What is being built to replace the I-5 Interstate Bridge?
The I-5 Interstate Bridge carries I-5 over the Columbia River between Portland, Oregon and Vancouver, Washington. Its two spans date from 1917 and 1958. WSDOT and ODOT run a joint program to replace it.
The plan covers five miles of I-5. It adds new bridges over the Columbia, a new North Portland Harbor bridge, light rail from Portland to Vancouver with three stations, and rebuilt interchanges from Marine Drive to SR 500. The old bridge comes down. The program splits the work into 29 contract packages.
How much will the new I-5 bridge cost?
In March 2026 the program put the cost at $13.5 billion to $15.2 billion, with a likely cost of $14.4 billion. That is $7.8 billion of base cost plus $6.6 billion for inflation and risk. In 2022 the estimate was up to $7.5 billion.
The first core set of projects costs $7.65 billion, which leaves a funding gap of $1.2 billion to $2.2 billion. Federal grants include $1.5 billion from the Bridge Investment Program and $600 million from the Mega program. Critics use figures as high as $17 billion.
Who is bidding to build the new I-5 bridge?
WSDOT runs the first big contract, the Columbia River Bridge Replacement (XE3754), worth an estimated $3.3 billion to $3.9 billion. Only one team sent qualifications: Columbia River Constructors, a joint venture. Kiewit Infrastructure West Co. leads construction, with Guy F. Atkinson Construction and Traylor Bros. Kiewit Engineering Group leads the design.
On Nov. 12, 2026, WSDOT found the team's qualifications responsive and invited it to propose. The request for proposals posts Nov. 23, the proposal is due March 24, 2027, and a pick is expected about May 2027. Nothing is awarded yet.
Why is the single bidder a fight?
At a Nov. 16, 2026 joint legislative meeting, critics testified against the lone bidder. One said a single bidder puts the states in "an untenable bargaining position." News reports note that Kiewit also builds Oregon's I-205 Abernathy Bridge, which is more than two years behind schedule.
Separately, Iron Partners LLC has sued the Federal Highway Administration and related agencies to stop the project, saying they did not follow environmental and navigation laws. The case is pending.
Which firms have already worked on the I-5 bridge program?
WSP has been the general engineering consultant since 2020 and has been paid $260.3 million through June 2026. The final environmental study, from January 2026, names staff from WSP, Parametrix, Willamette CRA, Wolf Water Resources and ARG among its preparers.
In late 2023 and early 2024, Shannon & Wilson ran borings in the river's main channel, with Western States drilling from a barge. A new round of 16 borings runs from November 2026 to February 2027. Building is set to start in 2028, with opening about 2035.
Who WSDOT and ODOT hired before
Kiewit has led big bridge jobs for both state DOTs: WSDOT's SR 520 floating bridge and ODOT's Abernethy Bridge. Atkinson, also on this list, has led more than one stage of WSDOT's Puget Sound Gateway expressway work.
- Skanska (with AECOM as lead designer): design-builder on SR 520 Portage Bay Bridge and Roanoke Lid, about $1.4 billion, Seattle, WA, 2024.
- Guy F. Atkinson Construction (with Jacobs as designer): design-builder on SR 509 Stage 2 Completion Project, Puget Sound Gateway Program, $478.8 million, King County, WA, 2024. Also on this job.
- Kiewit Infrastructure West: builder on I-205 Abernethy Bridge, phase 1 of the I-205 Improvements Project, Oregon City and West Linn, OR, 2022 (notice of intent to award). Also on this job.
- Kiewit/General/Manson, A Joint Venture: design-builder on SR 520 Evergreen Point Floating Bridge, $586.5 million, the longest floating bridge in the world, Seattle to Medina, WA, 2011. Also on this job.
These are earlier or other jobs for the same owner. They are not counted in the 11 firms on this job.
How do the ways into the I-5 bridge replacement compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The team bidding the main bridge | A call to the firm's office, asking for the team on the I-5 bridge proposal | Every supplier, distributor and sales rep | A place in a $3.3 billion to $3.9 billion proposal before it is due | Not awarded yet; one team, with a pick about May 2027 |
| The program's consultants | A call to the engineering, geotechnical or environmental firm already on the program | Engineering, testing and survey firms | Work on the next study, boring or design package | Consultant work, not construction |
Who should go after the I-5 bridge replacement?
| Marine, steel and concrete suppliers | The main bridge team (Kiewit, Atkinson, Traylor) is pricing a $3.3 billion to $3.9 billion river crossing now, with its proposal due March 24, 2027. |
|---|
| Drilling, testing and survey firms | The geotechnical team (Shannon & Wilson, Western States) and 16 new river borings running to February 2027. |
|---|
| Engineering and environmental firms | The general engineering consultant (WSP) and the environmental study team (Parametrix, Willamette CRA, Wolf Water Resources, ARG). |
|---|
What should you do next on the I-5 bridge replacement?
- Pick the firms whose work matches what you sell, and call them this week.
