What is the Jaguars' stadium furniture RFP?
The Jaguars' Work With Us page, updated Oct. 21, 2026, posts a request for proposals for furniture, fixtures and equipment supply. The Parker Company, the team's procurement agent, is receiving the proposals, and they're due Nov. 16, 2026.
It covers loose FF&E for the premium interiors and the general admission and operations areas, in 5 bid packages: seating, banquettes and sofas, casegoods, workstations, and waste receptacles. The seating is loose furniture, not the bowl's fixed stadium seats.
The page states no dollar value and no quantities, and the RFP exhibits come by request from the contact the page names. We found no news story on the request. The Parker Company is based in Miami, and the Jaguars' award list names it for procurement services.
What's being bought at the Jaguars' stadium, and when?
Construction began in February 2025. The city issued the joint venture the fourth and largest construction permit, $696.5 million of work, on Feb. 27, 2026. The Jax Daily Record lists new low-voltage systems in its scope, including a converged building network, Wi-Fi and DAS.
The Jax Daily Record listed 4 trade packages for that phase in October 2025, from metals, roofing and drywall to tile, paint, food service equipment, LED displays, paving and playing surfaces. Their bids were due between Nov. 11 and Dec. 2, 2025, and the winners aren't published.
- Nov. 16, 2026: Loose furniture, fixtures and equipment proposals are due to The Parker Company.
- First half of 2027: The team said roof installation will begin, on a canopy shell made from ViewScape.
- August 2028: The renovated stadium opens, and operations buying comes closer to then.
The furniture packages are the only work we found with a future bid date.
How do the ways into the Jaguars' stadium compare?
| Way in | What it is | Best for | What you get | The limit |
|---|
| The furniture RFP | The Parker Company is taking loose FF&E proposals in 5 packages, due Nov. 16, 2026 | Furniture dealers and manufacturers' reps | A proposal in front of the team's purchasing agent | Exhibits come by request, and no value or quantity is posted |
| The construction manager | The Hunt Construction-Barton Malow joint venture, which bids the trade packages | Trade contractors and suppliers | Prequalification and bid documents by request | The packages we found had bid dates in late 2025 that have passed |
| The owner's door | The Jaguars' Work With Us form and [email protected] | Any firm that wants future requests | Your interest on file with the owner's project manager | No future request has a date posted |
| Selling to a named firm | A call to a firm on the award list, like J.B. Coxwell or Colasanti South | Suppliers and lower-tier subs | A conversation with a firm already on the job | The list doesn't show what's already bought |
| Small business certification | The City of Jacksonville's small and emerging business office | Small local firms | The certification the Jaguars' page asks for | It isn't a bid invitation |
Who should go after the Jaguars' stadium, and who shouldn't?
| Contract furniture dealers and reps | Parker's 5 loose FF&E packages are due Nov. 16, 2026, for the premium, fan and staff areas. |
|---|
| Office furniture firms | One of the 5 packages is workstations, for the stadium's operations areas. |
|---|
| Concrete, pipe and site suppliers | Colasanti South and J.B. Coxwell are named on the record, with company lines. |
|---|
| Firms that need a construction bid date | This isn't the job for you yet: the trade package dates we found passed in late 2025. |
|---|
What should you do next on the Jaguars' stadium?
- Request the RFP exhibits from The Parker Company through the Jaguars' Work With Us page before Nov. 16, 2026.
- Certify with the city's small and emerging business office and fill out the Work With Us form.
- Call the trade firms named on the record if you sell to concrete, plumbing, electrical or site work.
- Open the full list and find the firm named for your trade.
Questions people ask about the Jaguars' Stadium of the Future
Who is building the Jaguars' Stadium of the Future?
The Jaguars list AECOM Hunt and Barton Malow as construction manager, and the Jax Daily Record reports the contractor as a Hunt Construction-Barton Malow joint venture. HOK is the architect.
Who is the general contractor on the Jaguars' stadium renovation?
The Hunt Construction-Barton Malow joint venture, as construction manager. The city issued it the fourth and largest construction permit, $696.5 million of work, on Feb. 27, 2026.
How much does the Jaguars' stadium renovation cost?
$1.4 billion, with $775 million from the city and $625 million from the team, as the Jax Daily Record reported. The team's president told the paper it will go over $1.4 billion.
When does the Jaguars' stadium reopen?
The Jaguars say the Stadium of the Future opens in August 2028. The team plays its 2027 home games at Camping World Stadium in Orlando.
Is anything on the Jaguars' stadium open for bids?
Yes, one thing with a stated date. The Parker Company is taking proposals for loose furniture, fixtures and equipment in 5 packages, due Nov. 16, 2026. The construction trade packages we found had bid dates in November and December 2025, and those have passed.
What's in the Jaguars' furniture RFP?
5 packages of loose FF&E: seating, banquettes and sofas, casegoods, workstations, and waste receptacles, for the premium interiors and the general admission and operations areas. The page states no value and no quantities, and the exhibits come by request.
How do subcontractors and vendors get on the Jaguars' stadium?
Furniture firms send proposals to The Parker Company by Nov. 16, 2026. Trade firms go through the construction manager. The Jaguars' Work With Us page takes interest through a form and [email protected], and asks firms to certify with the city's small and emerging business office.
Who owns EverBank Stadium?
The City of Jacksonville owns the stadium and its parking lots, and Legends Global manages and maintains it for the city. The Jaguars are a tenant, and Jax Stadium, LLC is the development entity in the 2024 ordinance.
How big will the renovated stadium be?
The Jaguars give a base capacity of more than 63,000, expandable to more than 70,000, with 360-degree concourses and a transparent shell the team says cuts heat retention by 70% or more.
Who are the trade firms already on the Jaguars' stadium?
The Jaguars' award list names Campbell Plumbing, Miller Electric, Independence, Keller, Birken, J.B. Coxwell and Colasanti. The team's page and JEA's record name more, including W&W AFCO Steel and Alpha Insulation & Waterproofing.
What are the risks of chasing the Jaguars' stadium?
The furniture packages state no value or quantity, and Parker may already have suppliers it buys from. The winners of the late-2025 trade packages aren't published, so some trades are already bought.
What happens next at the Jaguars' stadium?
Furniture proposals are due Nov. 16, 2026. The team said roof installation begins in the first half of 2027, and the stadium opens in August 2028.
How we built this list
We read the Jaguars' Stadium of the Future pages, including the Work With Us page's awarded lists and its small-business features, the team's FAQ, JEA's Nov. 6, 2025 awards record, the city's 2024 stadium ordinance, a city permit on the site, HOK's news page and Jax Daily Record coverage. A row is on the list only if a record ties it to the stadium or its site. We don't add permit values together, and no figure here is a furniture value, because none is stated. A row with a passed bid date says so, and only the 5 furniture packages have a future date. First published Nov. 8, 2026. We'll update this page when a new permit, firm or bid date appears.

Porter Stanley is the founder of American Trades Index, which tracks new commercial construction projects and who's on them.
Sources, checked Nov. 8, 2026- Jacksonville Jaguars, Work With Us
- Jacksonville Jaguars, Stadium of the Future
- Jacksonville Jaguars, Stadium of the Future FAQs
- HOK, March 2026
- Jax Daily Record, Oct. 7, 2025
- Jax Daily Record, March 1, 2026
- Jax Daily Record, Aug. 14, 2026
- JEA, awards agenda, Nov. 6, 2025
- Jacksonville City Council, Ordinance 2024-0904-E
- The Parker Company