team. 22 firms are named on the job, listed above.

When will the Intel Ohio plant open?

Intel plans to finish the first fab in 2030 and make chips there from 2030 to 2031. The second fab is due in 2031, with chips in 2032. The plant was first due to make chips in 2025.

Why is the Intel Ohio plant delayed?

Intel slowed the pace of work in Ohio. In February 2025 it moved the first fab's finish to 2030. Chips were first due in 2025, so the plant is at least five years behind schedule.

Where is the Intel Ohio plant?

It is at 11511 Green Chapel Road NW in New Albany, in Jersey Township, Licking County, Ohio, east of Columbus.

How big is the Intel Ohio plant?

Phase 1 is two fabs with 2.5 million sq ft, including 600,000 sq ft of cleanrooms, plus a chiller plant, water buildings, an air separation unit, a substation and an office building.

How much has Intel spent in Ohio so far?

Intel told the state it spent $3.73 billion on the site through 2024, with $3.2 billion more under contract. By the end of 2025 it had spent about $5.26 billion, from Intel's letter to the state as reported.

How much does Intel pay Ohio suppliers?

Intel bought $2,016,245,168 from megaproject suppliers in 2024, per its report to the state. It does not publish what each firm was paid.

What is the newest news on the Intel Ohio plant?

On Oct. 21, 2026, crews set the first major structural truss on the first fab. We'll update this page when a new firm or record appears.

How we built this list

We read Intel's 2023 and 2024 reports to the Ohio Department of Development, which list the top 25 Ohio direct suppliers on the project, plus Intel's and Bechtel's own releases, Intel's construction timeline and the news. Each firm on the list is named on the job by one of those records. The reports list firms in A to Z order and do not say what each firm does or what it was paid, so a firm's kind comes from its own line of work, not from the record. McDaniel's and Northstar were named by Intel in May 2022 for staff augmentation and consulting on Gilbane's early site work team; we found no later record of either on the job, so their rows say 2022 only. The site address comes from Ohio EPA's public construction stormwater permit for the campus. The $5.26 billion is from Intel's 2025 letter to the state as reported in the news; we did not find the letter itself. Left out: Intel (the owner), the land seller, lawyers, the title company, cost, safety and environmental consultants, freight firms, a printer, a distributor and a union. Phones are each firm's own main or office line from its own site; Bechtel, HDR and Barnhart are head offices, not Ohio. We found no main line on the sites of MWH-Kokosing, Siemens, Trane and Linde, and no site for McDaniel's or Northstar. First published Nov. 21, 2026. We'll update this page when a new record or firm appears.

Porter Stanley

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.

More project reports

All project reports
Get all 22 firms, free

All 22 firms on the Intel Ohio chip plant

Enter your email and we will send it to you.

We send the list to this address, so use one you check. We never share it.