- Ask for the team on the I-5 Interstate Bridge Replacement between Portland and Vancouver.
- Watch for the request for proposals on Nov. 23, 2026, the proposal due March 24, 2027, and the pick about May 2027.
Questions people ask about the I-5 bridge replacement
How much will the new I-5 bridge cost?
The program's likely cost is $14.4 billion for five miles of I-5, in a range of $13.5 billion to $15.2 billion (March 2026). In 2022 it said up to $7.5 billion. It is an estimate, not money spent. The main bridge contract alone is $3.3 billion to $3.9 billion.
Who is building the new I-5 bridge?
No builder is awarded yet. The only team invited to propose on the main bridge is Columbia River Constructors: Kiewit Infrastructure West, Guy F. Atkinson Construction and Traylor Bros., with Kiewit Engineering Group on design. WSDOT invited it on Nov. 12, 2026.
How many teams bid on the I-5 bridge?
One. Columbia River Constructors was the only team to send qualifications for the main bridge contract, by Sept. 30, 2026. Critics testified against the lone bidder at a joint legislative meeting on Nov. 16, 2026.
When will the main I-5 bridge contract be awarded?
The request for proposals posts Nov. 23, 2026, and the proposal is due March 24, 2027. A pick is expected about May 2027, with building from 2028.
When will the new I-5 bridge open?
The program's schedule points to opening about 2035, with building starting in 2028.
Who is paying for the I-5 bridge replacement?
Oregon, Washington and federal grants, including $1.5 billion from the Bridge Investment Program and $600 million from the Mega program. The first core set of projects costs $7.65 billion and still has a funding gap of $1.2 billion to $2.2 billion.
Which engineering firms work on the I-5 bridge program?
WSP is the general engineering consultant, paid $260.3 million through June 2026. Parametrix, Willamette CRA, Wolf Water Resources and ARG helped write the environmental study. Shannon & Wilson did the geotechnical work.
How can subcontractors get on the I-5 bridge replacement?
Call the firms on the one team bidding the main bridge, starting with Kiewit's Vancouver office, before its proposal is due March 24, 2027. The program has 29 contract packages, so more bids will follow.
Is there a lawsuit against the I-5 bridge?
Yes. Iron Partners LLC has sued the Federal Highway Administration and related agencies to stop the project, saying they did not follow environmental and navigation laws. The case is pending.
What happens next on the I-5 bridge replacement?
The request for proposals posts Nov. 23, 2026, with a proposer meeting Dec. 1. Sixteen new river borings run through February 2027. We'll update this page when a contract is awarded or a new firm appears.
How we built this list
We read the program's cost fact sheet and cost validation report, WSDOT's contract page, submitters list and short list letter for XE3754, the final environmental study's list of preparers, the program's spending dashboard, a 2024 draft geotechnical report released through a public records request, and news reports, all on Nov. 21, 2026. We kept each firm a public record names on this program. Four are on the one team invited to propose on the main bridge; none holds an awarded construction contract. Seven are consultants by their named roles: the general engineering consultant, the environmental study preparers and the 2024 geotechnical team. Contract values for the joint venture are for the whole team, not one firm's share. Left out: the owners (WSDOT, ODOT, TriMet, C-TRAN), the joint venture itself (its members are listed), a lawsuit plaintiff, firms that only attended an industry meeting, a firm doing upkeep on the old bridge, the 2012 test shaft firm for the cancelled earlier project, and two firms we could not reach through their own site (a barge operator and a utilities consultant). Phones are each firm's own line from its own site; Kiewit Engineering Group's is its Colorado office, and Traylor Bros., WSP and Wolf Water Resources show no main line on their sites. First published Nov. 21, 2026. We'll update this page when a contract is awarded, a filing lands or a firm appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 21, 2026- IBR Program: Program Cost and Funding fact sheet (March 17, 2026)
- IBR Program: Cost Estimate Validation Process report (2026)
- WSDOT: Columbia River Bridge Replacement, Contract XE3754
- WSDOT: XE3754 submitters list (Oct. 6, 2026)
- WSDOT: XE3754 short list letter (Nov. 12, 2026)
- IBR Program: Final Supplemental EIS, List of Preparers (Jan. 2026)
- IBR Program: accountability dashboard (through June 2026)
- IBR Program: draft geotechnical data report (May 2024, via public records request)
- The Columbian: One company seeks to build I-5 Bridge replacement (Nov. 16, 2026)
- OPB / Oregon Capital Chronicle: likely contractor's history of cost overruns (Nov. 18, 2026)
- The Center Square: critics on the single bidder and funding gaps (Nov. 18, 2026)
- Bridge Design & Engineering: Replacement bridge contract worth US$1.4 billion awarded in Seattle (2024-04-05)
- ENR: Atkinson-Jacobs Team Named for $479M Puget Sound Gateway Project (2024-06-04)
- ODOT Urban Mobility Office: ODOT selects construction contractor for I-205 Improvements Project (May 2022)
- ENR: Floating bridge replacement work under way near Seattle (2011)